Request For Building Estimate by amakaDD(op):
Good morning Engineers and QS in the house.

Kindly help a sister with the estimate for this commercial build. Location is Lagos.

I need bulk pack figure for each stage of the contract.

Suggested breakdown could be:

1. Foundation/Substructure
2. Superstructure
3. Slab
4. Roofing
5. Mechanical/Electricals/Plumbing
6. *Finishing (Intetnal)
7. **External Finishing
8. Building Approval/community settlement

*Finishing includes _Windows, Doors, Burglar Bar, Borehole, Overhead tank, Ceiling, Balustrades etc._

**External Finishing includes _Septic tank, Interlocking tiles, Fence, Gate, Gatehouse..._

1. The build is sitting on a half plot.

2. This is expected to be a commercial project and ROI is key. So responsible cost cutting advice is welcome.

3. This is a crowdfunded project hence the need to clarify cost to non-technical members

cc: saydfact, rotech77, abdulwastecx, raymondFirstborn, KolaShangOne, spyder880, segcymoore, QSFemi etc.

Re: Request For Building Estimate by raymondFirstborn(m): 3:32pm On Nov 18, 2020
amakaDD:
Good morning Engineers and QS in the house.

Kindly help a sister with the estimate for this commercial build. Location is Lagos.

I need bulk pack figure for each stage of the contract.

Suggested breakdown could be:

1. Foundation/Substructure
2. Superstructure
3. Slab
4. Roofing
5. Mechanical/Electricals/Plumbing
6. *Finishing (Intetnal)
7. **External Finishing
8. Building Approval/community settlement

*Finishing includes _Windows, Doors, Burglar Bar, Borehole, Overhead tank, Ceiling, Balustrades etc._

**External Finishing includes _Septic tank, Interlocking tiles, Fence, Gate, Gatehouse..._

1. The build is sitting on a half plot.

2. This is expected to be a commercial project and ROI is key. So responsible cost cutting advice is welcome.

3. This is a crowdfunded project hence the need to clarify cost to non-technical members
Good afternoon, I can help you with the full cost breakdown.

Send the drawings to me on Whatsapp.
09056082348(call & WhatsApp)
raymondfubara@gmail.com
Re: Request For Building Estimate by amakaDD(op): 3:44pm On Nov 18, 2020
raymondFirstborn:
Good afternoon, I can help you with the full cost breakdown.

Send the drawings to me on Whatsapp.
09056082348(call & WhatsApp)
raymondfubara@gmail.com
Done.

Much appreciated sir
Re: Request For Building Estimate by Chekitaut: 6:18pm On Nov 18, 2020
Precise location in Lagos...?
Re: Request For Building Estimate by Chekitaut: 6:20pm On Nov 18, 2020
Foot size of the building...
Re: Request For Building Estimate by amakaDD(op): 1:57am On Nov 19, 2020
Chekitaut:
Precise location in Lagos...?
Surulere
Re: Request For Building Estimate by amakaDD(op): 2:00am On Nov 19, 2020
Chekitaut:
Foot size of the building...
Around 28m x 5.5m
Re: Request For Building Estimate by Chekitaut: 9:29am On Nov 19, 2020
amakaDD:
Around 28m x 5.5m
Carcass
Foundation @₦8m
Block set to 1st Decking @₦8m(ground floor)
Block set to 2nd Decking @₦8.5m
Block set to Roofing @₦8m
Total =₦32.5m

Finishing will cost you close to ₦35m
Re: Request For Building Estimate by peaceland(m): 10:31am On Nov 19, 2020
Please can you further break down the foundation aspect,
I find it interesting that half plot foundation will be that much.
Just for self education sir.
Thanks
quote author=Chekitaut post=96204208] Carcass
Foundation @₦8m
Block set to 1st Decking @₦8m(ground floor)
Block set to 2nd Decking @₦8.5m
Block set to Roofing @₦8m
Total =₦32.5m

Finishing will cost you close to ₦35m[/quote]
Re: Request For Building Estimate by Chekitaut:
peaceland:
Please can you further break down the foundation aspect,
I find it interesting that half plot foundation will be that much.
Just for self education sir.
Thanks
quote author=Chekitaut post=96204208] Carcass
Foundation @₦8m
Block set to 1st Decking @₦8m(ground floor)
Block set to 2nd Decking @₦8.5m
Block set to Roofing @₦8m
Total =₦32.5m

Finishing will cost you close to ₦35m
Recommend Raft foundation 1.2m height
Approx 6tons of TMT steel @₦295k/ton
3 trips of 30tons Granite @₦210k/trip
6trips of Sharp Sand@₦90k/trip
300 bags of Cement@₦3500/bag
300 1x12 @₦1600each
250 2x3 @₦450each
Binding wire 3bundle @₦8k/each
3bags Nail @₦8k./each
Filling Sand 10trips @₦90k(Sharp Sand)

Workmanship @₦800k
Supervision fee @₦500k
Re: Request For Building Estimate by peaceland(m): 2:02pm On Nov 19, 2020
Thanks greatly sir.
Really appreciate this.
Chekitaut:
Recommend Raft foundation 1.2m height
Approx 6tons of TMT steel @₦295k
3 trips of 30tons Granite @₦210k/trip
6trips of Sharp Sand@₦90k/trip
300 bags of Cement@₦3500/bag
300 1x12 @₦1600each
250 2x3 @₦450each
Binding wire 3bundle @₦8k/each
3bags Nail @₦8k./each
Filling Sand 10trips @₦90k(Sharp Sand)

Workmanship @₦800k
Supervision fee @₦500k
Re: Request For Building Estimate by Chekitaut: 1:21am On Nov 20, 2020
peaceland:
Thanks greatly sir.
Really appreciate this.
You welcome sir
Re: Request For Building Estimate by Bimpsyyyyy: 10:44am On Nov 21, 2020
amakaDD:
Good morning Engineers and QS in the house.

Kindly help a sister with the estimate for this commercial build. Location is Lagos.

I need bulk pack figure for each stage of the contract.

Suggested breakdown could be:

1. Foundation/Substructure
2. Superstructure
3. Slab
4. Roofing
5. Mechanical/Electricals/Plumbing
6. *Finishing (Intetnal)
7. **External Finishing
8. Building Approval/community settlement

*Finishing includes _Windows, Doors, Burglar Bar, Borehole, Overhead tank, Ceiling, Balustrades etc._

**External Finishing includes _Septic tank, Interlocking tiles, Fence, Gate, Gatehouse..._

1. The build is sitting on a half plot.

2. This is expected to be a commercial project and ROI is key. So responsible cost cutting advice is welcome.

3. This is a crowdfunded project hence the need to clarify cost to non-technical members

cc: saydfact, rotech77, abdulwastecx, raymondFirstborn, KolaShangOne, spyder880, segcymoore, QSFemi etc.
You can give a sister this job also, I am a female engineer will help u out cost effectively but will be paid percent for working on it , you will regret .
Re: Request For Building Estimate by Chekitaut: 10:55am On Nov 21, 2020
Not is missing
Re: Request For Building Estimate by Chekitaut: 10:56am On Nov 21, 2020
Bimpsyyyyy:
.
last sentence check
Re: Request For Building Estimate by amakaDD(op): 3:55pm On Nov 21, 2020
Bimpsyyyyy:
You can give a sister this job also, I am a female engineer will help u out cost effectively but will be paid percent for working on it , you will regret .
huh?

I assume typo.

But I reject it!!!
Re: Request For Building Estimate by topsy23(m): 5:15pm On Nov 21, 2020
You can contact us for your MEP design and estimate


Check out our thread

MEP installation
https://www.nairaland.com/1233943/contact-us-electrical-mechanical-plumbing/25


Distribution boards
https://www.nairaland.com/2668061/abb-distibution-board-schneider-distribution/6
1 Reply

Cost Of Building A House In Nigeria (free Building Estimate For All)Building EstimateCost, Estimate For Building A 3bedroom Bungalow In Nigeria (Detailed Info)234

Interior Of 100 Million Naira Fancy Duplex- Yay Or Nayland for sale at eleko for 3.5m per plot, title; gazetteBecause you don’t earn much doesn’t mean you shouldn’t save up and get 15%