INVEST NIGERIA: NLNG Train 7 Timeline - July 2018 To June 2021 - Politics - Nairaland
Nairaland Forum › Nairaland General › Politics › INVEST NIGERIA: NLNG Train 7 Timeline - July 2018 To June 2021 (419 Views)
1 Reply
| INVEST NIGERIA: NLNG Train 7 Timeline - July 2018 To June 2021 by presidency(op): 3:27pm On Jun 15, 2021 |
July 2018: Search for an EPC contractor for Train 7 begins, with the signing of Front End Engineering Design (FEED) with two consortia, B7 JV Consortium and SCD JV Consortium, in a Dual FEED Process. Guaranty Trust Bank of Nigeria and Sumitomo Mitsui Banking Corp. (SMBC) are appointed as Financial Advisers for the Project. March 2019: NLNG and Nigerian Content Development Monitoring Board (NCDMB) sign off an approved plan for Nigeria Content (NC) for NLNG’s Train 7 Project. September 2019: NLNG issues Letter of Intent for the EPC Contracts of the Train 7 Project to SCD JV Consortium, comprising affiliates of Saipem, Chiyoda and Daewoo 27th December 2019: NLNG takes the Final Investment Decision (FID) on Train 7, at a ceremony in Abuja, Nigeria April 2020: Approval of the Nigerian Content Compliance Certificate (NCCC) and Approved Vendors Lists (AVLs) by the Nigerian Content Development and Monitoring Board (NCDMB). 13th May 2020: Nigeria LNG Limited (NLNG) awards the Engineering, Procurement and Construction (EPC) Contracts for the Train 7 Project to SCD JV Consortium, comprising affiliates of Saipem (Italy), Chiyoda (Japan) and Daewoo (South Korea) June 15th, 2021: President Buhari performs NLNG Train 7 Groundbreaking Ceremony, to formally mark the commencement of construction. Train 7 will increase the capacity of NLNG's current six-Train plant by 35% from the current 22 Million Tonnes Per Annum (mtpa) to 30mtpa. The Project is anticipated to create more than 12,000 new direct jobs (and as many as 40,000 new indirect jobs) during the construction stage, and will attract $12 billion in new investment into Nigeria. |
| Re: INVEST NIGERIA: NLNG Train 7 Timeline - July 2018 To June 2021 by uptimumOne23(m): 4:22pm On Jun 15, 2021 |
Baba Buhari doing wonders In one Nigeria we stand.. Anyone who doesn't want to belong in Nigeria can go and create their own DOT Nation in Mars |
| Re: INVEST NIGERIA: NLNG Train 7 Timeline - July 2018 To June 2021 by maxlev1: 7:38am On Jul 07, 2021 |
presidency:This is lovely. I would love to be part of this project by working there. Pls can you help in any way? I am educated and also trained and certified in various skills among which I have working experience. |
Protesting Workers Shut Down $10 Billion NLNG Train 7 Project • NLNG Train 7: Another Milestone In The History Of Nigeria’s Oil And Gas Industry • President Buhari Breaks Ground For Nigeria LNG Train 7 • 2 • 3 • 4
Watch What A Prophet Said About Nnamdi Kanu • Since Buhari Became President • White Supremacy. Why We Destroyed Nigerians, Surrendered Country To Fulani