The client is currently resting and working towards funding the next stage which is the slab. A total of 12.8m is needed for the next stage. ricki: |
Thank you for the compliment sir |
.... |
Pictures coming in soon |
Thank you very much. We will commence laying two courses of concrete blocks on the reinforced concrete lintel beam on Tuesday. Meanwhile, the slab casting has been rescheduled to next month due to funding. We will soon post the proposed cost of the slab work.
|
It's been a while |
Thank you all for all the messages |
We shall imminently commence the acquisition process for the requisite materials essential for the slab. |
Happy Sunday to everyone! We genuinely appreciate all the thoughtful messages and inquiries that have been coming our way. It's wonderful to feel connected and to have such engaging correspondence. For those who might be contemplating their next significant construction endeavor, we would like to remind you that Mr. Fixer is constantly at your service, ensuring that your projects are handled with utmost care and professionalism, regardless of where they are located. Whether you're in the heart of a bustling city or a serene rural landscape, geographical barriers are never an obstacle for Mr. Fixer. We are committed to delivering excellence in your construction projects, no matter the state or region they are situated in. |
On Thursday, we successfully accomplished the task of casting the concrete columns and lintel on the ground floor, ensuring that the foundational framework of the building was securely established. In addition to this critical construction phase, we completed laying the plumbing pipes for the ground floor prior to proceeding with the concrete casting, thereby guaranteeing that all necessary infrastructure was in place before solidifying the concrete structure.
|
The pictures of the new iron rod we bought isn't available but the video recordings. If you wish to have the video update on the site you can drop a message on Whatsapp +2347046517600, we post video recordings of all our projects daily. Meanwhile attached are the previous photos of the imported irod rod we bought. But the facts is you can identify imported irod rod from local with pictures except you are in the field. One of the key differences between them, often not apparent at first glance, is the minor variation in thickness—while imported rods maintain an exact 16mm diameter, those produced locally often experience a slight reduction in diameter, making them appear less robust in comparison.
|
Costing for both the concrete lintel and columns casting work Formwork With the previous planks on the site we will be needing 90 planks if we remove and replace #315k 2by3 wood 20 @#1000 #20k Nail 30k Carpenter workmanship #170k Transportation #15k Total (if we reuse and remove ) #550k REINFORCEMENT Reinforcement for both the columns at the first floor and ground floor lintel using imported steel Y16 78 @#21000 #1638000 Y10 44 @#8500 #364k Binding wire #30k Workmanship #170k Transport #15k Total #2380000 CONCRETE WORK We have granite and sand all we need is cement 50bags #500k Workmanship #180k Total #680k GRAND TOTAL #3457000 |
Planks and wood for the form work now on site. A total of 90 planks, 20 pieces of 2by3 wood was supplied today.
|
We will commence supplying materials for the columns and lintel work tomorrow |
More pictures of the work done
|
As scheduled, we successfully reached the ground floor lintel on Saturday, just as we had planned. Remarkably, it took us only five days to complete the setting of more than 3,000 concrete blocks. Next on the agenda is the formwork for the lintel and columns.
|
Happy Sunday |
At Mr. Fixer, transparency is a fundamental principle that guides our operations. To exemplify this, we provide live screenshots of our ongoing projects, allowing you to stay informed and connected. No matter where you are in the world, our advanced systems enable you to not only view and listen to on-site activities but also engage in real-time conversations with the people there, ensuring a seamless and interactive experience. You get to see when they move materials in, know the quantity by zooming in, check if they are working or not. 100% transparency. Feel free to reach out to us on +2347046517600 mrfixerengineeringconstruction@gmail.com
|
Yesterday, we initiated the process of laying concrete blocks, and as of today, we have successfully completed four courses. Our objective is to continue working diligently so that by the weekend, we can reach the lintel level, marking a significant milestone in our construction progress.
|
The goal is to reach lintel level this week
|
3.4M is not to lay 4000 blocks but the price we got the blocks. A concrete block #850 * 4000 = #3.4m |
We have resume work today and for the block settings (concrete work excluded)here's the budget cost Using 4k blocks 1. 4k blocks 3 400 000 2. Sand 20 tons 160 000 3. Workmanship #480k 4. Miscellaneous like water pumping, drums... #96000 Total #4 133 000
|
Good morning |
We are starting the ground floor block settings first week of next month and hoping to do the slab work next month as well. |
Estate fee #180000 Trench digging #187800 Tree uproot #80000 Temporary store #250000 Iron rod and binding wire #1 185 000 Cement #970000 Sand and granite #1 000 000 Pegs, wood, nail for setting out #85000 Workmanship (carpenter and iron bender) #110000 Concrete footing (100mm) workmanship #180000 (mixer included) Wood, nail & Workmanship for formwork #294000 CCTV installation with monthly subscription #250000 Concrete block + setting out 2125 #1 785 000, (note; foundation total height is 2.25m due to the land conditions) Raising foundation reinforcement column up to 3m #895 000 Foundation plitch concrete beam #2 618 000 (reinforcement, formwork, sand and granite, workmanship included) Laterite filling (410tons) #3 075 000 (workmanship included) Miscellaneous like transportation, water ...#200000 Total for foundation to laterite filling #13 344 800 Below is total cost expenses spent from filling to dpc Materials Cement 2 000 000 Sand 265k Granite 450 000 + 320 000= #770k Polythene sheet 48k Nail for form work 8k Carpenter workmanship #25k Rammering 40k Plumbing 190k Fuel for pumping 10k Tanks for water 2big & 1 medium. Big is 2k per day, medium is 1k per day (#5k per day). Tuesday till Saturday Saturday 5 days. 25k. Concrete mixer 2 days = #122.5k Casting workmanship #208k (Day 1 150k + Day 2 58k) Miscellaneous like security, transportation... 107k TOTAL #3 819 500 GRAND TOTAL FOR FOUNDATION #17,163,500. The foundation total height is 2.5m because of the land conditions (#2.9m extra above budget). |
A total of 137 bags of cement was used, 40 tons of sand, 50 tons of granite
|
Let me highlight the benefits of a Damp Proof Course just to enlighten us A Damp Proof Course (DPC) is a critical component in building construction that prevents moisture from rising through walls and floors, offering several key benefits: 1. Prevents Structural Damage: DPC blocks capillary action, stopping moisture from seeping into walls, floors, and foundations. This protects the building from issues like weakened masonry, crumbling plaster, and deteriorating timber, ensuring long-term structural integrity. 2. Reduces Mold and Mildew Growth: By keeping moisture out, DPC minimizes the risk of mold and mildew, which thrive in damp environments. This promotes a healthier indoor environment and prevents respiratory issues or allergies caused by mold exposure. 3. Protects Interior Finishes: Moisture can damage paint, wallpaper, and plaster, leading to peeling, staining, or cracking. DPC helps maintain the aesthetic quality of interiors, reducing the need for frequent repairs or redecoration. 4. Improves Energy Efficiency: Damp walls lose heat more quickly, increasing heating costs. A properly installed DPC keeps walls dry, improving thermal insulation and reducing energy bills. 5. Increases Property Value: Buildings with effective damp proofing are more attractive to buyers, as they indicate a well-maintained structure with fewer future repair costs. DPC can enhance the marketability and longevity of the property. 6. Prevents Timber Decay: In buildings with wooden elements, DPC prevents moisture from reaching timber, reducing the risk of rot and insect infestations, which can compromise structural components like beams and joists. 7. Enhances Comfort: A dry building is more comfortable to live in, free from the damp, musty odors and cold, clammy conditions associated with moisture infiltration. 8. Cost-Effective Maintenance: Installing a DPC during construction or retrofitting it in older buildings prevents costly repairs caused by damp-related damage, saving money in the long run. By incorporating a DPC, builders and homeowners can ensure a durable, healthy, and cost-efficient living environment. DPC is a necessity because if you don't do it correctly or neglect it to save costs, you will end up spending more when the moisture begins to cause problems. Additionally, tiling the wall, screeding, or plastering won't prevent moisture from moving. Prevention is better than cure. Do it right and do it once.
|
Below is total cost expenses spent. Materials Cement 2 000 000 Sand 265k Granite 450 000 + 320 000= #770k Polythene sheet 48k Nail for form work 8k Carpenter workmanship #25k Rammering 40k Plumbing 190k Fuel for pumping 10k Tanks for water 2big & 1 medium. Big is 2k per day, medium is 1k per day (#5k per day). Tuesday till Saturday Saturday 5 days. 25k. Concrete mixer 2 days = #122.5k Casting workmanship #208k (Day 1 150k + Day 2 58k) Miscellaneous like security, transportation... 107k TOTAL #3 819 500
|
The completion of the Damp Proof Course concrete casting took place on Saturday, and the entire project incurred a total cost of 3,812,000.
|
As part of the preparations for the concrete casting scheduled for tomorrow, the Damp Proof Membrane installation was completed successfully. We used a membrane with a thickness of 500 microns (500µm), which is equivalent to a 2000 gauge (2000G) thickness. In terms of materials, we have supplied a total of 200 bags of cement, valued at #2,000,000, along with 20 tons of granite, priced at #320,000, to supplement the existing stock of 30 tons. Presently, we have an inventory that includes 40 tons of sharp sand, 50 tons of granite, and 200 bags of cement, ensuring we are well-equipped for the casting process tomorrow.
|