Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 6:56am On Dec 04, 2019 |
Good day all..I'm really not much of a writer, but I'll make the post as concise as possible. Here we go... So mid-july I was contacted to design/build a 6-bedroom country home for a client in Ikwuano, Umuahia, project was expected to kick start in early 2020 and would serve as a replacement for their father's aged 4-bedroom bungalow. So in view of the expected commencement, sample designs were prepared and one exceptionally stood out..he loved it! 3-4 weeks later, my client lost his Dad.. oh, that was a tragedy! Bad news for us right? Anyway, the family met, the old man is to be buried this December...so what's to be done regarding the old house? where will people stay when they come for this burial? These and many more were questions my client battled with. But in the end, for every option on the table, funds seemed to be an issue but finally, we decided to remodel the old house, add new structures to it and provide sanitary facilities inside.. yea! Modified: Now I got the photos of the old house.. 1 Like
|
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 7:00am On Dec 04, 2019 |
photos: The old building after the roof were pulled off. I'll look for the photos when the roofs were still on. It had; 1. 3-rooms (the larger one served as the lounge, barely 3.3m by 3m, the other 2 were mostly 3m by 3m). 2. 2 smaller rooms at the extreme left. 3. an off site pit toilet (yea, na village house) 1 Like
|
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 7:18am On Dec 04, 2019 |
Continuing... So, looking at house, my client opted for a new and larger lounge 5.5m by 5.25m, a new room 3.6m by 3.45m and a spacious entrance porch 3.6m by 2.5m. Also the small er rooms were knocked off and 2 toilets/bath provided in their stead So, the estimates were prepared and materials provided, and we set to work. N/B: Materials purchases were done by him, but in line with the provided estimates.
|
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 7:33am On Dec 04, 2019 |
Oh, well..we had a little twist after the initial arrangements and excavations. One more room was to be added, bringing the total to 2 new bedrooms, a lounge, entrance porch and 2 toilets. The work continued. So for the existing building, we found out it was built using 4" blocks (4inch blocks)..yea, its that old. Now, how do you add extra 3-courses of block work using 5" blocks on an older wall built with 4" blocks?? ..and then also expect it to handle the roof load? Pillars and beams! yes, pillars and beams are the answer. So, basically we cracked the old walls at a spacing of about 3m intervals for pillars to be installed and also areas with progressive cracks from the foundation up to the old roof were cracked up and reinforced. The pillars were 0.125m by 0.225m reinforced by 3-12mm rods. 3 Likes
|
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 7:48am On Dec 04, 2019 |
So, back to the foundation works. New foundation depth for our addition was 2feet or 0.6m. Blinding concrete was 5inches or 0.125m.
|
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 7:53am On Dec 04, 2019 |
Block works...
|
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 7:58am On Dec 04, 2019 |
You can drop questions if you're following.. more updates later. Got to go to work. |
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 1:22pm On Dec 04, 2019 |
More updates: Iron works, Carpentry and block works going on simultaneously.
|
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 1:29pm On Dec 04, 2019 |
Leveling:
|
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 1:33pm On Dec 04, 2019 |
Roofing: Roof area = 288.1Sqm Expected roof height = 4.2m Ceiling type= PVC ceiling. Roofing sheet type: longspan aluminum (0.4mm) 1 Like
|
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 1:44pm On Dec 04, 2019 |
Ongoing today:
Septic tank/soakaway pit .block works continue.
plastering continues.
PVC ceiling installation commences. |
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 1:45pm On Dec 04, 2019 |
Ongoing today: Septic tank/soakaway pit .block works continue. plastering continues. PVC ceiling installation commences. 95% of aluminum frames for windows installed already.
|
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 11:10am On Dec 05, 2019 |
Good day all..today we continue with the plastering while fixing door frames and work also continue on the PVC ceiling.
|
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Hum2020: 12:10pm On Dec 05, 2019 |
@josnac you are doing wonderful job there but I may ask how much is total cost of this building work and how is the cost of Labour's down in the east thanks 3 Likes |
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 12:20pm On Dec 05, 2019 |
Hum2020: Thank you Sir. To your question, we are yet to recalculate how much that has been spent so far..being a structure in the village, some materials like wood and sand were sourced locally at a far cheaper rate than what was in the initial estimates. Now for labour in the East, I would say its relatively low based on how I work with my team. But I'm certain it differs from contractor to contractor. 2 Likes |
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 6:37pm On Dec 07, 2019 |
We continue with the plastering, doors and window dressing. Window hoods being moulded also while PVC ceiling is 90% complete. 1 Like
|
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by tonididdy(m): 6:54pm On Dec 07, 2019 |
Josnac:Well done � 2 Likes |
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 7:03pm On Dec 07, 2019 |
tonididdy:Thanks you Sir. |
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 8:36am On Dec 10, 2019 |
Updates: All internal doors are fixed and being dressed. Floors are primed in readiness for tiling...and we also commenced installation of the window hoods. Everything about plastering is to be rounded up today hopefully, the burial fast approaches. 3 Likes
|
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 8:43am On Dec 10, 2019 |
I must commend the doggedness and commitment of the guys working with me here..they deserve some real accolades. Would be going off site today or tomorrow for some other engagements, so it means next updates would most probably be at the finished stage. Thanks for staying tuned Josnac 3 Likes |
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 6:42am On Dec 14, 2019 |
Hello, welcome back. I initially planned to travel few days ago but it was put off...so here's a few more photo updates. 1 Like
|
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 7:49pm On Dec 23, 2019 |
Final photos... hope the hazy weather due to harmattan doesn't make it too blurry. 3 Likes
|
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by debbydee(f): 10:25pm On Dec 23, 2019 |
Josnac: Good job 1 Like |
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 10:31pm On Dec 23, 2019 |
debbydee:Thank you @debbydee 1 Like |
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by ITbomb(m): 11:42am On Dec 29, 2019 |
That was fast, well it should be when money is available You said you are yet to get the cost, that means you just mention the figure and it is provided Pity the man had to die before the building was renovated 1 Like |
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 7:04pm On Jan 13, 2020 |
ITbomb: Sorry for the delayed response ITbomb..yea, funds were available as at when I needed it. we spent just a bit over #3m on it. 1 Like |
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by SammyJac(m): 4:53pm On Apr 13, 2020 |
I didn't see any electrical wiring (neither conduit nor surface). Why was it left out? Nice job bro. 1 Like |
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by diordaves(m): 10:08am On Jun 21, 2020 |
Good job. Fantastic final budget. So sad the old man did not live to see the amazing and commendable transformation. Well done. ⭐⭐⭐⭐⭐ 2 Likes |
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by twinskenny(m): 10:47am On Jun 21, 2020 |
SammyJac: Wanted to say the same thing But good job all the same 1 Like |
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Walted0n: 5:03pm On Jun 23, 2020 |
Wonderful... I love the transformation 1 Like |
Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 5:56pm On Jun 24, 2020 |
Sorry for the delay in responding. With respect to the electrical works..the wiring was surface as it could be done faster and my client was operating on a budget. Secondly, I did point out in one of my posts that I might travel, it was during my trip that the electrical work was done, at least you could see some lights were on in a few of the final photos. SammyJac: twinskenny: Yea..it was sad, but thanks anyway. diordaves: Thank you. Walted0n: |
For Your Pop Ceiling, Wall Screeding Andtiles / Functional 20 room hotel on 1000sq.m in Asaba now N22m(net) Pics / Shower Enclosures
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 33 |