Welcome, Guest: Register On Nairaland / LOGIN! / Trending / Recent / New
Stats: 3,152,661 members, 7,816,697 topics. Date: Friday, 03 May 2024 at 03:30 PM

Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) - Properties - Nairaland

Nairaland Forum / Nairaland / General / Properties / Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) (1652 Views)

Remodelling And Reconstruction Of A Town Hall In Pictures / All Interior Redesign - Reconstruction Works of Dennis3D / Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. (2) (3) (4)

(1) (Reply) (Go Down)

Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 12:57pm On Jan 24, 2020
Good afternoon and happy new year.
Welcome to my new photo diary of an ongoing remodeling job.
Project info:
Existing building had a pharmacy, a dispensing room, a store room, two small bedrooms and a lounge.

New structure is to have a pharmacy, one bedroom with convenience facilities, a store room, a dispensing room, a lounge and an extra convenience for pharmacy staffs.

Project Location: Azumini Ndoki I'm Ukwa East L.GA Abia State.
Estimated cost 4million naira.
Expected project duration: 1months and 3weeks.
Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 12:59pm On Jan 24, 2020
Pictures
1. Old building before commencement of work.
2-3. Expected final finishing barring any last minute changes.

Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 1:03pm On Jan 24, 2020
Today..we're removing the unnecessary wall and moving the debris away from site.
I'm optimistic we can as well begin excavations for the new walls needed ASAP.


More photo updates on the way...stay tuned.

Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by ArcToyin(m): 1:28pm On Jan 24, 2020
Well done!!! Did you put up any design for old and new structure?
Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 4:41pm On Jan 24, 2020
ArcToyin:
Well done!!! Did you put up any design for old and new structure?

Thank you.
First picture is the old structure, second and third pictures are the model for the proposed structure.
Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 4:42pm On Jan 24, 2020
Excavations...

Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 8:29am On Jan 25, 2020
Good morning.
We're continuing with excavations..plan is to round up today and then cast the foundation concrete.
Depth: External walls is 900mm
Internal walls is 600mm.

Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 2:36pm On Jan 25, 2020
Foundation concrete works (Blinding), iron works.

Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 10:22am On Jan 27, 2020
Good morning an welcome back after the weekend break.
Saturday saw us begin and finish the foundation blinding. Today we start block works while also preparing rebar.

Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 6:43pm On Jan 27, 2020
Afternoon updates..

Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 10:36am On Jan 29, 2020
Good morning to everyone following, sorry I couldn't update yesterday ad I had assignments on another site to follow up.
On my return this morning, this is how far we've gone.

Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 3:56pm On Feb 02, 2020
UPDATES!!

Good afternoon and a happy Sunday.
Been unavoidably absent from site for a couple of days, just returned today and went straight to appraise the label of work done..a few pictures below.
Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 3:56pm On Feb 02, 2020
UPDATES!!

Good afternoon and a happy Sunday.
Been unavoidably absent from site for a couple of days, just returned today and went straight to appraise the level of work done..a few pictures below.
pillars have been cast up to lintel levels, with lintel reinforcements placed on and firmly hooked at the joints.
Windows openings have also been clearly marked out, save for a couple of them and a door opening which unavoidably fell in the position of an old wall..they will be opened up after the walls are firmly secured.

1 Like 1 Share

Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 4:02pm On Feb 02, 2020
Like I said earlier at the beginning of the thread, the 3-D image is the target output of the remodeling project except of course if there were changes midway, well, such a change occurred and I will update the design image accordingly, but later.
Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Perfecttouchade: 4:18pm On Feb 02, 2020
Great work @josnac..We fabricate Aluminium windows in Casement, casement burglary embedded, sliding, curtain walls /windows. You can reach out to us via 08153665659 WhatsApp.. thanks
Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 12:02pm On Feb 04, 2020
Perfecttouchade:
Great work @josnac..We fabricate Aluminium windows in Casement, casement burglary embedded, sliding, curtain walls /windows. You can reach out to us via 08153665659 WhatsApp.. thanks

Okay Sir.
Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 12:05pm On Feb 04, 2020
Some updates for today.
Lintels are done, front beams and leveling are in progress.

Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 8:15am On Feb 07, 2020
Good morning and sorry for the delayed updates. we have levelled up and roofing will commence by next Monday. Got a picture here and a video, but can't send the video.

Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 2:01pm On Feb 10, 2020
Hello guys,
I'm back to the site today as we commence the roofing work.
There was a little adjustment during the block works and we had to increase the entrance porch to the pharmacy, thus our previous roof design was dropped in favour of the new one.

Josnac:
Pictures
1. Old building before commencement of work.
2-3. Expected final finishing barring any last minute changes.

So, here I've got a few photos to share as usual.
Suffice it to say my clients brother is a Carpenter, he's handling the woodworks here and I believe he can do justice to the roof.

Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 4:51pm On Feb 13, 2020
Roof woodworks..

Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 8:21am On Feb 21, 2020
Hello guys, good morning and sorry for the delayed updates.
We've rounded up the roofing job, just been busy with other assignments.
Will bring more photos as soon as I can.

Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 6:59am On Feb 27, 2020
Electrical piping..

Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 6:48am On Mar 27, 2020
Hello...
Good day and welcome back. Sorry for the delayed updates as I've been out of the state on other site engagements. On my return, ceiling, plumbing, electrical piping and drawing of cables have been concluded. Also the plastering is done, save for areas that would be tiled.

Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 5:42pm On Jun 24, 2020
Completed!!

(1) (Reply)

Curcel Concept.. For Your Estate Landscaping. Pavining. Flood Control And Suppl. / Who Knows A Really Good Block Industry In Lagos/ibadan? / 3 B

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 23
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.