Re: Update On Zungeru Power Plant Project. by Nobody: 11:17am On Jan 25, 2020
Muyiwaipere:
Building an hydro electric power plant in a desert ..
Chai waste of money

Well good work there
Re: Update On Zungeru Power Plant Project. by AmTruth: 11:20am On Jan 25, 2020
Is this were our borrowed monies are going to? If so this project deserve the borrowing
Re: Update On Zungeru Power Plant Project. by francis5051: 11:20am On Jan 25, 2020
Rosskiye:
Buhari is working.
Chineke kpo kwagi oku..
Re: Update On Zungeru Power Plant Project. by Ustec: 11:23am On Jan 25, 2020
Muyiwaipere:
Building an hydro electric power plant in a desert ..
Chai waste of money

Well good work there
Stop embarrassing your illiterate self on a public forum.

3 Likes 1 Share

Re: Update On Zungeru Power Plant Project. by contigiency(m): 11:26am On Jan 25, 2020
BwalaMarama:
Good development. We'll surely reach the promise land some day. If not during our generation then certainly our children's generation. There's hope for this country. Let's all work together to achieve that. God bless Nigeria.

I share your sentiments.
Re: Update On Zungeru Power Plant Project. by Nobody: 11:30am On Jan 25, 2020
What pains me the most is that it is foreign contractors and engineers handling these projects, thereby creating wealth for their own home countries.

Yet, Nigeria has thousands of engineers being churned out of the universities every year.

They have hundreds of engineering professors in these institutions. Yet, we ship their work off to foreigners.

When you travel abroad, these same foreigners won't hire you fresh off the boat unless you go to their schools etc

1 Like

Re: Update On Zungeru Power Plant Project. by Skillsnigeria: 11:31am On Jan 25, 2020
That's good
Re: Update On Zungeru Power Plant Project. by Topmaike007(m): 11:32am On Jan 25, 2020
China 75% funding in our own land.. abeg China should come and colonise us
Re: Update On Zungeru Power Plant Project. by Topmaike007(m): 11:33am On Jan 25, 2020
FrLukas:
What pains me the most is that it is foreign contractors and engineers handling these projects, thereby creating wealth for their own home countries.

Yet, Nigeria has thousands of engineers being churned out of the universities every year.

They have hundreds of engineering professors in these institutions. Yet, we ship their work off to foreigners.

When you travel abroad, these same foreigners won't hire you fresh off the boat unless you go to their schools etc
read the post again and see who is funding the project... To warrant foreign contractors
Re: Update On Zungeru Power Plant Project. by Topmaike007(m): 11:34am On Jan 25, 2020
AmTruth:
Is this were our borrowed monies are going to? If so this project deserve the borrowing
lolz
Re: Update On Zungeru Power Plant Project. by 9jatriot(m): 11:40am On Jan 25, 2020
It is hard to deny that there is a lot of massive projects ongoing but I wish we get our security within the country right, its becoming alarming to say the least.

2 Likes

Re: Update On Zungeru Power Plant Project. by michoim(m): 11:42am On Jan 25, 2020
God bless PMB!God bless Nigeria and God punish haters
Re: Update On Zungeru Power Plant Project. by Nobody: 11:45am On Jan 25, 2020
Topmaike007:
read the post again and see who is funding the project... To warrant foreign contractors

I saw it. 75% Chinese, 25% local funding.

Makes it even worse.

There is no free lunch anywhere.

Be rest assured that Nigeria will be paying back soon enough, one way or the other.

Chinese recolonization of Africa is real o.
Re: Update On Zungeru Power Plant Project. by PHijo(m): 11:48am On Jan 25, 2020
winterfell007:
Zungeru started as far back as 2013, wonder why it took so long??

If you read the post you would have noticed that it was plagued by legal issues.

1 Like

Re: Update On Zungeru Power Plant Project. by IpobAntidote: 11:50am On Jan 25, 2020
Magicians:
Thanks to Johnathan!

I am waiting for fooling igbo n ipob alike to start liking my comment to buttress the sort of lunacy that is being generated from a section of the country.

Aptly stated.
Re: Update On Zungeru Power Plant Project. by adanny01(m): 11:53am On Jan 25, 2020
Proud to be the one that excavated the first foundation for the transmission line evacuating power from the dam

3 Likes

Re: Update On Zungeru Power Plant Project. by Obdk: 11:54am On Jan 25, 2020
Magicians:
Thanks to Johnathan!

I am waiting for fooling igbo n ipob alike to start liking my comment to buttress the sort of lunacy that is being generated from a section of the country.


If you re not dumb. You would ve seen the project started 2013, sophisticated morronic afonja





The project started in May 2013 but legal matters and funding stalled its construction, its now expected to be completed by Dec 2021, and first unit is expected to start generation by Dec 2020.
Re: Update On Zungeru Power Plant Project. by funshint(m): 11:58am On Jan 25, 2020
Good one but what of Mambilla power project that has more potential....
Re: Update On Zungeru Power Plant Project. by adanny01(m): 11:59am On Jan 25, 2020
Muyiwaipere:
Building an hydro electric power plant in a desert ..
Chai waste of money

Well good work there

Are you re.tarded?

Where will you build a dam, Niger Delta?

This is the 3rd dam on this "desert" River Kaduna all in Niger state. If you dont know, River Kaduna is the main tributary of River Niger all the way from the hills of Plateau state. Shiroro is upstream of this dam while Kainji is downstream of this dam on the same River Kaduna.

A dam location is chosen from a series of natural occuring geographical features which you will not easily find anywhere but where it is, Niger state. Take it elsewhere, and flood will consume the land and people. Dam River Niger in Enugu and see the disaster that will unfold. The Mambila dam is on the tributary of the River Benue.

5 main features of a dam location is high current River, a large upstream reservoir area, a high gradient between upstream and downstream, 2 adjacent hills to the river and a very good environmental impact assessment report.

5 Likes

Re: Update On Zungeru Power Plant Project. by Topmaike007(m): 12:00pm On Jan 25, 2020
FrLukas:


I saw it. 75% Chinese, 25% local funding.

Makes it even worse.

There is no free lunch anywhere.

Be rest assured that Nigeria will be paying back soon enough, one way or the other.

Chinese recolonization of Africa is real o.
yeah bro...... And this calls for worry
Re: Update On Zungeru Power Plant Project. by aminho(m): 12:03pm On Jan 25, 2020
Muyiwaipere:
Building an hydro electric power plant in a desert ..
Chai waste of money

Well good work there
So niger state is now a desert?have you ever left your village

3 Likes

Re: Update On Zungeru Power Plant Project. by eldeens: 12:09pm On Jan 25, 2020
Muyiwaipere:
Building an hydro electric power plant in a desert ..
Chai waste of money

Well good work there

Have you ever been to Zungeru, or you just felt like commenting because of the hatred that blinded your eyes? Lemme schooled you, Zungeru is in Niger State, Niger state got its name from River Niger, if you are looking for a desert go to Sokoto, Zamfara and some part of Katsina, Jigawa, read your book and don't let the hatred in you push you to make comments that will make you stupid

7 Likes

Re: Update On Zungeru Power Plant Project. by adanny01(m): 12:20pm On Jan 25, 2020
funshint:
Good one but what of Mambilla power project that has more potential....

This same CNEEC/Sinohydro in Zungeru will move to the Mambilla site after this.

1 Like

Re: Update On Zungeru Power Plant Project. by adanny01(m): 12:34pm On Jan 25, 2020
FrLukas:


I saw it. 75% Chinese, 25% local funding.

Makes it even worse.

There is no free lunch anywhere.

Be rest assured that Nigeria will be paying back soon enough, one way or the other.

Chinese recolonization of Africa is real o.

I totally agree with you.

The Chinese are smart with this thing they do.

They give a country a loan, take it back as a contract for a project. While executing the project, they make a huge profit from it by charging the country construction profits plus loan profit at the same time. Say the construction profit is 25% of the contract and the loan profit is another 25%, that makes a 50% profit on the loan sum.

To make matters worst, they will not even have to disburse 100% of the loan, what they actually disburse is 37.5% while Nigeria brings 12.5% upfront for the project.

Say the dam cost $1billion, $750million is a loan with a 25% interest. Nigeria owes China $750+187.5million=$937.5m. But Nigeria needs counterpart funding of 25% so the actual cost to Nigeria for the dam is $937.5+250m=$1.187.5b. Meanwhile China will make 25% of $1b as construction profit as well as 187.5m as loan interest. Add the profit of $250m + loan interest $187.5m =$437.5m.

China makes $437.5m profit on $750m while the citizens get jobs and earn money outside the profit amount.

Also the only money they need to disburse in executing the project is $750-250m=$500m. They will recover over 100% when the loan is due.

Highway robbery indeed!

6 Likes 1 Share

Re: Update On Zungeru Power Plant Project. by aimuan(m): 12:36pm On Jan 25, 2020
bongo2011:
God bless this government for the commitment and sincerity in tackling the power sector challenges. This is physical achievement not audio as my people normally say.
The project was started by previous administration..
Re: Update On Zungeru Power Plant Project. by Edge1(m): 12:51pm On Jan 25, 2020
There are soo many retards on this post. I'm outta here

Re: Update On Zungeru Power Plant Project. by realestniggah: 12:59pm On Jan 25, 2020
Chinese are building Africa.. They want to own Africa

1 Like

(1) (2) (3) (4) (Reply)

Ikpeazu Relaxes Lockdown In Abia To Celebrate Easter, Gives Conditions / Breaking News!!! Bomb Blast In Kasuwa *monday Market Maiduguri* / We’ll Catch Shekau Before Elections — Jonathan

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 34
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.