Construction Of Eight(8) Room Self Contain - Properties - Nairaland

Nairaland ForumNairaland GeneralPropertiesConstruction Of Eight(8) Room Self Contain (1924 Views)

1 Reply (Go Down)

Construction Of Eight(8) Room Self Contain by olukaygold(op):
Construction of 8rooms self contains,3700,45 cements,20tons of Granite/Gravel are budgeted for the completion of the building.Sands are already available on the land.
First day, clearing of the land and uprooting the tree

Re: Construction Of Eight(8) Room Self Contain by olukaygold(op): 2:02pm On Apr 14, 2021
Moulding of blocks...3500 blocks are budgeted to raise the Eight(cool Self Contains from the foundation to roofing level... Keep following

Re: Construction Of Eight(8) Room Self Contain by keeper303: 3:30pm On Apr 14, 2021
Where is the location?
Re: Construction Of Eight(8) Room Self Contain by olukaygold(op): 3:57pm On Apr 14, 2021
keeper303:
Where is the location?
Ado-Ekiti sir. not far from the first site
Re: Construction Of Eight(8) Room Self Contain by olukaygold(op):
Work in Progress
Casting of the foundation

Re: Construction Of Eight(8) Room Self Contain by olukaygold(op): 6:43pm On Apr 20, 2021
Progressing...done with foundation with 600 blocks,and 15bags of cement used for both casting of the foundation and setting of the foundation blocks.

Re: Construction Of Eight(8) Room Self Contain by olukaygold(op): 10:48am On Apr 25, 2021
Good morning and happy Sunday
Here's my work update for today.
We've used 21bags of cement so far,15bags for casting and block settings of the foundation.6bags to raise the blocks from the foundation to this level. 2000blocks have been used so far

Re: Construction Of Eight(8) Room Self Contain by ajisco2010: 8:49am On Feb 12, 2022
Update
Re: Construction Of Eight(8) Room Self Contain by Orubebe01: 3:56pm On Apr 26, 2022
olukaygold:
Good morning and happy Sunday
Here's my work update for today.
We've used 21bags of cement so far,15bags for casting and block settings of the foundation.6bags to raise the blocks from the foundation to this level. 2000blocks have been used so far
Update us
Re: Construction Of Eight(8) Room Self Contain by olukaygold(op): 9:02pm On Apr 26, 2022
Orubebe01:
Update us
The project is on hold for now sir...
Re: Construction Of Eight(8) Room Self Contain by Vivianat(f): 3:27am On May 30, 2022
.