Welcome, Guest: Register On Nairaland / LOGIN! / Trending / Recent / New
Stats: 3,148,681 members, 7,801,963 topics. Date: Friday, 19 April 2024 at 07:04 AM

Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt - Properties (3) - Nairaland

Nairaland Forum / Nairaland / General / Properties / Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt (14947 Views)

Another Two-storey Building Collapses In Lagos / Victims Of The Collapsed Three-Storey Building In Lagos (Photos) / Three Storey Building Collapses At Ilasa, Lagos (Photos, Video) (2) (3) (4)

(1) (2) (3) (4) (Reply) (Go Down)

Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by erico2k2(m): 2:18pm On Oct 25, 2015
odiereke:
My email add is mikkydele@yahoo.co.uk
Bro U said u r based in choba abi? waht other stufff have u gt 4 hire? mixers?
Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by malkomx(m): 10:09am On Oct 26, 2015
erico2k2:

OK I will be doing same at Obiakpor not far from the East west fly over,December, your mixer and poker how much did it cost for a day's rental? and how much was the cost of labour per persons during the blinding?
erico2k2, the both equipment are mine but you could get a mixer in PH at about 15k per day while the poker goes for 10k per day.... operator pay inclusive.
Labour in this type of concrete work goes for 800naira per every bag of cement used... it's better paying per bag as it's puts seriousness into the workmen
Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by malkomx(m): 10:12am On Oct 26, 2015
odiereke:
Nice Job my broda, am really following up with your project. Am a civil Engineer too, based in Port around Choba Uniport area. I think I may be of assistance to you and your project in so many area. I have almost all civil equipments for hire. I may give you a call later to have a chat with you. Thanks keep the good works up my broda.
Odiereke thanks for the interest
Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by malkomx(m): 10:14am On Oct 26, 2015
smiley001:
Neat Job.
This is another thread to follow.

Weldone Boss.
welcome on board sir
Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by malkomx(m): 10:26am On Oct 26, 2015
While block work is ongoing in the trenches... I have marked out my 12x18 soak-away pit.
I want to use laterite dug out o this pit for my filling instead of importing laterite to the site

Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by malkomx(m): 10:28am On Oct 26, 2015
And we have proceeded with the excavation of the pit

Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by erico2k2(m): 11:58pm On Oct 27, 2015
malkomx:

erico2k2, the both equipment are mine but you could get a mixer in PH at about 15k per day while the poker goes for 10k per day.... operator pay inclusive.
Labour in this type of concrete work goes for 800naira per every bag of cement used... it's better paying per bag as it's puts seriousness into the workmen
thanks a lot
Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by malkomx(m): 11:46am On Oct 28, 2015
I must confess... this is good idea doing this excavation at this time. See sand for filling at my finger tip. Due to the highly compacted nature of this soil formation, the volume of sand that comes out of every cubic meter dug is far above one cubic meter..... "This ground dey vomit sand o" that's how my boy describes this scenario.
Bottom line is we will have more than enough sand for filling and save me some good money wink

Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by erico2k2(m): 5:14pm On Oct 28, 2015
malkomx:
I must confess... this is good idea doing this excavation at this time. See sand for filling at my finger tip. Due to the highly compacted nature of this soil formation, the volume of sand that comes out of every cubic meter dug is far above one cubic meter..... "This ground dey vomit sand o" that's how my boy describes this scenario.
Bottom line is we will have more than enough sand for filling and save me some good money wink
Good idea to save cost of materials

1 Like

Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by malkomx(m): 6:03pm On Oct 29, 2015
Next stage: filling.
We are getting there!

Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by Ericengineering: 5:21pm On Oct 30, 2015
malkomx:
Next stage: filling.
We are getting there!
nice layout. You got speed too. It's interesting seeing how a house is built.
Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by X2X(m): 12:57am On Oct 31, 2015
malkomx:
Next stage: filling.
We are getting there!

Well done.
Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by malkomx(m): 2:22pm On Nov 02, 2015
Soak away excavation: completed
filling/compaction: 90% completed
carpentry form work for ground floor completed with adequate braces.
90% prepped for casting ground floor slab

Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by malkomx(m): 2:28pm On Nov 02, 2015
Pending little plumbing works... concrete works for tomorrow

Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by malkomx(m): 2:18pm On Nov 03, 2015
Operations... ground floor slab

Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by malkomx(m): 11:05am On Nov 04, 2015
Curing our slab

Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by malkomx(m): 2:11pm On Nov 05, 2015
Block work

Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by malkomx(m): 2:16pm On Nov 05, 2015
While works @soak-away continues

Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by malkomx(m): 9:04am On Nov 06, 2015
Hitting lintel level right round

Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by malkomx(m): 9:05am On Nov 06, 2015
And casting footing for soak-away walls

Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by X2X(m): 12:53pm On Nov 06, 2015
Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by malkomx(m): 2:20pm On Nov 07, 2015
X2X:


I thought there is need for some kind of damp proofing membrane?
nice observation. The membrane was skipped because this site is on a hilltop.
Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by malkomx(m): 2:23pm On Nov 07, 2015
Carpentry@lintel

Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by malkomx(m): 2:24pm On Nov 07, 2015
Blockwork@soak-away

Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by malkomx(m): 2:45pm On Nov 09, 2015
Work continues on lintel columns and arches.... reinforced concrete

Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by malkomx(m): 2:48pm On Nov 09, 2015
Soak-away and septic tank walls to be strengthened midway by a reinforced concrete beam right round.
My carpenter on it!

Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by malkomx(m): 8:44am On Nov 16, 2015
Blockwork has been levelled.
Carpentry @first suspended floor commenced

Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by malkomx(m): 8:48am On Nov 16, 2015
Soak-away/septic tank work progress

Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by malkomx(m): 4:48pm On Nov 20, 2015
Rebar works on

1 Share

Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by malkomx(m): 5:10pm On Nov 20, 2015
@soak away included

Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by odiereke(m): 7:56am On Nov 24, 2015
erico2k2:

Bro U said u r based in choba abi? waht other stufff have u gt 4 hire? mixers?
Yes I stayed in Choba, Port Harcourt.
I have stuffs like Poker, vibrating table, Scaffolding, Electric Jack Hammer, Air Compressor Jack Hammer and other things. Just let me know what you need. My email is mikkydele@yahoo.co.uk or whatsapp me on 08022447715, 08039279878.
Re: Developing A Two-storey Building (6nos 2-bedroom Flats) in Portharcourt by odiereke(m): 8:02am On Nov 24, 2015
quote author=sako28 post=39335034]

Drop your email then we discuss more.

thanks[/quote]
My email address is mikkydele@yahoo.co.uk
Just saw your post now sorry for the delay.

(1) (2) (3) (4) (Reply)

For Your Electrical & Plumbing Installation Services(Email or Call Us) / Five Reasons Why Investing In Real Estate Is Better Than Saving In The Bank / I Need Estimate For Fencing 50ft X 100ft Or 460sqm Plot Of Land

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 25
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.