Welcome, Guest: Register On Nairaland / LOGIN! / Trending / Recent / NewStats: 3,149,803 members, 7,806,243 topics. Date: Tuesday, 23 April 2024 at 01:28 PM |
Nairaland Forum / Nairaland / General / Politics / 434MW Geregu Power Plant To Begin Power Generation This Week (15330 Views)
Fg Picks Geregu, Itu As 2,400mw Nuclear Power Sites / Jonathan Commissions Geregu-II Power Station / 434 MW Geregu 11 Power-plant Completed (2) (3) (4)
(1) (2) (3) (4) (5) (6) (7) (Reply) (Go Down)
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by Demdem(m): 5:03pm On Jan 09, 2013 |
ocelot2006: OBJ wasted time before he commenced work on NIPP. he unfortunately had other priorities. The NIPP didnt commence until 2003 and not 1999 when he became President. so its wrong for peeps to give an impression that OBJ sat on NIPP for 8yrs. thats simply not true. Kindly read the below. http://www.fig.net/pub/fig2010/papers/fs04g/fs04g_ehiorobo_4258.pdf |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by Touchforfree(m): 6:17pm On Jan 09, 2013 |
Chei ! n na how I go do am now !; I get 60 containers full of generators imported from Germany on top of d sea coming in into d country. I beg pray make we dey use all d turbines pump water for our houses oooooo. |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by Nobody: 6:38pm On Jan 09, 2013 |
Sincere 9gerian: All these infrastructure being built here and there should be secured because the HATERS and PAY-AS-YOU-GO critics, both fearing lose of relevance and source of income, can sponsor or personally vandalize those infrastructure. Oga mi, may your days be long and fruitful. |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by Arogba: 6:42pm On Jan 09, 2013 |
SCAMMMMM! The site of this power plant is located within 2km of Ajaokuta steel company, This project was initiated and completed by the Obj administration. The only problem with the plant was gas supply because the existing gas pipeline supplying Ajaokuta steel company was also meant to supply the power plant but after the completion of the project it was discovered that the pipeline had been vandalized since the steel company itself has never really worked. |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by Arogba: 7:00pm On Jan 09, 2013 |
Demdem: To those who delight in distorting facts. U can also read this to understand the careful planning of the OBJ's admin on power plants location. Right on point! |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by awodman: 8:16pm On Jan 09, 2013 |
gbadexy:I see U̶̲̥̅̊ got a comprehension problem...NIPP CAPACITY WOULD HIT 4264MW..not d whole of the nation's capacity |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by Nobody: 10:52pm On Jan 09, 2013 |
What could be more hypocritical than the same mischief makers, who accuse GEJ of not doing much in his less than 2yrs tenure now expecting us to shower praises on OBJ for bequeting us with uncompleted projects after 8 SOLID years at the helm of affairs. At the moment, there are more than 17,000 abandoned/uncompleted federal govt projects, littered nationwide. How come we have this much abandoned projects, considering the fact that many of our past leaders had ENOUGH TIME to conceive, commence and complete projects. OBJ had 8 SOLID and STABLE years to perform. Abacha had about 5yrs to make an impact. IBB had 8 SOLID and fairly STABLE years to do whatever he wanted. How come the over 17,000 abandoned and uncompleted projects? To add insult to injury some persons expect us to sing praises of OBJ for bequeting us with his own set of abandoned and uncompleted projects, after 8yrs in power? SMH! Supposing the president that took over from OBJ didn't believe in the project or didn't give it the seriousness it deserves, then the projects may have been left to rot away after billions of dollars have been expended. We should also give the credit for the ongoing construction of Lagos metro line to Jakande, who conceived the idea, did the feasibility studies and reached financial closure on the project and would have completed the project in the mid 80's if he were not sacked by Buhari and his gang 2 Likes |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by jmaine: 11:20pm On Jan 09, 2013 |
Sincere 9gerian: What could be more hypocritical than the same mischief makers, who accuse GEJ of not doing much in his less than 2yrs tenure now expecting us to shower praises on OBJ for bequeting us with uncompleted projects after 8 SOLID years at the helm of affairs. At the moment, there are more than 17,000 abandoned/uncompleted federal govt projects, littered nationwide. How come we have this much abandoned projects, considering the fact that many of our past leaders had ENOUGH TIME to conceive, commence and complete projects. OBJ had 8 SOLID and STABLE years to perform. Abacha had about 5yrs to make an impact. IBB had 8 SOLID and fairly STABLE years to do whatever he wanted. How come the over 17,000 abandoned and uncompleted projects? Take it easy on their repugnant souls . . . . . |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by Jeboy(m): 12:06am On Jan 10, 2013 |
Some peeps have sworn with their soul that they will never acknowledge any success recorded by GEJ even if it is to National Development.My prayers to them is May they not eat out of the good thereof. Somebody spent 8 yrs in power, you gave enough reasons why he may not complete projects. Another haven't spent 2 yrs complete and you have finalised he is slow,daft and not doing enough.God is watching yoy,you know yourselves. |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by delvinmaya(m): 1:29am On Jan 10, 2013 |
Tusky44: Seems like you are the one deluded here. Why don't you attempt dissolving your father's house? |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by fkaz(m): 1:40am On Jan 10, 2013 |
Arogba: SCAMMMMM! The site of this power plant is located within 2km of Ajaokuta steel company, This project was initiated and completed by the Obj administration. The only problem with the plant was gas supply because the existing gas pipeline supplying Ajaokuta steel company was also meant to supply the power plant but after the completion of the project it was discovered that the pipeline had been vandalized since the steel company itself has never really worked.Fact, those passing kogi to eastern state should known the truth. This project is by the roadside, it has been there b4 jonathan came in as vice president. |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by EkoIle1: 2:09am On Jan 10, 2013 |
Sincere 9gerian: What could be more hypocritical than the same mischief makers, who accuse GEJ of not doing much in his less than 2yrs tenure now expecting us to shower praises on OBJ for bequeting us with uncompleted projects after 8 SOLID years at the helm of affairs. At the moment, there are more than 17,000 abandoned/uncompleted federal govt projects, littered nationwide. How come we have this much abandoned projects, considering the fact that many of our past leaders had ENOUGH TIME to conceive, commence and complete projects. OBJ had 8 SOLID and STABLE years to perform. Abacha had about 5yrs to make an impact. IBB had 8 SOLID and fairly STABLE years to do whatever he wanted. How come the over 17,000 abandoned and uncompleted projects? The same project you are still badmouthing and labeling ACN propaganda? Look here, you are not only expected to continue and finish ongoing projects initiated and started before you, that's your damn job and you ate expected to do that minimum. The problem with your Aso Rock uncle is simply that he has no vision, no initiative or idea of his own, he's so dumb, clueless and vacuous that the only idea and initiatives he has remains illiterate cassava bread idea, buying and collecting dozens of presidential cars, 10 presidential planes with N9 billion/year maintenance bill at the door steps of the taxpayers, N1 billion food bill and commissioning phony and 419 e library. Can't wait to see your clowns back in your swamps down south come 2015. |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by Demdem(m): 7:38am On Jan 10, 2013 |
Arogba: SCAMMMMM! The site of this power plant is located within 2km of Ajaokuta steel company, This project was initiated and completed by the Obj administration. The only problem with the plant was gas supply because the existing gas pipeline supplying Ajaokuta steel company was also meant to supply the power plant but after the completion of the project it was discovered that the pipeline had been vandalized since the steel company itself has never really worked. Right on point. Exactly what happened. On two different occasions years ago i has reasons to visit the steel complex power station and right before u enter Ajaokuta, the power plant is situated |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by Jeboy(m): 8:03am On Jan 10, 2013 |
My very good question to you guyz doing like good historians is why do u curse dis man for problems he inherited from past predecessors which he hasn't proferred solution for but u think its wrong to give him credit for the reverse? Simple Answer: Badbelleism |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by jmaine: 8:05am On Jan 10, 2013 |
People feel it's wisdom for Obj to have built power plants without cogent provisions and plans for gas supply needed to power them ..na talk be that ? The other guy (GEJ) comes in, and rectifies that major flaw and yet peeps feel he doesn't deserve a mention . . . No one can rob GEJ efforts in ensuring the NIPPs fire on as expected The nation has been bedeviled more with mega-excuses rather than the promised megawatts; why? http://www.thisdaylive.com/articles/nnaji-we-are-implementing-key-pillars-of-power-reform/117760/ ^^ Prof Barth Nnaji speaking . . . . . |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by Demdem(m): 8:12am On Jan 10, 2013 |
Demdem: Again, i salute the OBJ admin for initiating and commencing this project 2) The Geregu plant was located (BY OBJ) less than eight kilometres from the existing Pipeline that takes gas to the Ajaokuta Steel plant. |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by jmaine: 8:22am On Jan 10, 2013 |
Jeboy: My very good question to you guyz doing like good historians is why do u curse dis man for problems he inherited from past predecessors which he hasn't proferred solution for but u think its wrong to give him credit for the reverse? They are under an oath of secrecy to criticize anything GEJ . . .It could be so frustrating to whine,wail, and gnash their teeth with no tangible results emanating from their bile . . . . |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by jpphilips(m): 10:32am On Jan 10, 2013 |
Demdem: Again, i salute the OBJ admin for initiating and commencing this project Thank you for recognizing that NIPP was OBJ's brain child and he is the reason we are close to having steady electricity. during my tour of the NIPP i knew this day will come, not long ago, i visited yaba left to send relief materials to the inmates, i ran into a desperate man called Gen Buhari. he told me that OBJ embezzled all the NIPP funds without a single block on the ground. all efforts to convince him otherwise with proofs of the ones ive seen myself proved abortive. excerpts our discussion. [url]https://www.nairaland.com/1134045/obasanjo-cant-stop-criticizing-jonathan/6 [/url] |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by jpphilips(m): 10:39am On Jan 10, 2013 |
duality: I still don't understand this. I know Geregu to have an installed capacity of 414 mw.(gt1, gt 2 and gt3) although geregu operates as an island, it has its own challenges hence, it has never worked at installed capacity nor was it connected to the grid. however a phase 2 of the project was proposed. gregu was planned to have a total installed capacity of 4 gas turbines firing a total of 434mw, however only the first phase has been completed which is the turbine one and gas supply infrastructures, that alone delivers 134mw, subsequently as other turbines come on stream, 434mw can be achieved. |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by Demdem(m): 10:45am On Jan 10, 2013 |
jp philips: Genbuhari is a nutcase no doubt. Only the very foolish will say otherwise as regards NIPP. Infact its interesting to note that this Geregu plant in question has since been commisioned by OBJ as far back as 2007. Availability of gas has always been one of the main challenge. |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by jpphilips(m): 10:47am On Jan 10, 2013 |
jmaine: I totally agree with you that Egbin project was not an NIPP project, however, the NIPP has a contract for an infrastructural upgrade for Egbin. the upgrade guaranteed that Egbin fires at 1,320mw for the six 220mw installed turbines. |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by Demdem(m): 10:51am On Jan 10, 2013 |
jp philips, kindly permit me to bring forward ur past post as regards this topic. Its relevant here. thanks. jp philips: [color=#000099]@ GEN BUHARI 1 Like |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by jpphilips(m): 11:09am On Jan 10, 2013 |
tunalism: GEJ has really done an onerous nd breathtaking jobs when it comes to the power sector transformation agenda. I said this becos I have seen improvements in my area since the past one mnth. So, let's give it up to the man. More power to Get yourselves a pair of glasses before you go blind, the fact that electricity improved in your hood may not be GEJ's doing, it might be an Alaye who removed a fuse from your transformer or the transformer being bad. OBJ just like chukwuma soludo, sat thought and came up with the banger NIPP, strategically located to reflect source of raw material and capacity oriented to reflect population of a particular area. OBJ funded it in part before he left, the same GEJ you want to give credit to cannot even get credible people to run its administration, from an erudite Nnaji to a vacant padi padi office, is that what you term an achievement? Ok, since OBJ has come out with the grand plan of improving electricity generation, is it a crime for jona to come up with a grand plan for distribution as well?, so that people like me can as well give him his due credits. to even sell (aka privatize) the ones built for him is a problem, from Manitoba winning bid to manitoba not winning to Nest oil a servicing company who has constructed pipelines all their lives winning discos, if you cant see jonathan's confusion in the power sector then im afraid you need more than glasses. |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by jpphilips(m): 11:49am On Jan 10, 2013 |
jmaine: yaradua saw a massive corruption in the scheme but not unreluctant to fund it, he just wanted a clearer picture and know where he will tie his interests as new head of state since OBJ has left. at the time, the elumelu panel was constituted and elumelu went to the site, saw work in progress (though not without challenges)but demanded for bribe from the contractors, when they refused, he released a report claiming that nothing was on ground. Yaradua then halted the scheme temporarily. the Contractors fought back by releasing their different challenges which another committee was set up to address them, towards the demise of yaradua, the projects kicked off again. Take for example, when elumelu got to one of those sites, the base structures have all been done but the turbine couldn't be installed cos the reinforcement on a cross bridge could not support the weight of both the turbine and flat beds,as calculated by the structural engineers hired by the contractor. faced with that, the contractor applied for a contract variation to accommodate the structural reinforcement of the bridge so the turbine can pass of course, that wasn't part of their initial contract. the contractor pleaded with him to personally take him with his entourage across the river to see the turbine which he declined on safety grounds. he went ahead in the report to claim that the contractor has squandered the money given to him to purchase the turbine, meanwhile the turbine was already in Nigeria. the customs didn't help matters at the time, there was a time a lot of refinery accessories and NIPP equipments imported in the country were confiscated and Auctioned by the customs, the reason behind that and whether the FG was aware remains unclear till date. funding; some of the contractors were owed for a long period and most of their project assets were confiscated by banks in a bid to recover their money. i believe that a cumulative of all those challenges has poised yaradua to stall the projects at the time. |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by jpphilips(m): 1:14pm On Jan 10, 2013 |
Demdem: point of correction, there has been power spending from 1999 however, the NIPP was inaugurated in 2003. most of the projects that were funded before the NIPP are equally referred to as NIPP projects an example is the AES barge project in egbin which was completed in 2001,firing about 270mw, funding was released around 99 or so, but today we include AES as part of the NIPP, this is so because the NIPP master plan not only covered generation plants but also distribution and upgrade for existing ones. |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by Olaolufred(m): 1:30pm On Jan 10, 2013 |
jmaine: People feel it's wisdom for Obj to have built power plants without cogent provisions and plans for gas supply needed to power them ..na talk be that ? While it is good to note that GEJ is on track based on the developments in power sector, It does not also erase the fact that OBJ Initiated it, and worked more on the construction and installation of those power stations. Now that Goodluck through Barth Nnaji discovered some planning errors, The common sense is to rectify it. That is the essence of a visional govt. I will commend them for the progress so far(though they could do better) But I will not thank them for doing what they are paid to do. |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by jpphilips(m): 2:05pm On Jan 10, 2013 |
jmaine: People feel it's wisdom for Obj to have built power plants without cogent provisions and plans for gas supply needed to power them ..na talk be that ? i don't know if you are from Zimbabwe, Geregu power plant that i know was commissioned in 2007, it fired for a while and stopped due to gas challenges, in 2007 was the year obasanjo left office, he didn't even have the time to fix the problem, then came yaradua who elumelu deceived that the scheme was a scam because he was looking for kick backs, yaradua eventually stalled the scheme. prof bart Nnaji did a quick review and saw the strategic relevance of the project and advised Jonathan to revisit which he obliged, today, the gas issue has been solved and turbine one has come on stream remaining turbine 2 to 4 (meaning that jonathan did not add anything to what obasanjo left in 2007) let us be guided accordingly, the project has been commissioned since 2007, if i am to praise the actors, should i praise the man who thought about it, funded, constructed and commissioned it OR the man who addressed a challenge in his work, who should take the credit, gentlemen, Jonathan is doing a great dis service to this nation, believe me, if NNaji had continued, He could have come up with a grand plan that will glorify the Jonathan's administration in the power sector. |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by jmaine: 2:14pm On Jan 10, 2013 |
Double Post |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by jmaine: 2:14pm On Jan 10, 2013 |
jp philips: All said and done . . . .It's still irrefutable that Yar Adua stalled this project for 2.5 years, which not surprising coincides with his tenure as the President . . 2.5 years of delay is a huge dent to a massive project of this magnitude . . . . The GEJ you seek to vilify ,immediately after coming on board decided to vigorously pursue the implementation of Electricity Power Sector Reform Act of 2005, then considered and awarded contracts for the outstanding jobs while renewing the tenure of consultants. They also decided that only major turbine manufacturers would be allowed to bid for the power projects ( Though a setback was recorded here). GEJ implemented a cost reflective tariff in place to encourage the gas producers to supply more gas and reduce the friction of costing they had with PHCN due to their accumulating debt profile, also ensuring the power plants with deficit of a gas supply provision were revisited to clear that important huddle OBJ did his part by laying a good frame work which is undeniable . .but again, you must commend this admin for vigorously ensuring that OBJ commendable power reforms plan was continued with relevant policies (e.g the tariff pricing to encourage gas supply) put in place to ensure all set backs are limited . . . . |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by jmaine: 2:20pm On Jan 10, 2013 |
jp philips: Whatever you chose to say does not in any way invalidates GEJ efforts in revamping the power sector . . .Barth or No Barth . . .the reforms are going on . . . So what's the stress . . . . P:S ===> There is no point throwing stealth jabs . .let's keep this civil . . . |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by jmaine: 2:29pm On Jan 10, 2013 |
Olaolufred: No one is denying OBJ initiated them, no one is denying OBJ his due accolades for conceiving them even though suspicion arose on inflated contracts . . . but what we seek to address here are peeps telling us this admin had no inputs whatsoever in the current schemes of things . . . . .it's as simple as that . . . |
Re: 434MW Geregu Power Plant To Begin Power Generation This Week by Demdem(m): 2:31pm On Jan 10, 2013 |
jp philips: Yea thanks for the correction. I agree with that. |
(1) (2) (3) (4) (5) (6) (7) (Reply)
Nigerians Too Ignorant Of President Buhari's Achievements - Garba Shehu / Certificate Scandals Threaten 2019 Dreams / Buhari Campaign Organisation Reports Atiku To EU, AU Over ‘undemocratic Tendenci
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 126 |