Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 12:31pm On Oct 27, 2015
DAY 14:Surfaces treatment
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op):
Also on DAY 14:Topsy guys in action for plumbing work

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 6:00pm On Oct 27, 2015
DAY 14
We are favour with rain

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 11:53am On Oct 28, 2015
DAY 15:surfaces treatment

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 4:05pm On Oct 28, 2015
DAY 15:Bending schedule in progress

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 4:24pm On Oct 28, 2015
DAY 15:Damp proof membrane

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 4:32pm On Oct 28, 2015
DAY 15: Compaction process

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 7:51pm On Oct 28, 2015
Tomorrow being DAY 16:sand/cement screeding
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 8:14pm On Oct 28, 2015
Tomorrow being DAY 16:sand/cement screeding

-------
We are rounding up the substructure on DAY 19!
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 10:06am On Oct 29, 2015
DAY 16:Screeding as if decking grin

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 1:18pm On Oct 29, 2015
DAY 16:Another trailer towards oversite concrete

----------
Screeding in progress

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 12:03pm On Oct 30, 2015
DAY 17:Oversite reinforcement in progress

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 3:27pm On Oct 31, 2015
DAY 18:checking of reinforcement arrangements

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 4:36pm On Nov 01, 2015
Happy New month
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by X2X(m): 6:45pm On Nov 01, 2015
segcymoor:
D reason because we intend to compiled purely commercial projects we are constructing.
Thanks for the observations
I no sure say this na good enough reason oh. I think this project deserves a thread of its own.

All the same, well done.
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by twinskenny(m): 6:53pm On Nov 01, 2015
segcymoor:
Happy New month
same to you Boss
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 11:25am On Nov 02, 2015
Less than 20 DAY. ......We completed the substructure


-------
DAY 19:Casting of over site concrete

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 6:44pm On Nov 02, 2015
DAY19:Smooth and compact concrete



--------
Substructure completed!

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by twinskenny(m): 7:32pm On Nov 02, 2015
Eku ise sir
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 9:47pm On Nov 02, 2015
twinskenny:
Eku ise sir
I tell you no be small things




-------
We are challenge to roof this structure on or before the coming valentines day grin

.We set to proceed with superstructure tomorrow
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 12:44pm On Nov 03, 2015
Go further! .......


DAY 20:We proceed with superstructure
Establishment of kickers

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by omooba969(m): 2:41pm On Nov 03, 2015
Hello segcy, how many tons of iron rod & bags of cement did you have to use for this foundation stage?

Good job you are doing there & the pictures are really doing justice to your work also for the benefit of your audience.

9ice 1 bro. cool
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 3:13pm On Nov 03, 2015
omooba969:
Hello segcy, how many tons of iron rod & bags of cement did you have to use for this foundation stage?
Good job you are doing there & the pictures are really doing justice to your work also for the benefit of your audience.
9ice 1 bro. cool
2 trailers. .......less than 150 left over grin
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by omooba969(m): 3:46pm On Nov 03, 2015
segcymoor:
2 trailers. .......less than 150 left over grin
Thanks for prompt reply, much appreciated. May I know about the bags of cement too please. smiley
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 4:06pm On Nov 03, 2015
omooba969:
Thanks for prompt reply, much appreciated. May I know about the bags of cement too please. smiley
Oh this is actually cement. .


----------almost 22tons of reinforcement
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by omooba969(m): 4:16pm On Nov 03, 2015
segcymoor:
Oh this is actually cement. .


----------almost 22tons of reinforcement
Ok cool,thanks a lot.
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 6:52pm On Nov 03, 2015
DAY 20:Formwork in progress

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 9:10am On Nov 04, 2015
Formwork:powerful bracing.

--------
Watch out for the upright columns !

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 4:06pm On Nov 04, 2015
DAY 21:Casting to kicker

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 4:18pm On Nov 04, 2015
segcymoor:
DAY 21:Casting to kicker

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 12:04pm On Nov 05, 2015
DAY 22:Casting of columns

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by segcymoor(op): 3:50pm On Nov 05, 2015
segcymoor:
DAY 22:Casting of columns

1 2 3 ... 42 43 44 45 46 47 48 ... 113 Reply

PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI • PILE FOUNDATION FOR TERRACE BUILDING AT LEKKI • Construction Process Of A Wing Duplex+flat At Ajah • 2 • 3 • 4

Prices For These Paints • Find A Roommate In Lagos(only Graduates Please) • Professional Aluminum Windows, burglary proof, security Gate & Doors(Photos)