Building Plan Approval Requirements And Processes In Nigeria - Properties - Nairaland

Nairaland Forum / Nairaland / General / Properties / Building Plan Approval Requirements And Processes In Nigeria (40319 Views)

DEVELOPER ADVICE How To Get Building Plan Approval In Lagos / Why Your Building Plan Approval Take Long To Be Approved In Lagos & Other States / Building Plan Approval: Know The Local Planning District Office In Your Area Bya (2) (3) (4)

(1) (2) (Reply) (Go Down)

Building Plan Approval Requirements And Processes In Nigeria by Truefederalism(m): 7:35pm On Apr 21, 2017
Are you proposing a building project in any of these Nigerian cities?



Image Source: Pinterest

This document contains very important information; data that will help you avoid unnecessary stress and waste of hard earned resources.

You already already know that lands within Nigeria’s territorial boundaries are constitutionally vested in the Governors of our respective states, and that we have varying rules, regulations, codes and laws that guide the design and construction of buildings within these “territories”. What is obtainable in Lagos may not apply in Kano, and so on.

To make sure you do not encounter stress in your approval process, below is a compilation of building plan approval requirements around Nigeria. You do not know where your next brief will come from.



ABUJA
- Make application on prescribed application forms obtainable from the authority.
- Attach photocopies of title documents; Certificate of Occupancy (C of O), Right of occupancy (R of O), Titled Deed Plan (TDP), etc.
- Prepared plans on standard A3 size in 3 copies, drawn to scale of not less than 1:500 site plan
- Floor plans of 1:200 and 1:100 architectural drawings
- 3 copies of structural, mechanical, and electrical drawings.
- Site analysis report
- Environmental Impact Assessment Report (EIA)
- All plans are to be sealed by relevant professionals and submitted in both hard and soft copies.

- All applications in respect to petroleum filling stations, private hospitals, hotels, etc shall be accompanied with letter of licenses of the authority regulating that activity.

- Whenever approval is granted construction shall commence within 2 years, otherwise developer applies for validation.

- Developer is to apply for setting out approval when foundation is made, and obtain the setting out approval before continuing with further development.



LAGOS
- Crosscheck architectural drawings for the following Design Errors;

Cross ventilation
Proper scaling
Rooms should not be less than 3m x 3.6m
Legibility of lines
- Pre-vet documents with District Officer (DO)

- Make payment at bank with revenue code and agency code. Read and follow all advice given.

- Confirm receipt at accounts department, District Office.

- Prepare for site reconnaissance by District Officer

- Submit all documents

5 sets of sealed architectural drawings. See attached link on the need for registered architects
5 sets of sealed structural drawings and calculation sheets’
5 sets of mechanical and electrical drawings
Letter of supervision from COREN registered Engineers
Certificate of Occupancy
Clearance letter from LUAC
Confirmation letter from lands, or Consent
Clearance letter from Housing, Fire, Transportation and Drainage. See link also for Fire Outbreak in Port Harcourt
Confirmation letter from NTDA
Evidence of payment of Ground Rent
Soil test report
Environmental Impact Assessment (EIA)
Survey Plan (5 copies and 1 original)
Tenement rate receipt
Passport photograph of applicant
Electronic tax clearance of applicant (with copy of last tax payment receipt)
Development levy receipt
Evidence of payment of assessment fees
Site photographs.
The following is included if applicant is a company

Two directors’ tax clearance
Most recent company tax clearance
Evidence of pay as you go of company


PORT HARCOURT

- Put ARCON stamps and append your signature on the first set of drawings
- Make six (6) photocopies from the stamped original drawing
- Put the ARCON seal on all the copies
- Submit four (4) sets of drawings (photocopies) to the secretariat for approval.
- Keep one copy as consultant’s copy
- Submit one copy to the client.
- The following documents must be attached
- Structural calculation sheet
- Soil test report
- CVs of consultant Electrical, Mechanical and Structural Engineers
- Architect’s Practice License (photocopy) covers for Architect’s CV
- Site analysis Report and Plan (SAR&P)
- Environmental Impact Assessment (EIA). This applies if building is to be used for commercial purposes
- Workmen compensation
- Charting report of building plan
- Evidence of C of O (certificate of occupancy) from RIVGIS


We hope this helps

source: http://www.archfiler.com/building-plan-approval-requirements-and-processes-in-nigeria/

7 Likes 3 Shares

Re: Building Plan Approval Requirements And Processes In Nigeria by mufutau55(m): 8:57pm On Apr 21, 2017
Anything for Oyo and Ogun States? Thanks.

Hajji M.
Re: Building Plan Approval Requirements And Processes In Nigeria by Badgers14: 11:59pm On Apr 21, 2017
Anything on Imo State?

Cc: Truefederalism
Re: Building Plan Approval Requirements And Processes In Nigeria by Nobody: 7:07am On Apr 22, 2017
The EIA report is not that compulsory in Abuja unless you are planning to build an industry or factory
Re: Building Plan Approval Requirements And Processes In Nigeria by money121(m): 7:08am On Apr 22, 2017
Ok
Re: Building Plan Approval Requirements And Processes In Nigeria by Nobody: 7:08am On Apr 22, 2017
Great.... anyways check this out...


do you have skills, do you own a company, do you own a business, but you don't know how to promote it? you don't know who your targeted audience are? is your business crashing down?
Final Say Business Solutions is here for you...
Let us promote your business for you, let us connect you to clients all over the globe, let us revive that dying business/company for...
Contact Final say Business Solution today and you'll be glad you did.
Call Michael for more info... 07031041675
Re: Building Plan Approval Requirements And Processes In Nigeria by Coldplay007(f): 7:10am On Apr 22, 2017
is a structural plan necessary in Lagos and Oyo states?
Re: Building Plan Approval Requirements And Processes In Nigeria by money121(m): 7:11am On Apr 22, 2017
Material: *Aluminum (0.45mm thick)*

Client: Nairalander

Style: *Steptiles*
Colour: North brown and biegi

*Roof:* 317.2m @ N1800/sqm = *N570,960

*Flashing:* 58.05m @ N1700 = *N98,685
*Cladding:* 64.14m @ N1700 = * N109,038

*Accessories:* = *N30,000*

*Workmanship:* = *N65,000*
Bending =#5,000
Transportation=#27,000

*Total* = *N905,685*

Location: Moniya in Ibadan Oyo State

Call/WhatsApp 080-85-310-359 For Your Next Roofing Project

1 Like 1 Share

Re: Building Plan Approval Requirements And Processes In Nigeria by misterawo: 7:11am On Apr 22, 2017
Nice
Re: Building Plan Approval Requirements And Processes In Nigeria by Nobody: 7:13am On Apr 22, 2017
A four (4) bedroom semi-detached duplex with all rooms ensuite and tiled floors, ample parking space in a serene environment is up for sale.
Location: Ajah, Lagos.
Price: (Affordable and negotiable)

Call/WhatsApp: +2348138718647; +2348023480776
info@naijapropertiesonline.com

www.naijapropertiesonline.com

Re: Building Plan Approval Requirements And Processes In Nigeria by Nutase: 7:15am On Apr 22, 2017
shocked
Re: Building Plan Approval Requirements And Processes In Nigeria by sakalisis(m): 7:24am On Apr 22, 2017
Educative
Re: Building Plan Approval Requirements And Processes In Nigeria by opalu: 7:25am On Apr 22, 2017
Ok
Re: Building Plan Approval Requirements And Processes In Nigeria by shedy03(m): 7:30am On Apr 22, 2017
this is helpful. thanks.
we are registered Electrical and Mechanical Engineering Consultant. call us on 08054382435 for your approval & construction drawings(Mechanical & Electrical).
Re: Building Plan Approval Requirements And Processes In Nigeria by nengibo: 7:34am On Apr 22, 2017
Truefederalism:
Are you proposing a building project in any of these Nigerian cities?



Image Source: Pinterest

This document contains very important information; data that will help you avoid unnecessary stress and waste of hard earned resources.

You already already know that lands within Nigeria’s territorial boundaries are constitutionally vested in the Governors of our respective states, and that we have varying rules, regulations, codes and laws that guide the design and construction of buildings within these “territories”. What is obtainable in Lagos may not apply in Kano, and so on.

To make sure you do not encounter stress in your approval process, below is a compilation of building plan approval requirements around Nigeria. You do not know where your next brief will come from.



ABUJA
- Make application on prescribed application forms obtainable from the authority.
- Attach photocopies of title documents; Certificate of Occupancy (C of O), Right of occupancy (R of O), Titled Deed Plan (TDP), etc.
- Prepared plans on standard A3 size in 3 copies, drawn to scale of not less than 1:500 site plan
- Floor plans of 1:200 and 1:100 architectural drawings
- 3 copies of structural, mechanical, and electrical drawings.
- Site analysis report
- Environmental Impact Assessment Report (EIA)
- All plans are to be sealed by relevant professionals and submitted in both hard and soft copies.

- All applications in respect to petroleum filling stations, private hospitals, hotels, etc shall be accompanied with letter of licenses of the authority regulating that activity.

- Whenever approval is granted construction shall commence within 2 years, otherwise developer applies for validation.

- Developer is to apply for setting out approval when foundation is made, and obtain the setting out approval before continuing with further development.



LAGOS
- Crosscheck architectural drawings for the following Design Errors;

Cross ventilation
Proper scaling
Rooms should not be less than 3m x 3.6m
Legibility of lines
- Pre-vet documents with District Officer (DO)

- Make payment at bank with revenue code and agency code. Read and follow all advice given.

- Confirm receipt at accounts department, District Office.

- Prepare for site reconnaissance by District Officer

- Submit all documents

5 sets of sealed architectural drawings. See attached link on the need for registered architects
5 sets of sealed structural drawings and calculation sheets’
5 sets of mechanical and electrical drawings
Letter of supervision from COREN registered Engineers
Certificate of Occupancy
Clearance letter from LUAC
Confirmation letter from lands, or Consent
Clearance letter from Housing, Fire, Transportation and Drainage. See link also for Fire Outbreak in Port Harcourt
Confirmation letter from NTDA
Evidence of payment of Ground Rent
Soil test report
Environmental Impact Assessment (EIA)
Survey Plan (5 copies and 1 original)
Tenement rate receipt
Passport photograph of applicant
Electronic tax clearance of applicant (with copy of last tax payment receipt)
Development levy receipt
Evidence of payment of assessment fees
Site photographs.
The following is included if applicant is a company

Two directors’ tax clearance
Most recent company tax clearance
Evidence of pay as you go of company


PORT HARCOURT

- Put ARCON stamps and append your signature on the first set of drawings
- Make six (6) photocopies from the stamped original drawing
- Put the ARCON seal on all the copies
- Submit four (4) sets of drawings (photocopies) to the secretariat for approval.
- Keep one copy as consultant’s copy
- Submit one copy to the client.
- The following documents must be attached
- Structural calculation sheet
- Soil test report
- CVs of consultant Electrical, Mechanical and Structural Engineers
- Architect’s Practice License (photocopy) covers for Architect’s CV
- Site analysis Report and Plan (SAR&P)
- Environmental Impact Assessment (EIA). This applies if building is to be used for commercial purposes
- Workmen compensation
- Charting report of building plan
- Evidence of C of O (certificate of occupancy) from RIVGIS


We hope this helps

source: http://www.archfiler.com/building-plan-approval-requirements-and-processes-in-nigeria/
Is Port harcourt a state?

1 Like

Re: Building Plan Approval Requirements And Processes In Nigeria by babapressy(m): 7:35am On Apr 22, 2017
How true
Re: Building Plan Approval Requirements And Processes In Nigeria by Sambusiness(m): 7:40am On Apr 22, 2017
Just passing by
Re: Building Plan Approval Requirements And Processes In Nigeria by fishbone11(m): 7:44am On Apr 22, 2017
chijioke980:
Great men today take the risk and become what they are today
Why not you take the risk and become someone Great today
Call the number below
Great men offer assistance and favour for other to be great, if I have genuine fixed games like u proclaim I will post it free for the world to see and I would have joy in my heart to have changed somebody's life (make great). So my friend prove yourself with a good heart. You must be a millionaire from all the winnings from all the fixed games u have be wining judging from yr pic u have been posting of yr winnings. Haba broda, we get brain na

4 Likes

Re: Building Plan Approval Requirements And Processes In Nigeria by fairheven: 8:00am On Apr 22, 2017
If you wait the approval of the things ,you may never start your project.. Because some of the officials are just out to milk you dry

1 Like

Re: Building Plan Approval Requirements And Processes In Nigeria by Sunmolar(m): 8:09am On Apr 22, 2017
Pls, what of Ibadan. I have a farm factory building to erect. Do i need to go through all....
Re: Building Plan Approval Requirements And Processes In Nigeria by samjeorg(m): 8:19am On Apr 22, 2017
nengibo:

Is Port harcourt a state?






No bro, but most building construction project in Rivers State only occur in 3 local government area: Port Harcourt City, Obio/Akpor, and too some extent Ikwerre LGA. while other LGAs are considered to be out of MUD / RTP zone or GREATER PORT HARCOURT CITY PROJECT.

In other words, Rivers Government only concentration are in Areas covered by this bodies, which are all in Port Harcourt metropolis.

Going to the Riverine and Creeks, Like Kola, Bille, and others you are on your own.

1 Like

Re: Building Plan Approval Requirements And Processes In Nigeria by kinzodigital: 8:30am On Apr 22, 2017
samjeorg:

Please, can anyone in the house help us with stages and requirements for approval in Edo State?





No bro, but most building construction project in Rivers State only occur in 3 local government area: Port Harcourt City, Obio/Akpor, and too some extent Ikwerre LGA. while other LGAs are considered to be out of MUD / RTP zone or GREATER PORT HARCOURT CITY PROJECT.

In other words, Rivers Government only concentration are in Areas covered by this bodies, which are all in Port Harcourt metropolis.

Going to the Riverine and Creeks, Like Kola, Bille, and others you are on your own.


Re: Building Plan Approval Requirements And Processes In Nigeria by kinzodigital: 8:31am On Apr 22, 2017
Badgers14:
Anything on Imo State?

Cc: Truefederalism
Anything for Edo State?
Re: Building Plan Approval Requirements And Processes In Nigeria by ItsMeAboki(m): 8:38am On Apr 22, 2017
What of Kano State?
Re: Building Plan Approval Requirements And Processes In Nigeria by EngrBouss(m): 8:51am On Apr 22, 2017
Contact me on 07087210933

Re: Building Plan Approval Requirements And Processes In Nigeria by toxxnoni(m): 9:00am On Apr 22, 2017
Water borehole drilling, geophysiacal survey, soil test, pile foundation
Contact us
Call or whatsapp 08136569906

Re: Building Plan Approval Requirements And Processes In Nigeria by Alasi20(m): 9:12am On Apr 22, 2017
Booked
Re: Building Plan Approval Requirements And Processes In Nigeria by nengibo: 9:25am On Apr 22, 2017
samjeorg:







No bro, but most building construction project in Rivers State only occur in 3 local government area: Port Harcourt City, Obio/Akpor, and too some extent Ikwerre LGA. while other LGAs are considered to be out of MUD / RTP zone or GREATER PORT HARCOURT CITY PROJECT.

In other words, Rivers Government only concentration are in Areas covered by this bodies, which are all in Port Harcourt metropolis.

Going to the Riverine and Creeks, Like Kola, Bille, and others you are on your own.


Building Plan Approval Requirements And Processes In Some Nigerian States
Re: Building Plan Approval Requirements And Processes In Nigeria by moneylords(m): 9:53am On Apr 22, 2017
Re: Building Plan Approval Requirements And Processes In Nigeria by UJs: 10:00am On Apr 22, 2017
WELL FINISHED 3 & 5 BEDROOM DETACHED BUNGALOW(S) & DUPLEX WITH BQ FOR SALE

FITTED KITCHEN CABINETS AND WARDROBES

GATE HOUSE

BQ

ORIGINAL SANITARY WARES

QUALITY TILES & GRANITES

JACUZZI

BATH TUB

ETC

GOOD TITLED DOCUMENTS

SERENE ENVIRONMENT

LOCATION: DIVINE HOMES ESTATE WITHIN THOMAS ESTATE, AJAH

PRICE: CALL

INTERESTED BUYER SHOULD PLEASE CONTACT: 08170271511 OR 08035430603 FOR IMMEDIATE RESPONSE & MORE DETAILS

(1) (2) (Reply)

Caramelo Strip Club Is Being Demolished By FCTA After Arrest Of Strippers / Documents To Ask For When Buying Land Anywhere In Nigeria / American Lady Threatens To Stab Nigerian Housemate Over The Use Of Toilet

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 46
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.