Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 6:16pm On Sep 05, 2017 |
Pics |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 6:36pm On Sep 09, 2017 |
Iron work |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 6:39pm On Sep 09, 2017 |
Suckaway almost completed |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 6:40pm On Sep 09, 2017 |
. |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 6:41pm On Sep 09, 2017 |
Keep they calls coming 2348035425917 |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 9:55pm On Sep 12, 2017 |
Still on deck |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by Babs612000(m): 1:55am On Sep 13, 2017 |
oscarnoble: Suckaway almost completed Please what is the size of this suck-away and how much is the digging. |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 5:30pm On Sep 13, 2017 |
Babs612000:
Please what is the size of this suck-away and how much is the digging. they measurement is 7 by 14ft.. They charged me n30,000 for the digging 1 Like |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 5:43pm On Sep 13, 2017 |
Plastering of the suckaway |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 5:45pm On Sep 13, 2017 |
Suckaway decked |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 5:47pm On Sep 13, 2017 |
Still on they final decking |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 5:49pm On Sep 13, 2017 |
. |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by nwoye72: 7:45pm On Sep 13, 2017 |
NWanne how many bags of cement and tones of granet u used on the first decking thanks 1 Like |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 7:00am On Sep 14, 2017 |
More |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 1:10pm On Sep 15, 2017 |
Still moving |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 1:11pm On Sep 15, 2017 |
. |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 1:17pm On Sep 15, 2017 |
LETS DESIGN AND HANDLE YOUR BUILDING PROJECT CALL US +2348035425917
Nobos construction We are the leading company in building design and construction...
we offer the following service
1) Building design (* Architectural * Structural * Electrical* Mechanical plan)
2) Building construction
3) Real estate |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 5:24pm On Sep 16, 2017 |
Suckaway |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 5:25pm On Sep 16, 2017 |
Iron work done |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by yak(m): 9:41am On Sep 18, 2017 |
oscarnoble: Suckaway is this the only soak away for the entire building? |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 6:44pm On Sep 18, 2017 |
yak:
is this the only soak away for the entire building? no sir still going to erect more one |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by yak(m): 7:28pm On Sep 18, 2017 |
we are following sir |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 8:40pm On Sep 18, 2017 |
yak: we are following sir thank u sir |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 8:46pm On Sep 18, 2017 |
Boarding of they deck, ready for casting |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 9:49pm On Sep 20, 2017 |
Done with they carpentry and iron work of the last deck.. I am having delays in bringing materials for the casting 1 Like |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 9:22pm On Sep 25, 2017 |
I started casting today ,,all thanks to God |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 9:27pm On Sep 25, 2017 |
Pics |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 9:24pm On Sep 26, 2017 |
One flat was completed |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 4:13pm On Sep 29, 2017 |
Second deck completed |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 4:14pm On Sep 29, 2017 |
More |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 4:16pm On Sep 29, 2017 |
Still nobos construction Call us on +2348035425917 |
Re: Construction Of 2 Bedroom Block Of 6 Flats In Owerri,imo State by oscarnoble(m): 7:18am On Oct 01, 2017 |
Waiting for the deck to dry up a little b4 work commence |