| DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 7:37am On Jan 23, 2022*. Modified: 10:41pm On Sep 05, 2025 |
DeBridge Integrated Service Ltd is a Company based in South East and also covers South South in construction of residential and commercial building. Project title: Proposed Lecture Hall & Offices in for School of General Studies. We are handling the project as sub-contractor.
|
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 7:39am On Jan 23, 2022*. Modified: 8:02am On Jan 29, 2022 |
Work began since 7th January with foundation digging @#2500/pertition. Over priced due to hard nature of soil. One week work with column base @#500 each Picture taken on 16th. Blinging going on. |
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 7:42am On Jan 23, 2022*. Modified: 6:31am On Jan 29, 2022 |
Blinging of foundation and colums have taken almost 50 tons of granite and 6 trips of sand.
|
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 12:00am On Jan 24, 2022*. Modified: 3:15am On Mar 10, 2022 |
Laying of foundation started on Friday with the carpentry work starting today. The DPP and his engineers were on site last weekend to certify the foundation, columns, pillars, baskets measurement and quality of work being done.
|
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 12:11pm On Jan 26, 2022*. Modified: 6:28am On Feb 19, 2022 |
Done with laying (4000 blocks used, 5 Mansons worked for 5 days on counting @50/block. Filling starts immediatly. Expecting some trips of laterite. Mark budget is cheaper than tipper on the overall.
|
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 8:50pm On Jan 28, 2022*. Modified: 10:37pm On Sep 05, 2025 |
God has bless us with another contract. From South East to South South. |
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 3:19pm On Jan 29, 2022*. Modified: 6:28am On Feb 19, 2022 |
We just came back from PH and l visited site. Nothing happening for now. Two trips of mark for now. A little pause due to price disagreement which gave time to visit PH.
|
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by Tunami(m): 6:24pm On Jan 29, 2022 |
kalu61:Nice job |
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 9:43pm On Feb 07, 2022 |
Work has resume with full force now. The idea to dig the soak aways(3) came to save us the cost of few trips of filling sand.
|
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 11:28am On Feb 08, 2022 |
Spraying of Anti-termite insecticide
|
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 8:06pm On Feb 09, 2022*. Modified: 6:50pm On Feb 10, 2022 |
All the soak away have been completed but the excavated sand didn't meet our expectations. More filling sand coming tomorrow @30,000/mark
|
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 6:34pm On Feb 10, 2022 |
Filling continues with wetting of filled areas.
|
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 8:16pm On Feb 14, 2022 |
Getting ready for hard core laying
|
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 8:30pm On Feb 17, 2022 |
Rammering of the whole area @20,000/day
|
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 8:34pm On Feb 17, 2022 |
Ongoing placing of DPC membrane @9,000/10kg and laying of hard core @51,000/trip.
|
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 11:58am On Feb 27, 2022 |
We are set for the casting.
|
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 12:10am On Mar 02, 2022 |
The casting has started with full speed using mixer @20k/day and 14 labourers @700/bag
|
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 6:42am On Mar 02, 2022 |
The VC at the site yesterday for the project Laying Ceremony to mark his 1year in office.
|
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 9:25pm On Mar 02, 2022*. Modified: 3:16am On Mar 10, 2022 |
1.Casting continuation. 2. We have started the block work after forming this morning.
|
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 8:02pm On Mar 08, 2022 |
It's being a very tough week as God blessed GPowers with another project. I will creat a thread for that tomorrow. Mean while, sorry for not keeping you updated with our capital project. |
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 8:09pm On Mar 08, 2022 |
We completed the flooring on Monday with hand mixing. The mixer developed fault and had to be returned. Over 300 bags of cement @700/bag entered into this flooring with 2 masons/day for 6 days.
|
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 8:15pm On Mar 08, 2022 |
I had to form out block work for 3 masons today with my I.T students. I plan engaging about 4-5 masons tomorrow to lift the structure to lintel level all round if all things being equal. Sorry for the pictures quality. I took it as the rain was about to fall as l was leaving the site.
|
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 3:20am On Mar 13, 2022 |
Raising of the whole walls continues. Two masons will be on site today to complete everything block work to lintel level. It rained heavily yesterday and small portion (20 blocks) of the wall was destroyed by the rained because the wall was yet to set.
|
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 8:42am On Apr 15, 2022 |
We are back to site now to complete the project. 50% of the capital project has been released to the main contractor and all the reinforcement materials are on site now. Iron bender (4 persons) are speeding up the work. Cutting of iron, tying and mounting of the continuation pillars.
|
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 12:44pm On Apr 16, 2022 |
Boarding of the pillars have started. Two carpenters are seeing to that. Mounting of pillars still going on
|
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 10:13am On Apr 21, 2022 |
Reinforcements completed and boarding is still on going. Only one carpenter is in the site now, the others have moved to PH for our work at Sun City Garden Estate Port Harcourt. You can check my profile for the thread.
|
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 8:20am On May 02, 2022 |
Casting of beans and columns started last week. Sorry, for not being able to update you.
|
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 8:25am On May 02, 2022 |
The boards of most of the areas are yet to be loosen. The main focus this week will the the front columns as seen in the last picture. Each column is estimated to take 2 and half bags of cement.
|
| Re: DeBridge Integrated Service Building Of Proposed Lecture Hall & Offices In MOUAU by kalu61(op): 10:35am On May 02, 2022 |
Happy Eid Mubarak! to all Muslim faithfuls.
|
The Construction Of Proposed 4bedroom Duplex • Construction Of 8 Bedroom Duplex At Umuahia North By DeBridge Integrated Service • Building Of My Cheap Self Cons with Pics • 2 • 3 • 4
Dezyns And Structures • Nicely Finished 4bedroom Bungalow At Sholebo Estate Ebutte Ikorodu. PIXXX • First City To Generate All Its Electricity From Wind Turbines