Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 6:27am On Jun 12, 2019 |
More
|
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 6:25am On Jun 12, 2019 |
Next, it's time for some wood works( roofing)  . Let there be wood.
|
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 6:21am On Jun 12, 2019 |
We Begin work on the shoot out or verandah.tho the shoot out is not too perfect but it's ok nonetheless
|
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 6:20am On Jun 12, 2019 |
I will attach cost of things in the front page when I am done with the photos upload |
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 6:19am On Jun 12, 2019 |
More pics
|
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 6:17am On Jun 12, 2019 |
The only constant thing in life is change.dont ever stop improving as you move in life
|
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 6:15am On Jun 12, 2019 |
More
|
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 6:14am On Jun 12, 2019 |
More photos
|
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 6:13am On Jun 12, 2019 |
And we get to the lintel stage
|
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 5:27am On Jun 12, 2019 |
Tammynator: Wow! How many days did it take to get to this level? God bless the works of your hand. Due to the slowness of the work it took us 7 days to get to this level .the bricklayers dragged the work on purpose because they were working on another project simultaneously |
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 10:02pm On Jun 11, 2019 |
More pics coming soon |
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 8:23pm On Jun 11, 2019 |
more progress
|
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 8:21pm On Jun 11, 2019 |
see progress
|
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 8:16pm On Jun 11, 2019 |
Gabrokpara001: From the pictures you posted i can see you didn't locate any column/pillars at the corners even tho the building may stand, it is usually best practice to position pillars at critical positions as they will carry the roof and concrete fascia(if you intend to do one), as well as enabling you to make use of chain lintel instead of single lintels which most people use in other to cut cost but ask any professional he/she will advice you to go for chain lintel. Well good job so far God speed Thanks for your words of encouragement. The reason we left out the pillars and columns altogether was beacaue we had no plan to do any concrete fascia, parapet ,the house is just a bungalow and won't be carrying any heavy load ,and the land is really rocky serving as additional support for the building |
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 8:14pm On Jun 11, 2019 |
Tammynator: OP, God will surely help u finish your project. Firstly, I don't think it is a must to use 9" blocks for foundation. Here in Akwaibom, they even use 5" blind to build from foundation to roofing level for bungalows. Secondly, how did u know the 500 blocks will be enough for your foundation? And, did you buy the 2500 blocks needed for the main building all at once? Keep it up and always ask questions. Actually , from experience of the bricklayer he suggested we buy 400 blocks .buy as we progressed on the project we discovered we needed 100 more. due to the sloppiness of the land some part of the foundation was 3 coaches high, other were 2 coaches high... And about the 2500 blocks, we didn't buy them all at once.we bought 500 blocks first then when they were exhausted, we bought another 1000 blocks and so on. |
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 8:03pm On Jun 11, 2019 |
more
|
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 7:40pm On Jun 11, 2019 |
More
|
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 7:39pm On Jun 11, 2019 |
Hum2020: Op what a nice work you are doing there but must say that you are managing this work because I don't see the reason why it is taking you time to filled the foundation knowing that by filling up this foundation it will give a level results before you start setting the block to linte thanksh Well let me surmarise why I didn't fill it before raising the main building blocks in two points. 1.lack of experience 2.the workers were really lazy and seems I was even forcing them to get the job done |
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 7:12pm On Jun 11, 2019 |
More
|
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 7:03pm On Jun 11, 2019 |
Let the photos do the talking
|
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 6:39pm On Jun 11, 2019 |
mufutau55: You should jave fill the foundation and levelled it before progressing with upper block laying. This will help you to get good levelling gauge for all rooms and areas.
Hajji M. Well , first experience and nobody to ask how ist been done.we learn from experience.will try that in my next project ,God willing |
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 6:37pm On Jun 11, 2019 |
mufutau55: Why didnt you move away this palm tree before starting the foundation block laying?
Hajji M. The bricklayer and his boys were lazy and kept talking me out of removing the palm tree.they promise to remove it by cutting it into small pieces when they were done with the foundation.it was part of the reason I chased them away after they completed the foundation stage. I later paid some hausa men to help me roll away the palm tree trunk |
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 6:28pm On Jun 11, 2019 |
More photos
Photos speak a thousand words
|
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 6:24pm On Jun 11, 2019 |
Estimated blocks for the building
2500 blocks.
|
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 6:23pm On Jun 11, 2019 |
Building proper on the way
|
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 6:21pm On Jun 11, 2019 |
I negotiated with another bricklayer to help with the construction from foundation to roof stage of the building because the bricklayer that constructed the foundation was trying to extort me . Imagine he gave me a quotation of 200k just to raise the building from foundation level to roofing stage.
Anyways I got a good bargain of 85,000 naira from another bricklayer for the same job.
It's always good to take quotations from two or three workman before deciding on embarking on a project.but remember , cheap price doesn't mean it's the best.justt know how to negotiate and pick quality |
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 6:13pm On Jun 11, 2019 |
Still on the foundation .
To save cost, we didn't do German flooring.it was nt needed anyways since the land was dry land and very rocky
|
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 6:08pm On Jun 11, 2019 |
More from different angles.
Due to lack of experience , I used 6 inch blocks for setting of the foundation instead of 9 inches block.i later found out from the bricklayer that 9 inch was the standard block used in setting foundation of a house even if it's just a bungalow house
|
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 5:55pm On Jun 11, 2019 |
More photos
|
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 5:46pm On Jun 11, 2019 |
Photos of the foundation
|
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 5:36pm On Jun 11, 2019 |
Foundation completed.
Cost of foundation.
12 bags of cement used @ 2400 each 28,800 1 trip of sharp sand @ 15000 15000 1 trip of gravel @ 18000 18000 500 blocks 6 inches @130 65000 Sticks for setting the foundation 1000 Labour 42000 Total spent at this stage 169,000 |
Properties › Re: Construction of a simple 3 Bedroom Bungalow In 2019 by iamblest(op): 5:27pm On Jun 11, 2019*. Modified: 5:53pm On Jun 11, 2019 |
I think i have lost the photos of the bush clearing and foundation setting I took.but i will upload the photos of the foundation after they were completed
Cost of clearing the bushes .3000 naira. |