Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo - Properties (4) - Nairaland
Nairaland Forum › Nairaland General › Properties › Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo (14486 Views)
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 9:22pm On Apr 30, 2016*. Modified: 9:43pm On Apr 30, 2016 |
More progresive pictures for 47 working days achievement.
|
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by Yem0350: 8:51pm On May 01, 2016 |
EsanEmmanuel:You again |
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by EsanEmmanuel(m): 6:39am On May 02, 2016 |
Yem0350:
|
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 5:37pm On May 03, 2016 |
Plastering commencing
|
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 5:55pm On May 03, 2016 |
Progresive pictures
|
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by Olusojisorunmu(m): 9:20pm On May 06, 2016 |
Progresive pictures Weldone sir.... |
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by Olusojisorunmu(m): 9:38pm On May 06, 2016 |
Awesome!!! |
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 11:37pm On May 06, 2016 |
Thanks, how is kajola site? |
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 11:41pm On May 06, 2016 |
Update pictures
|
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by Olusojisorunmu(m): 7:12pm On May 09, 2016 |
Thanks, how is kajola site? Fine sir, progressing as well sir.... |
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 9:08pm On May 10, 2016 |
Well done |
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by Olusojisorunmu(m): 6:31pm On May 11, 2016 |
lafolabi:Yes sir! thk you sir. |
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by Olusojisorunmu(m): 6:32pm On May 11, 2016 |
lafolabi:Yes sir! thk you sir. |
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 12:41pm On May 16, 2016 |
Progresive pictures
|
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by msogunro: 2:48pm On May 16, 2016 |
Horlawoomey:I Googled "standard framed structure" but didn't find any information. Maybe there is another name for it. From the link below, can you let me know which of these frames is "standard framed structure"? http://www.aboutcivil.org/frame-structures-definition-types.html Or even better, can you describe it and explain why it is better and more expensive? Thank you. |
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by Horlawoomey(m): 5:46pm On May 16, 2016 |
msogunro:This is my own definition. A frame structure describes structure in which the loads from the floors or slabs are transferred through the beams to the column and the columns also transfer same to the foundation which now spread the load to the ground underneath. In this structure, the walls act as non load bearing, they only resist some wind load and act as demarcation. Building a frame structure involves the foundation works, after which the columns/pillars will be erected, followed by the beams, slab and stair. When the building is more than one storey, same process will continue till the required floor will be reached before the block works. It is more expensive because the members will require more formwork. A column with four sides will need formwork on all the four sides unlike two sides if the block work was done first. |
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by msogunro: 6:06pm On May 16, 2016 |
Horlawoomey:Thank you. If the walls are not load bearing and are just there to separate rooms, can cheaper material be used for the separation of rooms or, do I even need walls if I have an open floor concept? Hypothetical question: if I want all my external walls to be glass, could I do that without reducing the structural make-up or quality of the building? |
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 6:16pm On May 16, 2016 |
Progressing
|
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by Horlawoomey(m): 6:47pm On May 16, 2016 |
msogunro:Yes, cheaper materials can be used for the wall if there is any. The external walls can be made of the combination of aluminum and glass provided that their strength can withstand the wind pressure. Many office spaces that are being built these days are just skeletal concrete with glass wall siding and they are beautiful. I hope we will be able to come up with a cheaper and more reliable material than the traditional blocks and mortar soon. |
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 7:41am On May 19, 2016 |
Progresive picture
|
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by twinskenny(m): 8:07am On May 19, 2016 |
lafolabi:good job |
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 11:12pm On May 21, 2016 |
More progresive pictures .
|
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 3:45pm On May 31, 2016 |
More progresive pictures
|
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 3:52pm On May 31, 2016 |
More and more progresive. Glory be to almighty God
|
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 12:15am On Jun 01, 2016 |
73 working days achievement. Glory to the almighty God for this achievement and the great opportunity. |
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 10:16pm On Jun 01, 2016 |
Progresive pictures
|
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 1:14pm On Jun 02, 2016 |
Progresive pictures .
|
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by Olusojisorunmu(m): 12:14pm On Jun 07, 2016 |
lafolabi:Great work sir.....More grease to your elbow |
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 2:14pm On Jun 16, 2016 |
The almighty,miracle worker and greatest God is doing this great work.....thanks to all my friends and well wishers. |
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 11:33pm On Jun 17, 2016 |
Internal work
|
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 12:23am On Jun 23, 2016 |
More progresive pictures
|
| Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(op): 12:31am On Jun 23, 2016 |
More and more progresive
|
Construction Of Fourbedroom Duplex And Two Unit Of Two Bedroom Flat @ Isheriopic • Construction Of 4bedroom Duplex And 2unit 2bedroom Flat • Construction Of Bungalow For A Nairalander At Ajah Area By Rotech77 • 2 • 3 • 4