Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja - Properties - Nairaland

Nairaland Forum / Nairaland / General / Properties / Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja (1707 Views)

Construction Diary Of 8units Of 2/3brds Flat Structure By ARBO CONTRACTOR LTD / Want A Perfect Architecture Design And Build Construction This Year? / Want A Perfect Architecture Design And Build Construction This Year? (2) (3) (4)

(1) (Reply) (Go Down)

Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects: 6:20pm On Mar 11, 2021
Project Title: Residential Development Of a Block of Four units of 2bedroom flats

Project Location: Kubwa, Abuja

Contractor : Harneyprojects ltd RC 781615 ( www.harneyprojects.com)

Client : Nairalander

Project cost: 69 million naira

Project Duration: 7 months

1 Like

Re: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects: 6:28pm On Mar 11, 2021
The building approval process was done with Federal Capital Developement Authority (FCDA) . The lead Engineer ( Engr. A.P Saliu ) is a Coren Registered engineer and also a member of the Nigerian society of engineers(NSE) , his registration status lead to a smooth building approval process.

Re: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects: 6:53pm On Mar 11, 2021
The Construction team of 1 Coren registered engineer, Building technologist, carpenters, iron benders and other skilled artisans were dispatched to the site to execute the project.

Re: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects: 9:50am On Mar 14, 2021
The preliminaries work involved the construction of a store and drilling of a borehole
Re: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects: 10:54am On Mar 14, 2021
The main work began with the foundation.
FOUNDATION WORKS :

The setting out [/i]of the foundation was done using line, square, pegs, profile board, measuring tape and nails. The setting out team involved an engineer, builder and a carpenter.

[i]The excavation works [/i]preceded the conclusion of the setting out of which the buildings strip foundation was excavated to a depth of approx 1.2meter and width of 0.675m while the pad foundation was excavated to a depth of 1.4m and width of 1.2m. The excavation team involved a team of locally sourced labourers and the building technologist. The foundation involved a combination of stip foundation and pad foundation . The strip foundation would cater to the sancrete blocks walls while the pad foundation would cater to the columns which serve as part of the structural frame of the building.

[i]The Reinforcement work [/i]preceded the excavation. This involved a combination of 16mm,12mm and 10mm high yield TMT bars bent to the structural specification in the approved structural drawings. The reinforcement work for the pad base and columns were done and placed in the excavated foundation pit.

[i]The concrete works
involved mixing the concrete to a ratio of 1:2:4 using a concrete mixer and placed with wheelbarrows and shovels. A vibrating machine was used to ensure well-vibrated concrete. The strip footing has a thickness of 225mm while the pad footing has a thickness of 350mm


https://www.youtube.com/watch?v=85PUGjYVPy4

Re: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects: 12:08pm On Mar 14, 2021
Foundation blockwork
Blockwork preceded the foundation concrete works. It involved the placement of sancrete blocks on the strip footing bonded with mortar(a combination of cement and sharp sand (1:6). The blocks are laid to the Damp proof course (DPC) level specified in the architectural design. The specified height above Natural ground level (NGL) is 1.25m. The foundation blockwork was filled with concrete with a mix ration of 1:4:8

Foundation Colunms ,Pinth Beams and Damp proof course (DPC)

This involved reinforcement work, concrete works and carpentry works. The plinth beam became necessary due to the height of the foundation columns and was provided to prevent buckling

The reinforcement works was done to structural specifications and involved 4Y16 as main bars and Y10-200 c/c as shear reinforcement ( rings) for both the columns and plinth beam.

The carpentry works involved covering up the sides and providing bracing against failure. A combination of 1'' X 12' boards, 2'' x 4'' planks of wood and 3'' nails were used for the carpentry works.

The concrete was mixed to a mixed ratio of 1:2:4 conforming to the specified mix ratio in the structural design. The concrete was placed and compacted with a vibrating machine to avoid honeycomb and voids in the concrete.


N.B -
- ' sign denotes feet. An imperial system of measurement
- '' sign denotes inches. An imperial system of measurement

Re: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Timberwolves(m): 6:41pm On Mar 16, 2021
Job weldone

For the concrete, you used 1:2:4, is the ratio by weight or by volume? can you share more light on this ?
Re: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects: 8:37pm On Mar 16, 2021
Timberwolves:
Job weldone

For the concrete, you used 1:2:4, is the ratio by weight or by volume? can you share more light on this ?

Thank you.

The concrete mixture for this project was done by volume using head pans/ wheel barrows.
1 bag of cement would can be poured into 2 head pans, therefore the mix ratio by headpans was fone by mixing 1 bag of cement : 4 head pans of sand : 8 head pans of gravel. We put as little water as possible while still maintaining a workable mixture because workability of concrete is very important in concrete placement.
For larger projects with significant concrete volume, harneyprojects employes the use of a batching plant where concrete is mixed by weight.
Re: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Timberwolves(m): 10:36pm On Mar 16, 2021
that would be a rich concrete mix, keep it up

one more thing, how do you cope with workmanship? I have one site at pyakasa, opposite lugbe, the labourers n artisans in that axis aren't much professionals as per construction industry is concerned
Re: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects: 1:48am On Mar 17, 2021
Timberwolves:
that would be a rich concrete mix, keep it up

one more thing, how do you cope with workmanship? I have one site at pyakasa, opposite lugbe, the labourers n artisans in that axis aren't much professionals as per construction industry is concerned

We have a team of artisans with whom we have developed a working relationship over many years. They understand the quality we desire and they deliver accordingly.

1 Like

Re: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects: 2:06pm On Mar 19, 2021
Damp proof course (DPC )Works
This involved filling up the foundation voids with laterite of significant volume, compaction with a mechanical compactor, placement of hardcore, carpentry works and concrete works.
A damp proof membrane (DPM) was placed before concrete works to reduce the effect of the capillary action of moisture.

https://www.youtube.com/watch?v=uRhMXdQ9Fso

1 Like

Re: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects: 10:18am On Apr 04, 2021
Ground floor construction
This involved masonry works, reinforcement works, carpentry works and concrete works.

Reinfrocement works
This involved the reinforcement works for the ground floor colunms and lintel . Y16mm reinforcement bars was used for the colunms with 10mm reinforcement bars for the links. The lintel had a combination of 12mm reinforcement bars and 10mm reinforcemnt bars for the links. The structural drawings for the columns indicated 4Y16 and the links are Y10 @ 200mm c/c . The lintel is also 4Y12 with links of Y10 @ 300mm c/c

Masonry works
This involved laying of 9'' and 6'' blocks bonded with mortar . The blocks are laid to the height specified in the architectural drawings . A combination of plum, line.,square and leveling instrument was used to ensure a well levelled block.

Capentry works

This involved the use of 1'' x12''x 12' , 1'' x 9'' x 12' , 1'' x 6'' x 12' machine sawed planks to cover the vertical sides and suffix of the lintels and colunms. A combination of 2'' x 4 '' woods and binding wire were used to brace the planks against failure.

Concrete works

This involved placement of insiitu concrete for the colunms and lintels. The mix ratio used was 1:2:4 and the concrete was well vibrated with a vibrating machine. A concrete mixer was used to ensure a consistent well mixed workable concrete.

The Ground floor stage concluded with the laying of the final four courses of blocks on the lintel taking the height to the level specified in the architectural design. The plumber works for the ground floor and first floor was done to the specifications in the mechanical drawings

N.B

Mortar is a mixture of cement and sand in a mix ratio of 1:6 , Mortar is used to bond the sancrete blocks to achieve the desired bond type. The sharp sand can be partly or fully replaced with stone dust in location where stonedust is ready available. Experiments have shown that the best replacement for sharp sand with stonedust is a 50% partial replacement , this is also the best for partial replacement of sharp sand in concrete.

https://www.youtube.com/watch?v=pBbDEFK4TNs

Re: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects: 8:33am On Apr 05, 2021
Happy Easter from the Harneyprojects family

Re: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects: 7:08pm On Apr 24, 2021
First floor Slab Construction

This stage of work involves constructing the first-floor slab and beams based on the structural design of the structure. For this structure, a combination of 16mm reinforcement bars, 12mm reinforcement bars and 10mm reinforcement bars was used. TMT reinforcement was used as it is closer to the design tensile stress of 410N/mm2 than the other reinforcements in the market ( KAM reinforcement is also a very nice choice of reinforcement ).

Formwork Placement
This involved the placement of formwork comprising of 1"x 12" planks ( Marine boards are better due to strength and straightness of the boards and should be used if the budget permits), 2'' x 4 '' woods and bamboo for suffix support. A team of 5 carpenters worked for 5 days to complete this task.

Reinforcement placement
Reinforcement was placed based on the structural drawings. 12mm bars served as both the main and distribution bars for the slab while a combination of 16mm bars and 12mm bars were used as the main bars in the beams for both the tensile and compression zones. 10mm bars were used as links for the beams.

Concrete Plcaement

This follows the completion of the formwork and reinforcement placement. The concrete was mixed to a mix ratio of 1:2:4 in order to achieve the design concrete strength of 25N/mm2. A concrete mixer and poker vibrator was used to achieve a well compacted and workable concrete mix during the concreting.

https://www.youtube.com/watch?v=YsjpXO6Ssvc

Re: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects: 5:33pm On Apr 29, 2021
More pictures of the first-floor slab work

Re: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects: 5:36pm On Apr 29, 2021
more.....

Re: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects: 11:42am On Apr 30, 2021
First floor construction


This involved masonry works, reinforcement works, carpentry works and concrete works for the lintel and columns.

Reinforcement works
This involved the reinforcement works for the first floor colunms and lintel . Y16mm reinforcement bars was used for the columns with 10mm reinforcement bars for the links. The lintel had a combination of 12mm reinforcement bars and 10mm reinforcement bars for the links. The structural drawings for the columns indicated 4Y16 and the links are Y10 @ 200mm c/c . The lintel is also 4Y12 with links of Y10 @ 300mm c/c

Masonry works

This involved laying of 9'' and 6'' blocks bonded with mortar . The blocks are laid to the height specified in the architectural drawings . A combination of plum, line., square and levelling instrument was used to ensure a well-levelled block. Due to the height involved, extra precautions were taking for the safety of the masons.

Capentry works


This involved the use of 1'' x12''x 12' , 1'' x 9'' x 12' , 1'' x 6'' x 12' machine sawed planks to cover the vertical sides and suffix of the lintels and colunms. A combination of 2'' x 4 '' woods and binding wire were used to brace the planks against failure.

Concrete works


This involved placement of in-situ concrete for the columns and lintels. The mix ratio used was 1:2:4 and the concrete was well vibrated with a vibrating machine. A concrete mixer was used to ensure consistent well mixed workable concrete.

Re: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects: 7:28pm On May 07, 2021
More pictures

Re: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects: 9:02am On May 14, 2021
Happy Sallah celebration to our Muslim brothers and sisters

Re: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects: 2:01pm On May 14, 2021
Roof Construction

This stage is divided into two units
- Construction of the roof beam/ concrete facial

- Construction of the Roof truss and placement of roof covering
Re: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects: 2:06pm On May 14, 2021
Roof beam/Concrete Facial

The roof beam as a depth of 300mm and reinforcement detail that involved the use of 12mm bars as the main bars and 10mm bars as the links.
Concrete facial with an horizontal/vertical pattern was used.
Concreting was done after the completion of the reinforcement and formwork placement

Re: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects: 3:25am On May 16, 2021
Roof truss/ Roof covering

The roof truss was done with treated hardwood timber .The number used is listed below :-
2x6 @ 160pcs
2x4 @ 380pcs
2x3 @ 450pcs
2x2 @ 250pcs
nails 4" inches @ 4 carton
nail 3" inches @ 2 cartoon
sohangram @ 3 gallon

The roof covering used was 0.55mm thick aluminium shingle measuring 450sqm .

Re: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects: 3:28am On May 16, 2021
More roofing pictures.

Re: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects: 3:30am On May 16, 2021
Roof covering pictures..

Re: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects: 10:16am On Jul 01, 2021
Design | Build | Realestate

www.harneyprojects.com

Info@harneyprojects.com

Re: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects: 5:16pm On Jul 20, 2021
DESIGN | BUILD | REALESTATE

Re: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects: 4:38pm On Dec 25, 2021
DESIGN | REAL | REALESTATE

Re: Kubwa-build Construction Diary Of a Block of 4 units of 2 bedroom flats in Abuja by Harneyprojects: 7:22am On Jan 01, 2022
Happy new year from the Harneyprojects team

(1) (Reply)

Need A House To Buy At Otedola Estate / Carltons Gate Chevon Drive 40million Naira / Land For Sale In Uyo

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)