| My Low Cost 4 Bedroom Bungalow Project. by Collins1507(op): 5:33pm On Dec 19, 2020 |
This thread is meant to document my progress here. [color=#990000][/color][b][/b]
|
| Re: My Low Cost 4 Bedroom Bungalow Project. by Collins1507(op): 5:36pm On Dec 19, 2020 |
The clearing done. Profile done and digging started
|
| Re: My Low Cost 4 Bedroom Bungalow Project. by Collins1507(op): 5:42pm On Dec 19, 2020 |
Laying of foundation blocks with 6" solid block.
|
| Re: My Low Cost 4 Bedroom Bungalow Project. by Nobody: 5:46pm On Dec 19, 2020 |
This place resembles imo state Following... |
| Re: My Low Cost 4 Bedroom Bungalow Project. by Nobody: 5:47pm On Dec 19, 2020 |
Collins1507:this block isn't hollow block? |
| Re: My Low Cost 4 Bedroom Bungalow Project. by Flexherbal(m): 5:54pm On Dec 19, 2020 |
Nice one! All the best!! |
| Re: My Low Cost 4 Bedroom Bungalow Project. by Collins1507(op): 6:03pm On Dec 19, 2020 |
Filling with sharp sand of about 23 trips
|
| Re: My Low Cost 4 Bedroom Bungalow Project. by Collins1507(op): 6:04pm On Dec 19, 2020 |
southniyikaye:It is in Enugu State sir. |
| Re: My Low Cost 4 Bedroom Bungalow Project. by Collins1507(op): 6:08pm On Dec 19, 2020 |
Casting of concrete German floor with beam
|
| Re: My Low Cost 4 Bedroom Bungalow Project. by Collins1507(op): 6:10pm On Dec 19, 2020 |
Completion of casting of German floor
|
| Re: My Low Cost 4 Bedroom Bungalow Project. by Collins1507(op): 6:12pm On Dec 19, 2020 |
Start of form work with 5" solid block.
|
| Re: My Low Cost 4 Bedroom Bungalow Project. by Collins1507(op): 6:15pm On Dec 19, 2020 |
Laying of blocks continue
|
| Re: My Low Cost 4 Bedroom Bungalow Project. by Collins1507(op): 6:17pm On Dec 19, 2020 |
Digging and forming of sock away pit
|
| Re: My Low Cost 4 Bedroom Bungalow Project. by Collins1507(op): 6:18pm On Dec 19, 2020 |
Work in progress in the sock away pit. With 12mm rod
|
| Re: My Low Cost 4 Bedroom Bungalow Project. by Collins1507(op): 6:24pm On Dec 19, 2020 |
Laying of rod for lintel and carpenter work.
|
| Re: My Low Cost 4 Bedroom Bungalow Project. by Collins1507(op): 6:27pm On Dec 19, 2020 |
Casting of lintel done.
|
| Re: My Low Cost 4 Bedroom Bungalow Project. by Collins1507(op): 6:29pm On Dec 19, 2020 |
LEVELLING DONE |
| Re: My Low Cost 4 Bedroom Bungalow Project. by Collins1507(op): 6:31pm On Dec 19, 2020 |
Woods for Roofing carcass brought to site and started
|
| Re: My Low Cost 4 Bedroom Bungalow Project. by Collins1507(op): 6:34pm On Dec 19, 2020 |
Roofing carcass done.
|
| Re: My Low Cost 4 Bedroom Bungalow Project. by Collins1507(op): 6:38pm On Dec 19, 2020 |
Collins1507:Awaiting for prospective bid from good Roofing guys. |
| Re: My Low Cost 4 Bedroom Bungalow Project. by yomi007k(m): 6:58pm On Dec 19, 2020 |
Wow fantastic job so far. You for attach cost to each of the pictures. |
| Re: My Low Cost 4 Bedroom Bungalow Project. by Collins1507(op): 7:17pm On Dec 19, 2020 |
yomi007k:I will do that later and break it down in stages |
| Re: My Low Cost 4 Bedroom Bungalow Project. by Collins1507(op): 7:34pm On Dec 19, 2020 |
Collins1507:Clearing of trees ---37,000 Digging of foundation --40,000. Iron bender for column and base -- 5000 Blocks 6" 1500pcs ---195,000 Sand 2trips 10,000. cement 75bags --- 166,000 Gravel 2trips 36000. Full load of water tanker ---13,000 Labour for laying of foundation blocks ---65,100 TOTAL #567,100
|
| Re: My Low Cost 4 Bedroom Bungalow Project. by yomi007k(m): 7:38pm On Dec 19, 2020 |
Well done bro. What was the duration of the project and at what timing(year or month). I personally had to halt my project due to the sudden hike in cement. |
| Re: My Low Cost 4 Bedroom Bungalow Project. by Collins1507(op): 7:56pm On Dec 19, 2020 |
**Labour for blinding of foundation ---21,000.** First Sand filling with mud sand 10trips ---50,000. (it didn't go anywhere). Then we switched to sharp sand of 16trips--- 104,000. Gravel 2trips ---34,500 (different person). 10mm rod 20pcs ---33,0000 8mm rod 10pcs --13,000. Plank 48pcs--- 39,900. 2*2. 20pcs ---5,000. Nail 3" 1bag ---6,800 Transport--- 9000 Labour for filling up of foundation ----26,200. ======342,400 TOTAL #567,100+342,400= #909,500 |
| Re: My Low Cost 4 Bedroom Bungalow Project. by Collins1507(op): 7:58pm On Dec 19, 2020 |
yomi007k:My brother I actually started in march ending. And I still on it small small. |
| Re: My Low Cost 4 Bedroom Bungalow Project. by yomi007k(m): 8:04pm On Dec 19, 2020 |
Collins1507: ![]() You are very lucky o. I started around July/Aug and I was slow which made the price change catch up with me. I wish I started earlier, invested more money and was faster. Well, I am just hoping things may improve around February 2021. |
| Re: My Low Cost 4 Bedroom Bungalow Project. by Collins1507(op): 8:12pm On Dec 19, 2020 |
Binding wire--- 9000 Iron bender/capenter (same person) ---13,000. Labour for rammering--10,000 Cement 40bags 94,000. Labour for german floor (58bags) and mason ------49,800.==175,800 TOTAL #909,500+175,800==#1,085,300
|
| Re: My Low Cost 4 Bedroom Bungalow Project. by Collins1507(op): 8:15pm On Dec 19, 2020 |
yomi007k:Am even hoping so, because the price of roofing sheets went up 3x. Am waiting till then too |
| Re: My Low Cost 4 Bedroom Bungalow Project. by Collins1507(op): 8:27pm On Dec 19, 2020 |
Digging of suck away pit---22,000. clearing of the sand for back filling ---11,000. Labour for laying of blocks ---40,000. Iron bender/carpenter 17,000. Plastering and flooring ---12,000. 12mm rod 10pcs ---22,800 ¼rod 15pcs--15,000.== 139,800 #1,085,300 +139,800==#1,225,100
|
| Re: My Low Cost 4 Bedroom Bungalow Project. by Collins1507(op): 8:48pm On Dec 19, 2020 |
5" block 2500 pcs --300,000 Labour from forming to lintel ----69,800 Carpenter Labour--18,000. Iron bender---20,000. Labour for casting of lintel --17,100. 5" bottom 20pcs--9,000 10mm rod 20pcs ---35,800. T. P & labor ---8,500. Cement 20bags---48,000.====526,200 #1,225,100 + 526,200 ==#1,751,300 |
| Re: My Low Cost 4 Bedroom Bungalow Project. by Collins1507(op): 8:53pm On Dec 19, 2020 |
Levelling of lintel labour ---38,500. Cement 5bags ---15,500.===54000 **NOTE: ALL THE ROOMS ARE ENSUITE*** ==#1,751,300 + 54,000====#1,805,300 |