Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 10:00pm On Apr 04, 2016 |
electrical piping
|
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 9:55pm On Apr 04, 2016 |
first floor slab reinforcement
|
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 9:26pm On Apr 01, 2016*. Modified: 10:55pm On Apr 01, 2016 |
reinforcement for first floor beams
|
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 9:13pm On Apr 01, 2016 |
thanks |
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 11:18pm On Mar 31, 2016 |
progressive work
|
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 11:11pm On Mar 31, 2016 |
more pictures
|
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 11:02pm On Mar 31, 2016 |
progressing
|
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 11:55am On Mar 28, 2016 |
Thanks so much.Enjoy your Easter. |
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 11:54am On Mar 28, 2016 |
thanks so much.Enjoy your Easter. |
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 10:48pm On Mar 27, 2016 |
happy Easter to everyone. |
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 9:35am On Mar 27, 2016 |
Septic tank is part of 18 days achievement. |
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 9:26am On Mar 27, 2016 |
septic tank is part of 18 days achievement.
|
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 9:15am On Mar 27, 2016 |
18 working days. first floor form work kick start. Glory be to GOD.
|
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 5:08am On Mar 27, 2016 |
thanks oga aventure |
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 5:06am On Mar 27, 2016 |
God bless you sir. |
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 10:40pm On Mar 25, 2016 |
form work materials for first floor slab
|
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 10:00pm On Mar 25, 2016 |
17 days. we finished casting the remaining columns for grand floor. Also working on soak away and septic tank
|
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 10:37pm On Mar 24, 2016 |
more pictures
|
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 10:16pm On Mar 24, 2016 |
columns.
|
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 9:22pm On Mar 24, 2016*. Modified: 9:51pm On Mar 24, 2016 |
casting of 50% of grand floor column.
|
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 9:14pm On Mar 23, 2016 |
septic tank block work.
|
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 8:51pm On Mar 23, 2016 |
Grand floor concrete work.
|
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 8:38pm On Mar 23, 2016 |
thanks so much sir. |
Properties › Re: General Topic Thread-To Discuss Anything And Everything in Building Construction by lafolabi(m): 8:29pm On Mar 23, 2016 |
my oga am much around sir, am presently working on twin duplex construction in magodo. check it on my thread thanks |
Properties › Re: General Topic Thread-To Discuss Anything And Everything in Building Construction by lafolabi(m): 8:21pm On Mar 23, 2016 |
mufutau55: Where have you been, brother. Welcome back.
Hajji M. |
Properties › Re: General Topic Thread-To Discuss Anything And Everything in Building Construction by lafolabi(m): 10:47pm On Mar 22, 2016 |
good day every one. nice topics . |
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 10:30pm On Mar 22, 2016 |
compacting.
|
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 10:05pm On Mar 21, 2016 |
thanks oga moor |
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 10:03pm On Mar 21, 2016 |
|
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 9:35pm On Mar 21, 2016 |
progressing
|
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 9:17pm On Mar 21, 2016 |
earth filling and water for settlement before compaction.
|
Properties › Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 9:05pm On Mar 21, 2016*. Modified: 9:27pm On Mar 21, 2016 |
excavation of soak away and septic tank
|