Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 11:45pm On Aug 19, 2020 |
Roof cover
|
Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 6:59am On Aug 11, 2020 |
Plastering the parapet before covering the roof carcass |
Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 6:58am On Aug 11, 2020 |
We got here.
|
Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 7:58am On Aug 01, 2020 |
Here we go.... crowning our efforts
|
Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 9:24pm On Jul 27, 2020 |
Parapet formwork ready for concrete placement Progress!
|
Properties / Re: Piling Operations In Portharcourt, And Surrounding Riverine Communities by malkomx(m): 8:16am On Jul 26, 2020 |
Piling operations |
Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 7:17am On Jul 25, 2020 |
Parapet rebar works almost immediately
|
Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 10:44pm On Jul 23, 2020 |
Parapet
|
Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 10:42pm On Jul 23, 2020 |
Roofing wood
|
Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 3:00pm On Jul 20, 2020 |
Front beam works ongoing
|
Properties / Re: Piling Operations In Portharcourt, And Surrounding Riverine Communities by malkomx(m): 7:30am On Jul 20, 2020 |
Men at work |
Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 7:29am On Jul 20, 2020 |
Progress |
Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 9:16pm On Jul 19, 2020 |
loffers:Sure. Thanks |
Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 11:56am On Jul 19, 2020 |
Getting there already Speed!
|
Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 11:36am On Jul 17, 2020 |
Soak away completed
|
Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 11:33am On Jul 17, 2020 |
Progress
|
Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 1:51pm On Jul 16, 2020 |
Works on the front columns going on simultaneously
|
Properties / Re: Piling Operations In Portharcourt, And Surrounding Riverine Communities by malkomx(m): 9:35am On Jul 16, 2020 |
Placing rebar cage in a 12m bored pile of Dia450mm
|
Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 11:02pm On Jul 15, 2020 |
chimexdnice1:Water in the right quantity as an integral component of concrete is as important as the cement used. No matter how tightly placed your wooden form work is, water will still leak through the joints. The wood itself has a high capacity to soak water. These will reduce the amount of water available for the complete hydration of the cement in the concrete mix The nylon we use as DPM serves two purposes namely: 1. Retains water in the concrete mix to ensure complete hydration of cement and proper non-brittle hardening 2. Helps preserve the wooden form work for future use since soaked wood will loose its strength as a result of water-induced fermentation. |
Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 10:44pm On Jul 15, 2020 |
Lintel operations
|
Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 8:17am On Jul 15, 2020 |
Block work hitting lintel level already
|
Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 9:42pm On Jul 13, 2020 |
joycluv:The size of your deck will determine the quantity of rebars While the load coming on the deck will determine the size and number of rebars for the beams. All these have been predesigned and shown with the bending schedule on your structural drawings Let a qualified engineer interprete your structural drawings for you and calculate the quantity of the various sizes of rebar and their correct positioning on your deck. Except you are a civil/structural Engr decking reinforcements is not a DIY affair |
Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 9:32pm On Jul 13, 2020 |
Milestone 3: We are up and running Let’s make up for lost time Block work + rebar extension
|
Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 9:28pm On Jul 13, 2020 |
mexxy1:Thank you for your interest |
Properties / Re: Piling Operations In Portharcourt, And Surrounding Riverine Communities by malkomx(m): 6:11pm On Jul 12, 2020 |
Considering building on reclaimed land? Let’s handle your pile foundation for you Quality job within a great budget Men@work in Asari/Toru LGA in Rivers State
|
Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 5:57pm On Jul 12, 2020 |
ricki:Welcome bro, we are all bosses together |
Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 5:55pm On Jul 12, 2020 |
mexxy1:This is a sizable building. All the cost of construction of the suspended floor (decking) is 3.3M This does not include monies spent from foundation through DPC, Lintel to Deck-level block work. |
Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 11:46am On Jul 12, 2020 |
ricki:So far, a total of 3.3M was spent on the construction of this deck |
Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 11:16am On Jul 12, 2020 |
With yesterday’s concrete placement, the deck work is complete and we will proceed to the next milestone Monday.
|
Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 10:04pm On Jul 05, 2020 |
Form work and rebar works complete, Electricians and plumbers doing their thing We are almost set to place concrete on our deck
|
Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 9:58pm On Jul 05, 2020 |
ricki:Sure. We are still on it. When we complete this deck, we will provide you with how much was spent on manpower and materials every step of the way. Thanks for your interest Do stay tuned 1 Like |
Properties / Re: Developing A Four Bedroom Duplex In The Outskirts Of Owerri by malkomx(m): 8:01pm On Jul 01, 2020 |
Rebar works
|
(1) (2) (3) (4) (5) (of 5 pages)
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 20 |