Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 8:51am On Jul 02, 2022 |
Location - okota
FOUR BEDROOM DUPLEX + 3UNITS OF 3BEDROOM
DURATION - 6months
DESIGN AND CONSTRUCTION - SHELTERMONICS NIG LTD |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 8:52am On Jul 02, 2022 |
Approach view |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 8:54am On Jul 02, 2022 |
Setting out |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 8:55am On Jul 02, 2022 |
First stage - pilling. |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by JBriel: 8:56am On Jul 02, 2022 |
Six months. Money dey where e dey abeg |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 8:57am On Jul 02, 2022 |
Pile depth - 12m Diameter - 450mm |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 8:58am On Jul 02, 2022 |
Pilling operations ongoing |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by aylagos(m): 9:01am On Jul 02, 2022 |
Nice one please what is the size of the land ? |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by aylagos(m): 9:01am On Jul 02, 2022 |
raymondFirstborn: Location - okota
FOUR BEDROOM DUPLEX + 3UNITS OF 3BEDROOM
DURATION - 6months
DESIGN AND CONSTRUCTION - SHELTERMONICS NIG LTD those design are beautiful and unique |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by aylagos(m): 9:02am On Jul 02, 2022 |
Plus can I get estimates cost of building this project? 1 Like |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 1:28pm On Aug 10, 2022 |
40 points total |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 1:34pm On Aug 10, 2022 |
Update In pics from last month till Date .
Steel work to pile cap |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 1:38pm On Aug 10, 2022 |
. |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 1:39pm On Aug 10, 2022 |
Steel work |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 1:40pm On Aug 10, 2022 |
Form work for cap |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 1:41pm On Aug 10, 2022 |
Formwork done. |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 1:42pm On Aug 10, 2022 |
Concrete work done. |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 1:43pm On Aug 10, 2022 |
. |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 1:45pm On Aug 10, 2022 |
. 450m ground Beam |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 1:46pm On Aug 10, 2022 |
. 16mm TMT tiger used as starter bars 1 Like |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 1:47pm On Aug 10, 2022 |
Ground beam steel work |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 1:48pm On Aug 10, 2022 |
|
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 1:50pm On Aug 10, 2022 |
After wood work to beams, we moved to concreting |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 1:51pm On Aug 10, 2022 |
Steel bars |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 8:54am On Aug 11, 2022 |
Started filling straight away. |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 8:55am On Aug 11, 2022 |
. |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 8:56am On Aug 11, 2022 |
35trips total |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 8:56am On Aug 11, 2022 |
Damp proof |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 8:59am On Aug 11, 2022 |
Steel bars for the floor |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 9:00am On Aug 11, 2022 |
Concrete to floor. |
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 9:01am On Aug 11, 2022 |
|
Re: Construction Of A 4bedroom Duplex + 3units Of 3bedroom Apartment(pilling) by raymondFirstborn(m): 9:02am On Aug 11, 2022 |
Started block work on Monday. |