PropertiesHi Everyone. I Just Joined The Family . by Uchristian(op): 7:36pm On Sep 12, 2020
Hi everyone, this is a quotation given to me by an Engineer to do just a Foundation to Dpc and he charged 1.2million for labor. The house plan is to build a 4 bed room with two sitting room and attached 2 unit 3bed room duplex The land is in Enugu state. Please I need a help also calling on any good qualified Building Engineer. christiawebnet@gmail.com.. thanks




Estimate From FOUND. - DPC:
-Materials ÷
Reinf. Rod:
*Starter bars - 16mm - 48lengths @ #4700each = #228000,.
*Basket/chaining - 22mm - 123lengths @ #2800 each = #344400,
*Links - 8mm - 46lengths @ #1300each =#59800,
Binding wire - #8500.
{Estimated cost of rod = #640700}

TIMBER Material:
*Peg - 4bundles @ #800 each - #3200,
*2x2 - 34lengths @ #250each = #8500,
*1*12*12 - 129lengths @900each = #116100,
*3" nail - 1bag @ #8000
{Estimated timber cost = #135800}

CONCRETE Material:
*Gravel - 90ton - #540,000.
*Sharp sand - 20trips @ #10,000each = #200,000,
*Cement - 266bags at #2400each = #638400,
*Water -6tanks @ #3500 each = #21000,
*Water for compaction - 4tankers @ #7000each = #28000,
{Estimated cost of concrete = #1427400}

Material For Block Work:
*cement - 40bags @ #2400each = #96000,
*Sand for DPC filling - 30trips @ #10000 each = #300000,
{Estimated #396000}

( Total Estimated material cost = #2,619,900)