Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 8:51pm On Aug 01, 2020 |
Completed Pillar Work
|
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 8:42pm On Jul 22, 2020 |
Back View
|
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 8:36pm On Jul 22, 2020 |
Pillar
|
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 8:35pm On Jul 22, 2020 |
Pillar
|
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 7:25pm On Jul 13, 2020*. Modified: 8:43pm On Jul 22, 2020 |
Pillar Mounting
|
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 6:42am On Jul 09, 2020 |
First Floor
|
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 7:42pm On Jul 08, 2020 |
FRANCOBEN: First Floor Material and Manpower Estimate stands at N1,782,500. |
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 5:57am On Jul 04, 2020 |
Access Road Blocking.
|
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 1:58pm On Jul 02, 2020 |
@hum2020.The new fence is the access road bought to be beautify to make the entrance look good! |
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 8:44pm On Jul 01, 2020 |
First Floor
|
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 6:33am On Jun 26, 2020 |
First Floor in Progress!
|
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 8:26pm On Jun 22, 2020 |
Blocking.
|
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 2:43pm On May 10, 2020 |
Molding of 2600 Blocks for First floor build.
Total Bags of cement: 70 Bags at N2,500 each Molding at N900 for each bag X 70. Block Carriage: N10 X 2,600. 4 Trips of Sand at N15,000 X 4. Transport and offloading: N8,500.
Total Cost of Molding 2600 Blocks for First floor = N332,500.
Blocks Breakdown: 9 inch= 1400 Blocks. 6 inch= 1200 Blocks.
Regards.
|
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 2:14pm On May 10, 2020 |
Hum2020: @Francoben the engineer charge 520 k for decking is this for laboures and his supervisor or just for only engineer for buildings because for me this is on high side thanks . Hi.The Engineer charge includes both the labour work such as carpenter,iron benders and block works. Regards. |
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 6:05pm On May 07, 2020 |
joycluv: Op I like what you're doing. Plz what's the size of the duplex? Length: 126. Width: 78. |
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 6:03pm On May 07, 2020 |
joycluv: The Length and the Width Length: 126. Width: 78. Regards. |
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 7:02am On May 07, 2020*. Modified: 7:43pm On Jul 08, 2020 |
First Floor Material and Manpower Estimate stands at N1,782,500. |
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 8:51am On May 05, 2020*. Modified: 2:31pm On May 10, 2020 |
First Floor(Stage 4) Cost Breakdown and Estimation.
|
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 7:30pm On Apr 26, 2020 |
House Plan
|
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 5:37pm On Apr 26, 2020 |
Land Size: 130 X 80.
Length: 130. Weight: 80.
House Plan:
|
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 8:50am On Apr 22, 2020 |
First floor blocks molding
|
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 8:47am On Apr 22, 2020 |
Upper Floor getting set
|
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 8:46am On Apr 22, 2020 |
Getting set for the upper floor
|
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 8:45am On Apr 22, 2020 |
Getting Set for the first floor.
|
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 11:41pm On Mar 03, 2020*. Modified: 2:19pm On May 10, 2020 |
Decking completed.
Total Cost Spent on Decking Stage.
N2,972,850.
|
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 11:39pm On Mar 03, 2020 |
Decking completed.
|
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 2:44pm On Jan 10, 2020 |
The 520k charged by the engineer is broken down below.
Plumbing Work: 60k Carpenter Work: 90k Electrician Work: 70k Decking Work: 120k Supervision: 80k Iron Work: 100k |
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 11:32am On Jan 07, 2020*. Modified: 1:53pm On Jan 07, 2020 |
Building
|
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 11:29am On Jan 07, 2020 |
6 bedroom duplex. 2 down..4 up. |
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 3:11pm On Jan 03, 2020 |
Side View
|
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 4:47pm On Dec 31, 2019 |
Plumbing 2
|
Properties › Re: Fence Building With A Security House+6 bedroom duplex and boysquarter.. by FRANCOBEN(op): 4:46pm On Dec 31, 2019 |
Plumbing
|