Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op): 2:25pm On Nov 15, 2025
bixton:
Well I don't know those who have it installed like that you use.....

But I'm used to it being installed like this and I have my right hand to hold it and place in position for left hand to wash bumbum.
Yes right hand to hold it and left hand to clean bum
That is what I explained and it in pics as that
Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by bixton(m): 2:30pm On Nov 15, 2025
rotecch77:
Yes right hand to hold it and left hand to clean bum
That is what I explained and it in pics as that
I think they are different...


Pic 1......Yours
Pic 2......Mine..

Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op): 2:44pm On Nov 15, 2025
I can see my is right while yours is left.
But the best convenient position is right fixed.
It’s stress free try it next time you will see
Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by bixton(m): 3:03pm On Nov 15, 2025
rotecch77:
I can see my is right while yours is left.
But the best convenient position is right fixed.
It’s stress free try it next time you will see
I am sure you do use it also.
Please kindly explain how you do it given your position as installed?
Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op): 3:22pm On Nov 15, 2025
bixton:
I am sure you do use it also.
Please kindly explain how you do it given your position as installed?
As I explained earlier up there that is the way now
But sometimes ago we do position it on left hand as yours but few years now we do it as It’s shown on my thread now…. You know we learn things everyday to make life easier
Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op): 2:27pm On Nov 17, 2025
Watch out for more update
Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op): 5:39pm On Nov 17, 2025
Life update

Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op):
Still in progress

Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op): 3:50pm On Nov 25, 2025
More

Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op): 7:34pm On Nov 25, 2025
We don’t compromised with quality materials and quality work
Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op): 9:22am On Nov 28, 2025
Children game house/fun fare section finishing is in progress

Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op): 9:26am On Nov 29, 2025
Gym section

Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op): 4:54pm On Nov 29, 2025
More pics loading
Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op): 3:47pm On Dec 03, 2025
External

Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op):
Double size septic tank 24ft x12ft x10ft

Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op): 1:15pm On Dec 11, 2025
More update coming soon
Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op): 12:41pm On Dec 12, 2025
Checking for leakage before tiling of the pool

Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op): 10:40am On Jan 15
External work is in progress.. floor filling and leveling, mechanical work etc

Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op):
Steel cantilever canopy
2mtrs long

Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op): 2:54pm On Jan 22
More update loading
Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op): 10:47am On Jan 23
More

Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op): 5:55pm On Jan 30
Priming is in progress with quality primer paint

Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op): 7:36am On Feb 01
Still in progress
Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op):
Pool mechanical work

Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op):
Wall preparation for painting still in progress

Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by Greenarrow01(m): 8:46am On Mar 11
rotecch77:
Wall preparation for painting still in progress
Good morning @rotecch77
Pls how many plots of land is the total land for everything on this project. From the hall to the bakery and the games center.
How many square meters pls


And do you have any idea or are you willing to disclose the amount spent so far ?
Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op): 10:38am On Mar 12
Greenarrow01:
Good morning @rotecch77
Pls how many plots of land is the total land for everything on this project. From the hall to the bakery and the games center.
How many square meters pls


And do you have any idea or are you willing to disclose the amount spent so far ?
Good morning chief.
The total landed area is 3plots of land
The initial budget for the project was N250m for the Hall and the gym/ eatery building

Later we added Game Center, bakery, swimming pool and others utilities building to it.
Total cost will be added to the initial N250m which will be posted here later
Thanks

Game Center and bakery pics

Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by Greenarrow01(m): 2:33pm On Mar 12
rotecch77:
Good morning chief.
The total landed area is 3plots of land
The initial budget for the project was N250m for the Hall and the gym/ eatery building

Later we added Game Center, bakery, swimming pool and others utilities building to it.
Total cost will be added to the initial N250m which will be posted here later
Thanks

Game Center and bakery pics
Thank you so much for your reply


For something like this

pls guys I just need a quick advise. Will 3 plots of land be enough for an event centre. It will have 2 seperate halls (700 and 250 banquet halls)
2. Space for pictures, kitchen, 20-30 cars park, generator area, changing room, a mini store, and 10 toilets.

2. Small outdoor space of 200-300sqm area for garden wedding and events






how many plots will be enough and roughly how much will run it. Osun state (not Lagos ooh.
Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op): 3:52pm On Mar 12
Greenarrow01:
Thank you so much for your reply


For something like this

pls guys I just need a quick advise. Will 3 plots of land be enough for an event centre. It will have 2 seperate halls (700 and 250 banquet halls)
2. Space for pictures, kitchen, 20-30 cars park, generator area, changing room, a mini store, and 10 toilets.

2. Small outdoor space of 200-300sqm area for garden wedding and events






how many plots will be enough and roughly how much will run it. Osun state (not Lagos ooh.
It’s should be enough but it depends on good arrangement and construction
We can handle such for you sir if you don’t Mind
Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op): 3:10am On Mar 18
External work still in progress
Another massive project as this is loading
Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op): 7:07am On Mar 22
More Pics loading …

Re: Construction Of Royal Hall And Mega Eatery By Arbo Contractor Ltd by rotecch77(op): 8:48am On Mar 28
More

1 2 3 ... 7 8 9 10 11 Reply

Remodeling Of Old Duplex To Modern Type By Arbo Contractor Ltd ( Rotech77Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTDThe Erecting journey of 2stories building of 12 flats by Arbo Contractor Ltd234

3,000 Litres Water Tank With 7ft Iron Stand For SaleBuy: Granite,marble And Tiles From Major Importer In Nigeria.Brand New Korean Perkins Soundproof 10KVA To 500KVA Generators