Re: My Building Process: 3 Bedroom Bungalow by comprende(op): 4:39pm On Aug 14, 2016
More

Re: My Building Process: 3 Bedroom Bungalow by comprende(op): 4:48pm On Aug 14, 2016
Eventually did as advised. Two coaches/courses outside walls and three interior walls.

Next stage concrete fascia and roofing but make I drink small water first.... grin

As per cost incurred.

Foundation approx 980k, would have cost less if not for corrections made, raising the building up to this point cost approx 1.120m...all in.
Re: My Building Process: 3 Bedroom Bungalow by 2sexynet: 7:05am On Aug 15, 2016
comprende:
Eventually did as advised. Two coaches/courses outside walls and three interior walls.

Next stage concrete fascia and roofing but make I drink small water first.... grin

As per cost incurred.

Foundation approx 980k, would have cost less if not for corrections made, raising the building up to this point cost approx 1.120m...all in.
you mean you foundation alone cost 980k approximately and from foundation to this stage you spent another 1.120M? Am I right?
Re: My Building Process: 3 Bedroom Bungalow by fabulous85: 7:16am On Aug 15, 2016
2sexynet:
you mean you foundation alone cost 980k approximately and from foundation to this stage you spent another 1.120M? Am I right?
am also suprised. it is too much
Re: My Building Process: 3 Bedroom Bungalow by 2sexynet: 7:23am On Aug 15, 2016
fabulous85:
am also suprised. it is too much
let's wait to hear from him smiley
Re: My Building Process: 3 Bedroom Bungalow by comprende(op): 8:41am On Aug 15, 2016
2sexynet:
let's wait to hear from him smiley
I would appreciate your opinions please.

What would have been a fair amount?
Re: My Building Process: 3 Bedroom Bungalow by johnson232: 9:28am On Aug 15, 2016
abouzaid:
first i would advice you to go with three courses of block, because of pop, secondly, a house with high ceilings would definitely be cooler than one with a low ceiling according to simple physics, third, you used pillars on your house because you would be installing parapet/concrete fascia which is very heavy because it's made from reinforced concrete, that's probably why your builder asked you to use two blocks on the outside walls since the concrete fascia would act as the third wall, you can crosscheck this with your builder since only him knows his reason.
if u are not an architect, u must be an engineer to know all these...

well said sir...
Re: My Building Process: 3 Bedroom Bungalow by johnson232: 9:31am On Aug 15, 2016
2sexynet:
you mean you foundation alone cost 980k approximately and from foundation to this stage you spent another 1.120M? Am I right?
didn't u see the german floor?