Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 11:40am On Jan 04, 2017 |
Good day fellow nairalanders on property section. Being a silent nairalander all this while, though I tried updating a previous work I did n many others but time won't let me complete the ones I created n the 1 I intend creating, but I promise to complete this very 1. Thanks in anticipation Cc mufutau55 Segzy14 |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 11:53am On Jan 04, 2017 |
A quick 1 about this project. The building is standing on about 380sqm. (not precise actually). Owned by......that's a secret and it's to be sold after completion. Its actually a build and sell thing. The ground floor consist of Foyer Living room Dinning Kitchen Guest room Attached BQ First floor 3 bedrooms all ensuites Family lounge Note: the building is subject to change as the construction work is going on. Enough of talks. Let's move to work. |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 11:56am On Jan 04, 2017 |
The work started since last year (December ending to be precise. so will upload pictures from the setting out to the present stage. SETTING OUT 1 Share
|
Re: Construction Of 4 Bedroom Duplex With Attached BQ by greenermodels: 12:10pm On Jan 04, 2017 |
temmy6996:can we see the floor plan? would you give cost updates? i have interest in this type of structure. |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by twinskenny(m): 12:16pm On Jan 04, 2017 |
Hello sir and congratulations Please can we come in for the electrical? https://www.nairaland.com/3530162/northern-foreshore-projects-electrical-fittings Thanks |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 12:16pm On Jan 04, 2017 |
Blinding of foundation trenches
|
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 12:22pm On Jan 04, 2017 |
greenermodels:Will upload the floor plans and probably the 3D, but like I said earlier, the design is being modified to accommodate some features so as to maximise the limited available space. Thanks |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 12:26pm On Jan 04, 2017 |
twinskenny:It'll be 9c working with you sir considering your reputation and referrals on this forum , but I have my complete team to work on this particular project. I'm given you my words, will call you soonest for something Juicy. Thanks |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by mufutau55(m): 12:26pm On Jan 04, 2017 |
On board and following. Hajji M. |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by greenermodels: 12:27pm On Jan 04, 2017 |
temmy6996:two bedrooms downstairs plus three bedrooms upstairs is five bedrooms. |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 12:28pm On Jan 04, 2017 |
mufutau55:Thanks so much sir. I appreciate |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by greenermodels: 12:28pm On Jan 04, 2017 |
temmy6996:following. |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by Nobody: 12:53pm On Jan 04, 2017 |
mufutau55: Funny enough sir, this guy was my classmate in school(FUTMINNA), he is so good, I hail him. He is fully in charge of this build,pls give cost updates. Let us see what he have for us. I have been to the site in question. Pls let the questions start rolling in. |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by twinskenny(m): 12:56pm On Jan 04, 2017 |
temmy6996: Lovely sir... Wish you good luck |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 1:03pm On Jan 04, 2017 |
segzy14:My Oga, thanks so much. Will give cost updates sir. FUTmx.....we. rock |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by Nobody: 1:04pm On Jan 04, 2017 |
greenermodels: It is one bedroom downstairs and three bedroom upstairs. 1 Like |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 1:46pm On Jan 04, 2017 |
The foundation is an Inverted "TEE " beam. This is the same as the normal rectangular raft foundation but the cross-section is modified to an inverted T so that the flanges reduce the contact pressure on the ground. The base was first boarded and casted b4 the raft wall is casted
|
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 1:48pm On Jan 04, 2017 |
More pictures
|
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 1:53pm On Jan 04, 2017 |
To make the work easier for me, i'll give the cost afternoon each milestone. |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 2:13pm On Jan 04, 2017 |
The formwork of the raft using steel panels. The piping was also done immediately after the base casting.
|
Re: Construction Of 4 Bedroom Duplex With Attached BQ by greenermodels: 2:45pm On Jan 04, 2017 |
good work. |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 3:08pm On Jan 04, 2017 |
Sandfilling works started immediately after the removal formwork
|
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 3:15pm On Jan 04, 2017 |
More pictures
|
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 3:24pm On Jan 04, 2017 |
greenermodels:Thanks so much sir |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by Nobody: 4:32pm On Jan 04, 2017 |
Why is the foundation (though it seems pretty strong) starting from the ground level? Won't the house be detached and moveable from the ground? |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 4:56pm On Jan 04, 2017 |
Muafrika2:Good question sir. if you look closely, you'll realise that the foundation base is lower than the existing road level. the compound will still be sandfilled during the final stage of the work. what you'll have left will just be 450mm (1ft6in) up to the floor slab (german floor). I hope I've answered your question. thanks 1 Like |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by mufutau55(m): 5:31pm On Jan 04, 2017 |
segzy14: That school is surely producing good students. I think I will need to come enroll there too. Hajji M. 1 Like |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 11:57am On Jan 05, 2017 |
Good day all. Guess ur day has being good. We proceed with the watering, compacting and blinding of the backfilled foundation before the reinforcement of the floor slab. Pictures coming shortly. Thanks |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 11:58am On Jan 05, 2017 |
mufutau55:Won't be a bad idea sir, but be ready for the drills . |
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 12:01pm On Jan 05, 2017 |
Top of beams washed off sand and ready for blinding
|
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 12:07pm On Jan 05, 2017 |
More pictures of compacting and the roll of thick polythene sheet to serve the purpose of damp proof membrane
|
Re: Construction Of 4 Bedroom Duplex With Attached BQ by temmy6996(m): 12:09pm On Jan 05, 2017 |
Pictures
|
4 BEDROOM LUXURIOUS SMART HOUSES AT G EMPIRE GARDEN GUZAPE ABUJA, FEW UNITS LEFT / Distress Sale Of 900sqm Land At Mayfair Garden Estate Lekki 27m / Are You In The Building Industry? Don't Miss This Event
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 46 |