Welcome, Guest: Register On Nairaland / LOGIN! / Trending / Recent / New
Stats: 3,152,961 members, 7,817,818 topics. Date: Saturday, 04 May 2024 at 08:22 PM

BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd - Properties - Nairaland

Nairaland Forum / Nairaland / General / Properties / BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd (2392 Views)

Bitsworks Project Memoirs: Construction Of A Church Auditorium Surulere Lagos / BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla / Bitsworks Project Memoirs: Construction Of 4 Units Of 2 Bedrooms Flat Ikorodu (2) (3) (4)

(1) (Reply) (Go Down)

BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 7:52pm On Mar 30, 2017
BITSWORKS Nigeria is a multi-discipline construction company comprising of architects, builders, civil engineers and interior designers.

We currently have a brief for a client to construct 4 units of 2 bedrooms flats on a plot of land in Mowo-Kekere, Ikorodu. There is an existing bungalow in the land already but it is a fairly flat terrain.

We will share the floor plan, elevations and 3D views once we have finalized on the design and permission has been given by the client.

Size of land - 640 sqm
Total area of building - 168.4sqm

Estimated budget for construction - currently unknown
PROJECT timeline - 10 months

We have started with the foundation work and work is moving at a steady pace. Excavation and blinding of the foundation has been completed.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 8:00pm On Mar 30, 2017
Block setting of the foundation, we are using 9" vibrated blocks .

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by chuksjuve(m): 8:23pm On Mar 30, 2017
Nice one...keep us updated..

for your landscape and beautification, kindly contact us by checking our profile for more details..

keep it up
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 5:57am On Mar 31, 2017
More block setting work pictures.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 6:03am On Mar 31, 2017
chuksjuve:
Nice one...keep us updated..

for your landscape and beautification, kindly contact us by checking our profile for more details..

keep it up

Noted sir. Thanks for the kind words.
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 6:06am On Mar 31, 2017
Four coach of block setting was achieved and the foundation was high enough. Work on the short columns in progress.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by Onuokwu: 4:57pm On Mar 31, 2017
Can you share the plan of this house please?
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 10:26am On Apr 01, 2017
Backfilling of the foundation trenches in progress.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by mufutau55(m): 12:47am On Apr 02, 2017
Very good straight line block laying work. Keep it up.

Hajji M.
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 1:16pm On Apr 02, 2017
Reinforcement mat work on the backfilled foundation. We are using 10mm rebars and spacing at 300mm (1foot) CC.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 5:51am On Apr 08, 2017
mufutau55:
Very good straight line blocking laying work. Keep it up.

Hajji M.

Thank you Hajji M.
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 6:04am On Apr 08, 2017
Casting of the german floor after the reinforcement mat was completed. Manual mixing was used and it was completed in 2 days.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 6:24am On Apr 08, 2017
More casting pictures of the oversite concrete (german floor).

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 12:17pm On Apr 09, 2017
Block setting in progress once the german floor was completed. We are using 9" and 6" blocks.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 4:29pm On Apr 09, 2017
More block setting pictures.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 6:15am On May 13, 2017
Lintel and columns work in progress.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 6:27am On May 13, 2017
Carpentry formwork for the suspended slab (decking) ongoing.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 6:42am On May 13, 2017
After completion of the decking platform, reinforcement work started.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 6:55am On May 13, 2017
Reinforcement work almost complete, staircase formwork and labourer stairs for casting.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by TenPassfour(m): 7:22am On May 13, 2017
Goodjob
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 7:50am On May 13, 2017
All set for casting of the suspended floor slab (decking) and we did the casting on Friday May 12th 2017.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 9:04am On May 13, 2017
TenPassfour:
Goodjob

Thank you.
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 9:06am On May 13, 2017
More pictures of the suspended floor slab casting.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 12:22pm On May 13, 2017
Suspended floor slab casting concluded.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by Nobody: 8:27am On May 16, 2017
Nice job.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 8:12am On May 20, 2017
StainlessH:
Nice job.

Thank you. BR
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by adewaleID: 8:24am On May 20, 2017
Look good, well done grin
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by wazobiaman: 8:32am On May 26, 2017
Buddy, can u give me a rough estimate of list of materials including no of planks to use for roofing of,

L= 50ft

B= 30ft

I will really appreciate

The roof style is Hip Roof
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS: 7:30am On May 29, 2017
The decking has been left to cure for 14 days plus now and we will be starting the first floor block setting soon.

(1) (Reply)

The Diamond Estate Phase 2,lekki Season Promo. Enjoy A N2m Discount Off!!! / What Is The Meaning Of Free Hold - Its A Property Title - Know Before You Buy / Own A Unit Of Our 3 Bedroom Semi Detached Duplex With BQ With N3m Deposit.

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 18
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.