Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger - Politics - Nairaland

Nairaland Forum / Nairaland / General / Politics / Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger (31796 Views)

2nd Niger Bridge: Host Communities Shut Down Julius Berger Office / Julius Berger Installs Live Camera On The 2nd Niger Bridge / Construction Works Begin On Agbara, Lusada Roads In Ogun - Photos (2) (3) (4)

(1) (2) (3) (4) (Reply) (Go Down)

Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by Islie: 12:08am On Nov 23, 2019
Okechukwu Nnodim



Global construction giant, Julius Berger, has put the percentage of construction works so far completed on the Second Niger Bridge at approximately 28 per cent .

It also released pictures showing how far work has progressed on the bridge that connects Delta and Anambra states.

In a report dated November 15 , 2019 , on progress made at the project site , which was obtained on Friday in Abuja , the firm stated that the scope of works comprise of 1 . 6 km long River Niger Bridge and 10 .3 km highway inclusive Owerri interchange and toll station.

The report stated that the letter of award for the project was issued on July 25 , 2018 , and the contract was signed on August 14 , 2018.

Work commenced on the project site on September 1 , 2018 , while the contract period was captured in the report as 42 months .

It was also learnt that the total manpower on the site was 1 , 201, as the firm stated that work was going on at the site .


https://punchng.com/breaking-construction-works-on-2nd-niger-bridge-28-complete-julius-berger/

2 Likes

Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by Lynx001: 12:48am On Nov 23, 2019
..Julius berger: we hv döne 28%. Release pics and other details.
fg:2nd niger bridge complete. Shows us prototype.
wetin police no go see 4 check point.
but i think the julius berger in nigeria is nt the real öne. Them use 3years do birabi street(gra) for PH. I think is the female version juliana berger

94 Likes 2 Shares

Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by Fadomero(m): 1:37am On Nov 23, 2019
Our government should stop paying berger with oil na ma own b dt
Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by leofab(f): 5:51am On Nov 23, 2019
Less than 30%

5 Likes

Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by meccuno: 6:25am On Nov 23, 2019
Scam. grin

4 Likes

Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by eposho: 8:19am On Nov 23, 2019
Lynx001:
..Julius berger: we hv döne 28%. Release pics and other details.
fg:2nd niger bridge complete. Shows us prototype.
wetin police no go see 4 check point.
but i think the julius berger in nigeria is nt the real öne. Them use 3years do birabi street(gra) for PH. I think is the female version juliana berger
U r funny bro

31 Likes

Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by Ijaya123: 9:36am On Nov 23, 2019
The expected completion date for this project is November 2022. All hands must be on deck to ensure there is no further delay so the government can move on to other important projects.

And put to silence those wailers whose chorus is Buhari has not done anything. I wonder how they will have the mind to travel on that bridge when the time comes.

23 Likes 1 Share

Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by Temptee101(m): 9:37am On Nov 23, 2019
shocked

Crazy folks

Audio 28% complete, they should excuse themselves from the media and get to work. Nothing is happening there unless the resumed work this morning

Just one bridge, different stories everyday

12 Likes

Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by Nobody: 9:37am On Nov 23, 2019
we don dey get there. nice job FG . This is what the criminal party , PDP, couldn't do for 16 long years. Bastards supported by thieves

8 Likes 3 Shares

Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by Nobody: 9:37am On Nov 23, 2019
this is what LASG should have done with the lagos badagry expressway. periodical updates that can be tracked on a website.

3 Likes

Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by solmusdesigns: 9:37am On Nov 23, 2019
cool
Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by slimthugchimee2(m): 9:39am On Nov 23, 2019
Lynx001:
..Julius berger: we hv döne 28%. Release pics and other details.
fg:2nd niger bridge complete. Shows us prototype.
wetin police no go see 4 check point.
but i think the julius berger in nigeria is nt the real öne. Them use 3years do birabi street(gra) for PH. I think is the female version juliana berger

Please send a link where FG said 2nd NB is complete?

11 Likes 2 Shares

Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by Finnese001: 9:39am On Nov 23, 2019
Audio bridge

1 Like

Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by Halexgos3(m): 9:39am On Nov 23, 2019
AUDIO WORK

1 Like

Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by Jsst: 9:39am On Nov 23, 2019
Good work. This will definitely advance the eastern economy.

REGISTER BELOW FOR PRACTICAL AND COMPREHENSIVE DIGITAL MARKETING TRAINING IN LAGOS
Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by BabaIbo: 9:39am On Nov 23, 2019
28% since?

This Julius Berger be like say no be the original one abi dem no release money for the contract ni

Anyway I hope Buhari finish the bridge before his tenure expires

4 Likes

Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by ZombieTERROR: 9:40am On Nov 23, 2019
Buhari effect continues


Audio work everywhere

5 Likes

Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by Donvictor2015: 9:40am On Nov 23, 2019
Good one. More grace PMB. I'm IBO and I think this man is trying for us more even more than the 6 years rule of Jonathan.

10 Likes

Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by Donvictor2015: 9:41am On Nov 23, 2019
Good one. More grace PMB. I'm IBO and I think this man is trying for us, even more than the 6 years rule of Jonathan.

2 Likes

Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by Sheriman(m): 9:41am On Nov 23, 2019
Anonymous Bridge

1 Like

Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by Bari22: 9:42am On Nov 23, 2019
graduqlly
Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by Nobody: 9:42am On Nov 23, 2019
[s]
Donvictor2015:
Good one. More grace PMB. I'm IBO and I think this man is trying for us more even more than the 6 years rule of Jonathan.
[/s]

Stfu it's IGBO not IBO

44 Likes 3 Shares

Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by Nobody: 9:43am On Nov 23, 2019
It's only in Nigeria a River bridge takes years to complete with photo ops and pageantries

7 Likes 3 Shares

Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by Nobody: 9:44am On Nov 23, 2019
Bari22:
graduqlly

I bet you take weeks to shit

1 Like 1 Share

Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by OfficialAPCNig: 9:44am On Nov 23, 2019
modelmike7:
we don dey get there. nice job FG . This is what the criminal party , PDP, couldn't do for 16 long years. Bastards supported by thieves
The biggest thieve in africa thief tinubu is a saint and member of PDP

1 Like

Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by contigiency(m): 9:45am On Nov 23, 2019
And some busy bodies said that Jonathan awarded and started the project. All I have to say is Thank God who gave us buhari.

5 Likes

Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by frowland(m): 9:45am On Nov 23, 2019
Lynx001:
..Julius berger: we hv döne 28%. Release pics and other details.
fg:2nd niger bridge complete. Shows us prototype.
wetin police no go see 4 check point.
but i think the julius berger in nigeria is nt the real öne. Them use 3years do birabi street(gra) for PH. I think is the female version juliana berger

Lol, nice one.

2 Likes

Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by Tokenism: 9:46am On Nov 23, 2019
28% all these while! Wait, how many years e go take una to complete the thing self cool

1 Like

Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by frowland(m): 9:47am On Nov 23, 2019
Tokenism:
28% all these while! Wait, how many years e go take una to complete the thing self cool

Each pillar you see there is 18 story high. Building such in water under 18 months is not a child's play. The target is 2022 I suppose.

7 Likes

Re: Construction Works On 2nd Niger Bridge 28% Complete – Julius Berger by Kuginzi: 9:49am On Nov 23, 2019
meccuno:
Scam. grin
Bad Belle

1 Like

(1) (2) (3) (4) (Reply)

Lagos Arraigns Eze Ndigbo, Frederick Nwajago, For Terrorism / My Turn Will Soon Come: Garba Adamu Tells Tinubu To Enjoy Amid Nepotism Claims / Presidency Reacts To Soyinka's 'Nebuchadnezzar' Tag On Jonathan

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 29
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.