Request For Building Estimate by amakaDD(op):
Good morning Engineers and QS in the house.

Kindly help a sister with the estimate for this commercial build. Location is Lagos.

I need bulk pack figure for each stage of the contract.

Suggested breakdown could be:

1. Foundation/Substructure
2. Superstructure
3. Slab
4. Roofing
5. Mechanical/Electricals/Plumbing
6. *Finishing (Intetnal)
7. **External Finishing
8. Building Approval/community settlement

*Finishing includes _Windows, Doors, Burglar Bar, Borehole, Overhead tank, Ceiling, Balustrades etc._

**External Finishing includes _Septic tank, Interlocking tiles, Fence, Gate, Gatehouse..._

1. The build is sitting on a half plot.

2. This is expected to be a commercial project and ROI is key. So responsible cost cutting advice is welcome.

3. This is a crowdfunded project hence the need to clarify cost to non-technical members

cc: saydfact, rotech77, abdulwastecx, raymondFirstborn, KolaShangOne, spyder880, segcymoore, QSFemi etc.

Re: Request For Building Estimate by raymondFirstborn(m): 3:32pm On Nov 18, 2020
amakaDD:
Good morning Engineers and QS in the house.

Kindly help a sister with the estimate for this commercial build. Location is Lagos.

I need bulk pack figure for each stage of the contract.

Suggested breakdown could be:

1. Foundation/Substructure
2. Superstructure
3. Slab
4. Roofing
5. Mechanical/Electricals/Plumbing
6. *Finishing (Intetnal)
7. **External Finishing
8. Building Approval/community settlement

*Finishing includes _Windows, Doors, Burglar Bar, Borehole, Overhead tank, Ceiling, Balustrades etc._

**External Finishing includes _Septic tank, Interlocking tiles, Fence, Gate, Gatehouse..._

1. The build is sitting on a half plot.

2. This is expected to be a commercial project and ROI is key. So responsible cost cutting advice is welcome.

3. This is a crowdfunded project hence the need to clarify cost to non-technical members
Good afternoon, I can help you with the full cost breakdown.

Send the drawings to me on Whatsapp.
09056082348(call & WhatsApp)
raymondfubara@gmail.com
Re: Request For Building Estimate by amakaDD(op): 3:44pm On Nov 18, 2020
raymondFirstborn:
Good afternoon, I can help you with the full cost breakdown.

Send the drawings to me on Whatsapp.
09056082348(call & WhatsApp)
raymondfubara@gmail.com
Done.

Much appreciated sir
Re: Request For Building Estimate by Chekitaut: 6:18pm On Nov 18, 2020
Precise location in Lagos...?
Re: Request For Building Estimate by Chekitaut: 6:20pm On Nov 18, 2020
Foot size of the building...
Re: Request For Building Estimate by amakaDD(op): 1:57am On Nov 19, 2020
Chekitaut:
Precise location in Lagos...?
Surulere
Re: Request For Building Estimate by amakaDD(op): 2:00am On Nov 19, 2020
Chekitaut:
Foot size of the building...
Around 28m x 5.5m
Re: Request For Building Estimate by Chekitaut: 9:29am On Nov 19, 2020
amakaDD:
Around 28m x 5.5m
Carcass
Foundation @₦8m
Block set to 1st Decking @₦8m(ground floor)
Block set to 2nd Decking @₦8.5m
Block set to Roofing @₦8m
Total =₦32.5m

Finishing will cost you close to ₦35m
Re: Request For Building Estimate by peaceland(m): 10:31am On Nov 19, 2020
Please can you further break down the foundation aspect,
I find it interesting that half plot foundation will be that much.
Just for self education sir.
Thanks
quote author=Chekitaut post=96204208] Carcass
Foundation @₦8m
Block set to 1st Decking @₦8m(ground floor)
Block set to 2nd Decking @₦8.5m
Block set to Roofing @₦8m
Total =₦32.5m

Finishing will cost you close to ₦35m[/quote]
Re: Request For Building Estimate by Chekitaut:
peaceland:
Please can you further break down the foundation aspect,
I find it interesting that half plot foundation will be that much.
Just for self education sir.
Thanks
quote author=Chekitaut post=96204208] Carcass
Foundation @₦8m
Block set to 1st Decking @₦8m(ground floor)
Block set to 2nd Decking @₦8.5m
Block set to Roofing @₦8m
Total =₦32.5m

Finishing will cost you close to ₦35m
Recommend Raft foundation 1.2m height
Approx 6tons of TMT steel @₦295k/ton
3 trips of 30tons Granite @₦210k/trip
6trips of Sharp Sand@₦90k/trip
300 bags of Cement@₦3500/bag
300 1x12 @₦1600each
250 2x3 @₦450each
Binding wire 3bundle @₦8k/each
3bags Nail @₦8k./each
Filling Sand 10trips @₦90k(Sharp Sand)

Workmanship @₦800k
Supervision fee @₦500k
Re: Request For Building Estimate by peaceland(m): 2:02pm On Nov 19, 2020
Thanks greatly sir.
Really appreciate this.
Chekitaut:
Recommend Raft foundation 1.2m height
Approx 6tons of TMT steel @₦295k
3 trips of 30tons Granite @₦210k/trip
6trips of Sharp Sand@₦90k/trip
300 bags of Cement@₦3500/bag
300 1x12 @₦1600each
250 2x3 @₦450each
Binding wire 3bundle @₦8k/each
3bags Nail @₦8k./each
Filling Sand 10trips @₦90k(Sharp Sand)

Workmanship @₦800k
Supervision fee @₦500k
Re: Request For Building Estimate by Chekitaut: 1:21am On Nov 20, 2020
peaceland:
Thanks greatly sir.
Really appreciate this.
You welcome sir
Re: Request For Building Estimate by Bimpsyyyyy: 10:44am On Nov 21, 2020
amakaDD:
Good morning Engineers and QS in the house.

Kindly help a sister with the estimate for this commercial build. Location is Lagos.

I need bulk pack figure for each stage of the contract.

Suggested breakdown could be:

1. Foundation/Substructure
2. Superstructure
3. Slab
4. Roofing
5. Mechanical/Electricals/Plumbing
6. *Finishing (Intetnal)
7. **External Finishing
8. Building Approval/community settlement

*Finishing includes _Windows, Doors, Burglar Bar, Borehole, Overhead tank, Ceiling, Balustrades etc._

**External Finishing includes _Septic tank, Interlocking tiles, Fence, Gate, Gatehouse..._

1. The build is sitting on a half plot.

2. This is expected to be a commercial project and ROI is key. So responsible cost cutting advice is welcome.

3. This is a crowdfunded project hence the need to clarify cost to non-technical members

cc: saydfact, rotech77, abdulwastecx, raymondFirstborn, KolaShangOne, spyder880, segcymoore, QSFemi etc.
You can give a sister this job also, I am a female engineer will help u out cost effectively but will be paid percent for working on it , you will regret .
Re: Request For Building Estimate by Chekitaut: 10:55am On Nov 21, 2020
Not is missing
Re: Request For Building Estimate by Chekitaut: 10:56am On Nov 21, 2020
Bimpsyyyyy:
.
last sentence check
Re: Request For Building Estimate by amakaDD(op): 3:55pm On Nov 21, 2020
Bimpsyyyyy:
You can give a sister this job also, I am a female engineer will help u out cost effectively but will be paid percent for working on it , you will regret .
huh?

I assume typo.

But I reject it!!!
Re: Request For Building Estimate by topsy23(m): 5:15pm On Nov 21, 2020
You can contact us for your MEP design and estimate


Check out our thread

MEP installation
https://www.nairaland.com/1233943/contact-us-electrical-mechanical-plumbing/25


Distribution boards
https://www.nairaland.com/2668061/abb-distibution-board-schneider-distribution/6
1 Reply

Cost Of Building A House In Nigeria (free Building Estimate For All)Building EstimateCost, Estimate For Building A 3bedroom Bungalow In Nigeria (Detailed Info)234

Introducing Tiwa Garden City Estate Ibeju Lekki Epe LagosHaue You Used Solar Submersible Water Pump? How Efficient Is It?3 Bedroom Bungalow For Sale At Ikoyi.