Franzese:Sadly, my town seems to very very expensive when it comes to land. Due to the fact I started this project, the one close to me is been fixed for 5m as at yesterday. |
IjebuWarrior:Amen. Thanks so much. |
Foundation was done yesterday and casting was done today.
|
ibechris:Amen. It has not been easy, so much tension lately. |
Good day, Please, can 5inches block be used for foundation in 3 bedroom and one bedroom bungalow? Will it have any ripple effect? |
House Project expenses as 02/07/2024. 1, Land - 4,500,000. 2, Agent fee - 150,000. 3, Deed - 15,000. 6, Survey with approval - 200,000. 4, Plan with approval - 250,000. 5, Tank - 214,000. 6, Community fee - 150,000. 7, Local Govt Council fee - 160,000. 8, Land Clearing - 80,000. 9, Road filling sand 3 trips - 150,000. House Stage to roofing 1, Cement @7700 each i, 15 bags for foundation - 115,500. ii, 7 bags for chain round - 53,900. iii, 20 linters beams and pillars - 154,000. iv. 50 bags of setting of block to roofing - 385,000. v. 17 for German floor - 130,000. vi, 20 bags for German floor - 154,000. vii, 140 bags for 5000 blocks - 1,078,000. 2, Granite, i, 2 Trips of 3by4 Granite for Foundation and Lintel - 340,000. ii, 2 Trips of half inch for parapet and German floor - 340,000. . 3, SAND @65,000 each. i, 5 Trips of sand for block setting - 325,000. ii, 14 trips of sand for moulding - 910,000. 4, Block Packing from floor to create space - 130,000. 5, water for Moulding - 30,000. 6, water estimate for building and casting - 50,000. 7, Rods 100 12mm rods @9500 each - 950,000 40 10mm rods @8300 each - 332,000 30 30mm rods @6500 each - 195,000 8, Boards 70 Boards @2700 - 189,000. 5 2by2 @900 - 4,500. 9,Nails for carpenter - 20,000. 10, Labourers. i Block Moulding - 224,000 ii, House to roof, all expense labour with Engineer fee - 1,500,000. iii, Carpenter fee to roofing - 450,000 11, Wheel barrow, Pan and Shovel - 110,000. This fee will be updated as expenses arises. |
Good day everyone, I am creating this thread to document the progress of my building project. I am currently building a 3 bedroom bungalow with a room and parlour, including a security house. I AM VERY OPEN TO CORRECTIONS AND SUGGESTIONS CAUSE AM A NOVICE. From time to time, i will be updating this page on what i have spent so far and the pics of the job as we make progress. The weather has not been too friendly and this has delayed the job. Work may not go on on some days cause of rain. I am not physically present, my very good friend who has been an engineer is handling the project somewhere in Delta State. Kindly comment or share advice if any.
|