| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 9:19pm On Oct 15, 2015 |
DAY 4:Formwork in progress
|
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by Dominionng(m): 6:55am On Oct 16, 2015 |
God speed Boss. Following keenly. |
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 10:42am On Oct 16, 2015*. Modified: 2:59pm On Oct 16, 2015 |
DAY 5:Even an hour is quite expensive to waste. Hence we have resumed this morning seen materials flooded ![]() We set to cast the ground beam (for all units) on DAY 11!
|
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 11:41am On Oct 17, 2015 |
DAY 6:Formwork almost completed
|
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 1:33pm On Oct 19, 2015 |
DAY:7 Reinforcement work in progress
|
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 3:45pm On Oct 19, 2015 |
6 nos of 16mm
|
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 6:41pm On Oct 19, 2015 |
Arrival of trailer of cement towards casting
|
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by Chekitaut: 8:50pm On Oct 19, 2015*. Modified: 9:14pm On Oct 19, 2015 |
segcymoor:We go beyond Granite... Thanks for believing in our services. ... Won't you rather Check Us Out? |
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 1:03pm On Oct 20, 2015 |
DAY 8:Plunmbig work and reinforcement checking in progress. -------------' We set to cast ground beam tomorrow |
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by Nobody: 6:16pm On Oct 20, 2015 |
segcymoor:Oga segcymoor why don't you create a new thread/topic for this project for we not to mix it up? Thanks. |
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 9:05pm On Oct 20, 2015 |
XYD2:D reason because we intend to compiled purely commercial projects we are constructing. Thanks for the observations |
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by skup008(m): 11:14pm On Oct 20, 2015 |
Following...... |
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 11:18am On Oct 21, 2015 |
Ground beam casting in progress
|
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by Chekitaut: 1:59pm On Oct 21, 2015 |
segcymoor:The Lord is with you, Congrat.... |
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 3:36pm On Oct 21, 2015*. Modified: 4:02pm On Oct 21, 2015 |
As at 3:30pm ....This particular block has been completed
|
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 3:39pm On Oct 21, 2015 |
Cleaning the. Concrete mixer
|
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by princechigzy(m): 3:57pm On Oct 21, 2015 |
One good fact here is that learning fast is guaranteed at every point. Comprehensive work Oga Segymoore, I am thrilled and beyond impressed. God's speed and Grace. |
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 4:01pm On Oct 21, 2015 |
Block B:less than 20min to go
|
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 4:36pm On Oct 21, 2015 |
segcymoor:Completed!
|
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 7:45pm On Oct 21, 2015 |
princechigzy:we appreciate u for believing in us. ---------------- MOORE-DESIGNBUILD LTD:We do structure right! |
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by Chekitaut: 12:32am On Oct 22, 2015 |
princechigzy:Don't mind the bros, that is only what he knows how to do best. Make him come play Ayo Olopon I go finish am. |
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 10:35am On Oct 22, 2015*. Modified: 7:35pm On Oct 22, 2015 |
DAY 10: We are able to achieved strong and compact concrete -------------- Ground beam completed! We are conscious of over speeding hence we need to pause for concrete to dry before filling
|
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 4:48pm On Oct 22, 2015 |
Special reinforcement for the starter bar
|
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by Nobody: 4:48pm On Oct 22, 2015 |
Great job bro! Very well done. |
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 10:04am On Oct 23, 2015 |
Ivoe:We appreciate you for believing in us! ------------ We set to serve but better |
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 9:14pm On Oct 23, 2015 |
Target: On or before DAY 18 --------- We should round up substructure work |
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 12:25pm On Oct 24, 2015 |
Filling work in progress
|
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by Dominionng(m): 2:47am On Oct 25, 2015 |
Late to class... Godspeed Boss. |
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 3:57pm On Oct 25, 2015 |
DAY 12:
|
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 11:00pm On Oct 25, 2015 |
We schedule to complete the filling work on DAY 13 |
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 1:22pm On Oct 26, 2015 |
Rounding up on filling
|
| Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 5:11pm On Oct 26, 2015 |
D project board!
|