Nairaland Forum / Nairaland / General / Politics / Pipelines, Flourmill Factories Causing Delay In Linking Lagos Rail To Seaport (10396 Views)
Lagos Red Line Rail To Be Commissioned On February 29th By President Tinubu / More Pipelines Arrive Kaduna Ahead Of The $2.8bn AKK Gas Project Ground Breaking / Obasanjo Criticizes Ambode For Abandoning Lagos Rail Project (2) (3) (4)
Re: Pipelines, Flourmill Factories Causing Delay In Linking Lagos Rail To Seaport by Nobody: 8:06am On Oct 06, 2019 |
Oloyedecherry: 1 Like
|
Re: Pipelines, Flourmill Factories Causing Delay In Linking Lagos Rail To Seaport by damoceile: 8:12am On Oct 06, 2019 |
whatever happened to constructing over head bridges that will specifically be for railways like they have in all these developed countries... or are there factories and pipelines in the air?? ... if they are truly serious and wants to really help our economy all the aforementioned things won't be an hindrance at all.. |
Re: Pipelines, Flourmill Factories Causing Delay In Linking Lagos Rail To Seaport by Nobody: 8:47am On Oct 06, 2019 |
Excuse Me government
|
Re: Pipelines, Flourmill Factories Causing Delay In Linking Lagos Rail To Seaport by TheAlchemist: 8:56am On Oct 06, 2019 |
revenge001: flourmill will make a killing either way, everybody involved must chop the national cake. |
Re: Pipelines, Flourmill Factories Causing Delay In Linking Lagos Rail To Seaport by fyneguy: 9:12am On Oct 06, 2019 |
revenge001: Why are you happy that the project is stalled? |
Re: Pipelines, Flourmill Factories Causing Delay In Linking Lagos Rail To Seaport by Nobody: 9:16am On Oct 06, 2019 |
revenge001: How much value does an individual add compared to Flour mills -Jobs, taxes, CSR etc. I would gladly and quickly compensate Flour Mills for relocation, if I were the government. |
Re: Pipelines, Flourmill Factories Causing Delay In Linking Lagos Rail To Seaport by harley88(m): 9:22am On Oct 06, 2019 |
Rensolar: Absolutely no sense in what you typed |
Re: Pipelines, Flourmill Factories Causing Delay In Linking Lagos Rail To Seaport by onadana: 9:47am On Oct 06, 2019 |
rman: I just tire for this people. |
Re: Pipelines, Flourmill Factories Causing Delay In Linking Lagos Rail To Seaport by mamaafrik(m): 10:05am On Oct 06, 2019 |
And one silly Sudanese goat will be calling youth LAZY,Lazy Federal Government and Ministry of Work and Transportation. |
Re: Pipelines, Flourmill Factories Causing Delay In Linking Lagos Rail To Seaport by Lokostic77: 10:10am On Oct 06, 2019 |
Fariq:northerners wont let this project see light of the day becsuse of their trailers, meanwhile this project would have help us reduce truck accidents in our society, God pass them |
Re: Pipelines, Flourmill Factories Causing Delay In Linking Lagos Rail To Seaport by olaniyilukman(m): 10:28am On Oct 06, 2019 |
It is sad what is happening in Nigeria. The urban and regional planning has fails in this regard, didn't they knew before allocating land to foreigners to build factories that it is rail way track... |
Re: Pipelines, Flourmill Factories Causing Delay In Linking Lagos Rail To Seaport by Fariq: 11:37am On Oct 06, 2019 |
Oloyedecherry: The initial design is from Iju to Ibadan & that has been achieved. But this government want to extend it to Apapa based on their new policy that all railway must terminate at the seaport. |
Re: Pipelines, Flourmill Factories Causing Delay In Linking Lagos Rail To Seaport by Fariq: 11:40am On Oct 06, 2019 |
Lokostic77: This has nothing to do with Northerners. Carry your conspiracy theory look elsewhere. |
Re: Pipelines, Flourmill Factories Causing Delay In Linking Lagos Rail To Seaport by Mcreloaded(m): 12:01pm On Oct 06, 2019 |
No problem without solution. Who do we now blame for this gross error, is it the contractor or the government or both. Unless they just drew a straight line on a map from Ibadan to Lagos port and quoted figures from thin air to construct this railway line without checking if there are obstacles. Any way sha like i said there is no problem with out solution it is only a matter of smart thinking like this pic shows bellow. 1 Like
|
Re: Pipelines, Flourmill Factories Causing Delay In Linking Lagos Rail To Seaport by Lucky5000(m): 12:27pm On Oct 06, 2019 |
Indirectly saying the project will be completed by 2023, another scam |
Re: Pipelines, Flourmill Factories Causing Delay In Linking Lagos Rail To Seaport by Felicity001(m): 12:37pm On Oct 06, 2019 |
Just imagine the level of ignorance. Didn't they carry out a survivor and proper mapping before they came up with the blue print? So they just mapped it on the air, ok the rail will go through this path and end here. Foolishness in the highest order. And money has been approved. The next thing now is abandonment. Useless country |
Re: Pipelines, Flourmill Factories Causing Delay In Linking Lagos Rail To Seaport by heysquare(m): 1:08pm On Oct 06, 2019 |
Shoodboi:Not as if the project is would not b completed but it might take more extension than earlier scheduled. For instance, there's a another bridge that on going now at Constain which after completion would allow for demolition of the old bridge which is too low for the transit of d train. Serious work is really going on there. Each time I pass through that area I awls commends Amaechi for d good job |
Re: Pipelines, Flourmill Factories Causing Delay In Linking Lagos Rail To Seaport by sulaak(m): 1:20pm On Oct 06, 2019 |
Luvinghubby: The Chinese are not cheating, they are factoring the enormous bribes they have to pay Nigerian politician. |
Re: Pipelines, Flourmill Factories Causing Delay In Linking Lagos Rail To Seaport by Nobody: 2:15pm On Oct 06, 2019 |
It's not even the completion of this mythical railway that worries me. It's the maintenance that will come afterwards. Or not |
Re: Pipelines, Flourmill Factories Causing Delay In Linking Lagos Rail To Seaport by ukahrawah: 3:23pm On Oct 06, 2019 |
The Nigerian govt ought to know that this problem can be resolved by constructing a tunnel deep below the obstructions. |
Re: Pipelines, Flourmill Factories Causing Delay In Linking Lagos Rail To Seaport by Rensolar(m): 4:02pm On Oct 06, 2019 |
harley88: OK bye |
Re: Pipelines, Flourmill Factories Causing Delay In Linking Lagos Rail To Seaport by Rensolar(m): 4:03pm On Oct 06, 2019 |
Inflammatory: Private chat me pls |
Re: Pipelines, Flourmill Factories Causing Delay In Linking Lagos Rail To Seaport by tck2000(m): 5:24pm On Dec 17, 2019 |
, |
LASTMA To Punish Bribe Taking Officer, Monsurat Akinleye / Emefiele: We’ll Toll Roads To Repay Infrastructure Debts / 2023: APC Cancels Nomination Fees For Female Aspirants
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 27 |