Welcome, Guest: Register On Nairaland / LOGIN! / Trending / Recent / NewStats: 3,215,619 members, 8,026,539 topics. Date: Wednesday, 11 December 2024 at 05:58 PM |
Nairaland Forum / Nairaland / General / Properties / Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) (18617 Views)
Luxurious 5 Bedroom Duplex, Fully Serviced With A Pent Floor / Construction Of A Four Bedroom Bungalow With A Pent / 3 Bed Room Flat With A Pent House, 2 Units Of A Room Self Contain. #20m (2) (3) (4)
(1) (2) (3) (4) (Reply) (Go Down)
Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by abdulwastecx(m): 4:09pm On Oct 27, 2017 |
Harney project structure brings to you the construction of this beautiful five bedroom duplex with a penthouse. The building is going to be sitting on a 450sqm of land (15m x 30m) Duration of project: unknown construction team: Harney project Location of project: Guzape, Asokoro extension Abuja 2 Likes |
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by abdulwastecx(m): 4:20pm On Oct 27, 2017 |
Starting with excavation check on the already excavated foundation: The foundation was excavated to the required depth by the estate responsible for setting out, but checks were carried out to verify the depth and width specified by the estate. The design provides the following foundation information; 1. width of the strip footings is 675mm and depth of not less than 1000mm 2. The width of the isolated pad footing were 1500 x 1500 and depth of not less than 1200mm 3. The width of the combined footings were 1750 x 1500 and depth of not less than 1200mm 4. There were 14 isolated pad base footings and 3 combined base footings. The excavation was checked and all adequate corrections were made to suit our work plan before commencement of blinding and subsequently placing of reinforcement |
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by abdulwastecx(m): 4:38pm On Oct 27, 2017 |
Placement of foundation pad footings and columns starting bar: The reinforcement for the pad footings is 16mm. The main reinforcement for the starting bar is Y16 (16mm in diameter) while the stirrup or ring is Y10 (10mm in diameter). The spacing for the isolated pad base is 200mm center to center only at the bottom of the pad base (after placement of concrete cover) The combined footings are reinforced with both bottom and top reinforcement all spaced at 175mm c/c. The columns are made up of 4 vertical bars (as the main bars) and rings spaced at 200mm c/c at regular intervals, leaving an allowance of 1000m ontop for continuation columns. 2 Likes 1 Share
|
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by abdulwastecx(m): 4:49pm On Oct 27, 2017 |
Preparation for the casting of the foundation: For this foundation, we have the following concreting information 1. Concrete anticipated strength: M25 ( strength of 25/mm2 after 21days) 2. Depth of pad footing is 450mm 3. Size of the coarse aggregates ( gravel/granite) is 19.5mm 4. Sharp sand free clay and dust 5. very sharp stone dust 6. Concrete mixer 7. Poker vibrating machine Batching method, we batch using 7 portions of granite, 2 portions of stone dust and 2 portions of sharp sand for one bag of cement water to cement ratio of 0.55
|
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by abdulwastecx(m): 4:58pm On Oct 27, 2017 |
More updates
|
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by uboma(m): 9:41pm On Oct 27, 2017 |
I am following with keen interest. 2 Likes |
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by abdulwastecx(m): 10:59pm On Oct 27, 2017 |
Completion of foundation footing concreting: The following observation can be made 1. the concrete mix is not too watering: we batch based on a water-cement ratio) to enable us to have adequate workability without compromising the concrete strength, because too much water will render our concrete weaker while too little water will make our concrete not workable (workability is the ease at which concrete flow when poured into form) 2.It can be observed that adequate vibration of the concrete was carried out to expel air burble from the voids of the aggregates in other to have a more consistent concrete 3. It can be seen that the mix is rich in cement and other constituent aggregates in their correct proportions 4. The anchorage of the starter bar to the basket is adequate ( about 450mm ) in other transfer loads from the column to the foundation footings adequately 5. starter columns are positioned at the center of the footing to have zero eccentricity 1 Like |
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by abdulwastecx(m): 11:09pm On Oct 27, 2017 |
Preparation and setting of foundation block wall: The foundation will be built in three different stages due to the topography of the site. The site slope from back to the front with such differences in level gotten through the help of our leveling instrument. We have been able to set our back height of damp proof course (DPC) to 4 courses of blocks and 450mm plinth beam ( the DPC of 150mm included in this dimension), while the lowest point in the front was pegged at 4 initial courses of block work with an intermediate beam reinforced with Y12 with ring spaced at 300mm c/c, 4 additional courses of block wall and a final plinth beam of 450mm (which also include the DPM) All the substructure block wall were filled with weak concrete of M5 to give them more structural rigidity The plinth at the DPC level was expended throughout to connect all the foundation columns to serve as a horizontal tie
|
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by abdulwastecx(m): 11:24pm On Oct 27, 2017 |
more updates
|
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by hardon1(m): 2:28am On Oct 28, 2017 |
rili a hilly environment |
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by abdulwastecx(m): 2:13pm On Oct 30, 2017 |
completion of the foundation walls. Here, we are going to fill all the block holes with concrete to convert the foundation walls int a load-bearing structure.
|
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by abdulwastecx(m): 2:24pm On Oct 30, 2017 |
We also introduce some tie beam at the center of any walls taller than 5 courses of block to break them and protect them against the active soil bearing pressure from the foundation filling
|
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by abdulwastecx(m): 2:27pm On Oct 30, 2017 |
We have more final pictures from the foundation block work for you guys 2 Likes
|
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by abdulwastecx(m): 2:51pm On Oct 30, 2017 |
Having completed the block work, we will start making arrangement for foundation filling.
|
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by abdulwastecx(m): 3:02pm On Oct 30, 2017 |
After completion of the filling, we have to allow the fill to settled by gravity and rainfall for two weeks before we finally compact the soil through the use of a mechanical roller
|
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by abdulwastecx(m): 3:06pm On Oct 30, 2017 |
After this stage, we will need to apply a DPM and a layer of hardcore to prevent moisture rising through the foundation. follow us as we apply these and we also make allowance for nominal reinforcement to prevent cracking of the DPC or german floor mass concrete 1 Like 1 Share
|
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by abdulwastecx(m): 3:10pm On Oct 30, 2017 |
We have more pictures of this stage.... Before I come with more pictures let me explain the nominal reinforcement we provided above. The reinforcement is Y8 ( 8mm diameter high yield steel) spaced at 350mm center to center across all the foundation area to help prevent cracking of the ground floor slab
|
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by abdulwastecx(m): 3:16pm On Oct 30, 2017 |
Finally, we are casting the DPC of the foundation we are going to use a mix ratio of 1:2:4, gravel, stone dust and sharp sand 1 Like 1 Share
|
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by Timtol(m): 4:04pm On Oct 30, 2017 |
Following,nice one ARE U A BUILDER OR AN ARCHITECT? |
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by uboma(m): 7:39pm On Oct 30, 2017 |
I am learning some useful tips here. keep up the good work. |
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by abdulwastecx(m): 7:40pm On Oct 30, 2017 |
Timtol: A civil engineer 5 Likes |
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by abdulwastecx(m): 7:45pm On Oct 30, 2017 |
More pictures from the complete foundation work 1 Like
|
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by abdulwastecx(m): 7:53pm On Oct 30, 2017 |
To the next stage of work which includes the following: 1. Block work up to lintel level 2. Ring lintel round the building 3. Additional block work up to decking level |
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by abdulwastecx(m): 7:55pm On Oct 30, 2017 |
Block work up to lintel level
|
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by abdulwastecx(m): 8:04pm On Oct 30, 2017 |
Lintel work 1 Like
|
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by Juokorow(m): 9:10pm On Oct 30, 2017 |
abdulwastecx:Great job, Abdul! 2 Likes |
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by Timtol(m): 10:07pm On Oct 30, 2017 |
abdulwastecx:ok,smart kindly chat me on whatsapp 08100452977 |
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by Timtol(m): 10:17pm On Oct 30, 2017 |
Wen,did u originally start this project? |
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by GREATESTPIANIST: 5:27am On Oct 31, 2017 |
I'm following........ thanks @op for this exposure!!! |
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by GREATESTPIANIST: 6:54am On Oct 31, 2017 |
abdulwastecx:Please Sir, what kind of sand did you use for filling before adding the hardcore? |
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by abdulwastecx(m): 4:12pm On Oct 31, 2017 |
More updates
|
Re: Construction Of Five Bedroom Duplex With A Pent House At Guzape(fct Abuja) by abdulwastecx(m): 4:33pm On Oct 31, 2017 |
GREATESTPIANIST: laterite soil 2 Likes |
Guide Cost Of Decking Slab Of A Standard Twin Three Bedroom / This Is Why You Should Use Red Bricks For Your (next) Building Projects. / The New Phase Of Hillcrest Estate Sabon Lugbe, Abuja. Be A Landlord Now!
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 30 |