My 3 Bedroom Bungalow Project - 2021 - 2022 (Lagos) by djseanjohn77: 2:47pm On Sep 05, 2023 |
It was not an easy task, knowing how inflation between the mentioned period jumped significantly, prices of building materials tripled in some cases went as fa as x4. But God finished it. It seats on a 2 plots
|
Re: My 3 Bedroom Bungalow Project - 2021 - 2022 (Lagos) by TemplarLandry: 2:48pm On Sep 05, 2023 |
Re: My 3 Bedroom Bungalow Project - 2021 - 2022 (Lagos) by djseanjohn77: 2:48pm On Sep 05, 2023 |
The process, how it all began
|
Re: My 3 Bedroom Bungalow Project - 2021 - 2022 (Lagos) by djseanjohn77: 2:50pm On Sep 05, 2023 |
djseanjohn77: Modification was done as times changed between the design period and the build period, hence, little modification to match current day aesthetics. |
Re: My 3 Bedroom Bungalow Project - 2021 - 2022 (Lagos) by djseanjohn77: 2:55pm On Sep 05, 2023 |
djseanjohn77:
|
Re: My 3 Bedroom Bungalow Project - 2021 - 2022 (Lagos) by Airesluxe: 3:11pm On Sep 05, 2023 |
Big congratulations. We all pray for blessings 🥂 |
Re: My 3 Bedroom Bungalow Project - 2021 - 2022 (Lagos) by djseanjohn77: 3:20pm On Sep 05, 2023 |
[quote author=djseanjohn77 post=125596293][/quote] The floor plan and the modification when finished. I didn't mention that the family i gave the work for supervision, modified the design initially. I detected after i requested for a video of the foundation be sent to me. I had to abandon the work for like 6 months after which i paid someone to be the new supervisor and got another contractor (the initial contractor was recommended by the family member as well. They didn't do any bad, but they wanted something that would finish fast against my original plan. The foundation was re-worked from beginning, concrete, some blocks were buried already. The house has 16 columns round and center, the oversight concrete was with membrane. Everything from start to finish was done as professional as it could be, no cutting corners, or managing of funds (as standard as it could be) 1 Like
|
Re: My 3 Bedroom Bungalow Project - 2021 - 2022 (Lagos) by djseanjohn77: 3:25pm On Sep 05, 2023 |
The 2 plots was fenced and gate fixed. The major challenge was the inflation, how price of cement went from less than 2k to over 4k, rods from 1000 - 1500 to 3500 - 4500, roofing sheets went from 1800 - 3750 etc.
|
Re: My 3 Bedroom Bungalow Project - 2021 - 2022 (Lagos) by djseanjohn77: 3:29pm On Sep 05, 2023 |
Still a lot of work to be done to bring it to that desired taste - but my family moved in since January 2023. Every picture here was before they moved. 2 Likes
|
Re: My 3 Bedroom Bungalow Project - 2021 - 2022 (Lagos) by djseanjohn77: 3:32pm On Sep 05, 2023 |
djseanjohn77: German doors for the outside doors, kitchen and dinning had hdf, while the room doors were juwon steel doors
|
Re: My 3 Bedroom Bungalow Project - 2021 - 2022 (Lagos) by AsomStructures: 4:18pm On Sep 05, 2023 |
Congratulations. Owning a house is a beautiful thing you can only pray and workhard for to achieve. There are visible modifications especially on the approach view. I think the design gives a better outlook than the construction. |
Re: My 3 Bedroom Bungalow Project - 2021 - 2022 (Lagos) by nasskar(m): 9:19am On Sep 11, 2023 |
djseanjohn77:money will spent . I love what I am seeing. Congratulations it's not ease 1 Like |
Re: My 3 Bedroom Bungalow Project - 2021 - 2022 (Lagos) by djseanjohn77: 2:59pm On Sep 02 |
AsomStructures: Yes, modification was made in the construction phase to match with most recent architectural designs. Like the additional windows, then the glass at the entrance of the waiting room to modify the usual trend of open type veranda. The waiting room is now serving 2 functions, as a waiting room and veranda at the same time. |
Re: My 3 Bedroom Bungalow Project - 2021 - 2022 (Lagos) by djseanjohn77: 3:01pm On Sep 02 |
Re: My 3 Bedroom Bungalow Project - 2021 - 2022 (Lagos) by djseanjohn77: 3:02pm On Sep 02 |
djseanjohn77: Finishing stage - I forgot to share this all this while.
|
(1) (Reply)
Introducing Silvergate Estate Ibeju Lekki By Kenttimo Limited / Sales And Buyback Investmen (sabbi Volume 1) Epe New City Estate, Iraye Epe. / New 4bedroom Architectural/house Plan Building Design
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 20 |