Cost Of Building A Mini Flat by Nobody: 4:22pm On Oct 11, 2017
Dear good people of Nairaland,

Based on the building plan, I need your expertise on breakdown estimate of building a mini flat around SIMAWA behind RCCG, Shagamu.

Will appreciate every contribution... Thanks

Re: Cost Of Building A Mini Flat by raymondFirstborn(m): 4:41pm On Oct 11, 2017
sulley:
Dear good people of Nairaland,

Based on the building plan, I need your expertise on breakdown estimate of building a mini flat around SIMAWA behind RCCG, Shagamu.

Will appreciate every contribution... Thanks



goodafternoon, send a mail with the building plan to.

raymondfubara@gmail.com

or
Whatsapp message with the building plan as an attachment.

to

09056082348
Re: Cost Of Building A Mini Flat by Nobody: 8:21pm On Oct 11, 2017
raymondFirstborn:




goodafternoon, send a mail with the building plan to.

raymondfubara@gmail.com

or
Whatsapp message with the building plan as an attachment.

to

09056082348

OK thanks
Re: Cost Of Building A Mini Flat by Nobody: 9:03pm On Oct 11, 2017
Professionals in the house, Kindly assist a brother with the estimate for the above plan... Pleaseeeeee
Re: Cost Of Building A Mini Flat by adebaxton(m): 4:05pm On Oct 12, 2017
sulley:
Dear good people of Nairaland,

Based on the building plan, I need your expertise on breakdown estimate of building a mini flat around SIMAWA behind RCCG, Shagamu.

Will appreciate every contribution... Thanks

Bldr. Adebayo
08058307787
smattad@yahoo.com

NB: Inbox me for a detailed estimate with finishing inclusive.


STAGE 1.
Marking Out of Building Area,Water Connection,Setting Out, Excavation/Blinding, Column Base ,Starter Column,Boarding of the Starter Column,Casting of the Starter Column,Sand filling

Wetting/Ramming/Compacting,Damproofing,Casting of Foundation Slab,Block Setting,Casting of Column, Beams-Lintel,Electrical Rough-in work,Mechanical Rough-in work.

Items Unit Item Unit Price Total Price
12mm Iron Rod 15 pcs 1,750 26,250
8mm Stirrup 8 Dozens 900 7,200
Binding Wire 5 Kg 5,000 5,000
Sharp Sand 15tonnes X 4 30,000 120,000
Gravel 15X2 Tonnes 45,000 90,000
Cement 75 Bags 2,600 195,000
Vibrated Block 1380 Unit 150 207,000
Tarpaulin 8 sheet 1000 8,000
658,450



Stage 2
Roofing

Items Unit Item Unit Price Total Price
Hardwood Rafter 85 Pieces 400 34,000
Hardwood Kingpost 15 Pieces 1,450 21,750
2” Nail ½ Bag 9,000 4,500
3” Nail 1 Bags 9,000 9,000
4” Nail 2 bag 9,000 18,000
Fascia Board 15 pieces 1,600 24,000
Ceiling Joist 80 pieces 300 24,000
Asbestos 85 pieces 1,200 102,000
PVC Ceiling Board* 9 Bundle 8,000 72,000
309,250




Stage 3. Plastering

Items Unit Items Unit Price Total price
Plastering Sand 3 Trucks 34,000 102,000
Cement 30 Bags 2,600 78,000
180,000

Re: Cost Of Building A Mini Flat by Nobody: 7:39pm On Oct 12, 2017
adebaxton:


Bldr. Adebayo
08058307787
smattad@yahoo.com

NB: Inbox me for a detailed estimate with finishing inclusive.


STAGE 1.
Marking Out of Building Area,Water Connection,Setting Out, Excavation/Blinding, Column Base ,Starter Column,Boarding of the Starter Column,Casting of the Starter Column,Sand filling

Wetting/Ramming/Compacting,Damproofing,Casting of Foundation Slab,Block Setting,Casting of Column, Beams-Lintel,Electrical Rough-in work,Mechanical Rough-in work.

Items Unit Item Unit Price Total Price
12mm Iron Rod 15 pcs 1,750 26,250
8mm Stirrup 8 Dozens 900 7,200
Binding Wire 5 Kg 5,000 5,000
Sharp Sand 15tonnes X 4 30,000 120,000
Gravel 15X2 Tonnes 45,000 90,000
Cement 75 Bags 2,600 195,000
Vibrated Block 1380 Unit 150 207,000
Tarpaulin 8 sheet 1000 8,000
658,450



Stage 2
Roofing

Items Unit Item Unit Price Total Price
Hardwood Rafter 85 Pieces 400 34,000
Hardwood Kingpost 15 Pieces 1,450 21,750
2” Nail ½ Bag 9,000 4,500
3” Nail 1 Bags 9,000 9,000
4” Nail 2 bag 9,000 18,000
Fascia Board 15 pieces 1,600 24,000
Ceiling Joist 80 pieces 300 24,000
Asbestos 85 pieces 1,200 102,000
PVC Ceiling Board* 9 Bundle 8,000 72,000
309,250




Stage 3. Plastering

Items Unit Items Unit Price Total price
Plastering Sand 3 Trucks 34,000 102,000
Cement 30 Bags 2,600 78,000
180,000




Really appreciate, thanks a lot.
Re: Cost Of Building A Mini Flat by sisi14: 9:58am On Jan 11, 2018
What I decide to use burnt bricks so I won't be plastering the brick outside, is it more expensive?
Re: Cost Of Building A Mini Flat by sisi14: 9:58am On Jan 11, 2018
What if I decide to use burnt bricks so I won't be plastering the brick outside, is it more expensive?
Re: Cost Of Building A Mini Flat by adebaxton(m): 1:25pm On Jan 11, 2018
sisi14:
What if I decide to use burnt bricks so I won't be plastering the brick outside, is it more expensive?

It depends on the size and cost of the brick.
Re: Cost Of Building A Mini Flat by Oluwadarasimies: 1:29pm On Apr 19, 2020
Call this number 0907859362 for sharp sand quality one
Re: Cost Of Building A Mini Flat by BecomeALandLord(m): 1:56pm On Jul 29, 2020
adebaxton:


Bldr. Adebayo
08058307787
smattad@yahoo.com

NB: Inbox me for a detailed estimate with finishing inclusive.


STAGE 1.
Marking Out of Building Area,Water Connection,Setting Out, Excavation/Blinding, Column Base ,Starter Column,Boarding of the Starter Column,Casting of the Starter Column,Sand filling

Wetting/Ramming/Compacting,Damproofing,Casting of Foundation Slab,Block Setting,Casting of Column, Beams-Lintel,Electrical Rough-in work,Mechanical Rough-in work.

Items Unit Item Unit Price Total Price
12mm Iron Rod 15 pcs 1,750 26,250
8mm Stirrup 8 Dozens 900 7,200
Binding Wire 5 Kg 5,000 5,000
Sharp Sand 15tonnes X 4 30,000 120,000
Gravel 15X2 Tonnes 45,000 90,000
Cement 75 Bags 2,600 195,000
Vibrated Block 1380 Unit 150 207,000
Tarpaulin 8 sheet 1000 8,000
658,450



Stage 2
Roofing

Items Unit Item Unit Price Total Price
Hardwood Rafter 85 Pieces 400 34,000
Hardwood Kingpost 15 Pieces 1,450 21,750
2” Nail ½ Bag 9,000 4,500
3” Nail 1 Bags 9,000 9,000
4” Nail 2 bag 9,000 18,000
Fascia Board 15 pieces 1,600 24,000
Ceiling Joist 80 pieces 300 24,000
Asbestos 85 pieces 1,200 102,000
PVC Ceiling Board* 9 Bundle 8,000 72,000
309,250




Stage 3. Plastering

Items Unit Items Unit Price Total price
Plastering Sand 3 Trucks 34,000 102,000
Cement 30 Bags 2,600 78,000
180,000




This quotation is too expensive... Habaa..!!
Are you building a duplex?
The requester needs a one bedroom flat

(1) (Reply)

Amazing Bungalows Affordable @ Abijo Gra To Suit Your Budget And Comfort / How To Calculate Numbers Of Roofing Sheets For Pitch Roof. / Permanet Solution To Rising Damp

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 18
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.