Cost Of Building A Four Bedroom Bungalow - Properties - Nairaland

Nairaland Forum / Nairaland / General / Properties / Cost Of Building A Four Bedroom Bungalow (1869 Views)

A Newly Completed Four Bedroom Bungalow With Pictures By A Young Engr / Cost Of Building A House In Nigeria / Construction Of Four Bedroom Bungalow, Onicha-ugbo, Delta State (2) (3) (4)

(1) (Reply) (Go Down)

Cost Of Building A Four Bedroom Bungalow by cacali(f): 3:57pm On Mar 02, 2015
Please can anyone advise on cost of building a four bedroom bungalow to carsass/lintel level. Land to be built on is dry land.
Re: Cost Of Building A Four Bedroom Bungalow by fendorf(m): 5:08pm On Mar 02, 2015
Contact us for your Granite,stone dust,sharpsand and sandfilling. 07064696356
Re: Cost Of Building A Four Bedroom Bungalow by klassicomega(m): 9:00pm On Mar 02, 2015
3500 blocks which can be either 6" or 9" @ 130 (6") =455000
45bags of cement @ 1900= 85500
1 load of gravel - 25000
Sand for setting block-80000
Workmanship-250000
Total-#890,500
Further enquiries
Call-08175912298
Re: Cost Of Building A Four Bedroom Bungalow by eghosajohnny: 2:32am On Mar 03, 2015
cacali:
Please can anyone advise on cost of building a four bedroom bungalow to carsass/lintel level. Land to be built on is dry land.

The question is where the plot is located

25 trucks of laterite @8000 =200k
Sand 4trucks @15,000 =60,000
Blocks 3,300@120= 396,000
Cement 50bags@ 1,900=95,000
Filling labour=40,000
Labour mason=220,000
Gravel 1truck=23,000

Sub total=1,044,000
Or granite 45,000

German floor
Sand 1truck @15,000=15,000
Gravel 15tons@46,000=46,000
Cement 30bags@1,900=57,000
Labour 50,000

Sub total=168,000
=1,044,000
Re: Cost Of Building A Four Bedroom Bungalow by cacali(f): 9:15am On Mar 03, 2015
Thank u so much. You've been quite helpful.
eghosajohnny:


The question is where the plot is located

25 trucks of laterite @8000 =200k
Sand 4trucks @15,000 =60,000
Blocks 3,300@120= 396,000
Cement 50bags@ 1,900=95,000
Filling labour=40,000
Labour mason=220,000
Gravel 1truc

Sub total=1,044,000
Or granite 45,000

German floor
Sand 1truck @15,000=15,000
Gravel 15tons@46,000=46,000
Cement 30bags@1,900=57,000
Labour 50,000

Sub total=168,000
=1,044,000

(1) (Reply)

To Let Tastefully 4bedroom Duplex + Relaxation @ Lekki Phase 1 (pics) For 2.7m / Check 3bed Bungalow Decking Set-back With 3shops Decked In Lagos With Cofo N15m / 3bed Flat With BQ In Alexandra Quarter,hopeville Estate,sangotedo Ajah (pics)

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 8
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.