Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures - Properties - Nairaland

Nairaland Forum / Nairaland / General / Properties / Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures (11168 Views)

Construction Of A 4bd/rm Duplex Benin City, Edo State / Construction Of A Twin 4bd/rm Duplex @IBADAN By Dioritestructures / CONSTRUCTION Of A 5bd/rm Duplex @OSAPA LONDON LEKKI LAGOS (2) (3) (4)

(1) (2) (3) (4) (5) (6) (7) (8) (Reply) (Go Down)

Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 3:17pm On Feb 05, 2019
Welcome back on board to all our followers in the past few years.
It's of sadness i found the mother thread and the construction threads removed or hidden, complain has been lounged and hope for rectification and if at all nothing is being done by the admin/moderator we will like to start over again and we make sure nothing of such occur again.
Thanks.



19th April 2019.....
Few days back it has been rectified, for new viewers please kindly click this to see where we started originally:

https://www.nairaland.com/4766518/construction-4bedroom-duplex-bq-abeokuta

Thanks for following.

3 Likes 3 Shares

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Larwin(m): 6:29pm On Feb 05, 2019
Oooops, sorry about that Bro @timtol

1 Like

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 7:11pm On Feb 05, 2019
Larwin:
Oooops, sorry
about that Bro @timtol
Thanks sir.
The challenge is posting those lot of pictures again.
Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 9:37pm On Feb 05, 2019
Proposed 4bedroom duplex with a Bq
Location: Abeokuta, Ogun state
Project duration: 5months(carcass,finishing and furnishing)

_EXTERNAL DIMENSION_: 21.325m By 12m
CLIENT: NON-NAIRALANDER
PLOT LOCATION: ABEOKUTA IN OGUN STATE.
_FEATURES_

[b][/b]Ground Floor*

Entrance
Anteroom
Lobby
Visitor WC
Main Family Lounge
Elevated dining
Kitchen with Island
Store/Laundry
Verandah
Equipped* Room
Lobby
Guest Bedroom ensuit
Dogleg Stairway
*_BQ FEATURES_*
Entrance
Living Room
Lobby
Kitchen
Bedroom ensuit.

[b][/b]First Floor*

Lobby
Upper Family lounge
Library/Office
Sit-Out
Gallery
Lobby
Master Bedroom(T/Bath with W.I.C)
Lobby
Madam Bedroom(T/Bath with W.I.C)
Lobby
Bedroom 4 ensuit
Dogleg Stairway

[b][/b]PENT FLOOR*

Lobby
Pent Lounge
Kitchenette
Toilet
Sit-Out

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 9:51pm On Feb 05, 2019
Few of the pictures i still got at the moment

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 9:56pm On Feb 05, 2019
More

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 10:14pm On Feb 05, 2019
Time we were celebrating German floor.
331bags used...161bags for casting alone.
TMT rods, 10mm 12mm 16mm and 20mm

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 10:16pm On Feb 05, 2019
More

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 10:22pm On Feb 05, 2019
From few pictures we got left.
Block work on first floor

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 10:25pm On Feb 05, 2019
More

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 10:28pm On Feb 05, 2019
More on this from the few pictures we got left

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 10:31pm On Feb 05, 2019
Pent floor decking

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 10:35pm On Feb 05, 2019
Decking for the pent

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 10:36pm On Feb 05, 2019
More

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 10:38pm On Feb 05, 2019
Gate house
Security house,maid and gen house
It's up to roofing level now...update later.
Sorry can't post all and in other like the faulty thread which was tempered with someone yet unknown.

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 10:49pm On Feb 05, 2019
Parapet works

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 10:51pm On Feb 05, 2019
Roofing

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 10:52pm On Feb 05, 2019
More

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 10:57pm On Feb 05, 2019
From the front...more on this

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 11:01pm On Feb 05, 2019
Plastering that's without screeding yet

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 11:03pm On Feb 05, 2019
We continue normal update from now but at least a brief Idea has been given to our new followers of what we are capable of handling.

Thanks for following

1 Like

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 3:31pm On Feb 06, 2019
More

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 3:35pm On Feb 06, 2019
Anteroom with the lobby to access the visitors' toilet.
That's plastering without screeding yet

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 3:35pm On Feb 06, 2019
Guest bedroom

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by ProWalker: 3:44pm On Feb 06, 2019
What is the total cost up to this point and the total estimate for this job to turnkey level?

Thank you

1 Like

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 4:57pm On Feb 06, 2019
ProWalker:
What is the total cost up to this point and the total estimate for this job to turnkey level?

Thank you
For carcass 18.5m
Plastering and window works 7.3m
To turnkey, it depends on the client's taste...more update later both exterior and interior.

1 Like

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 6:50am On Feb 07, 2019
More as we proceed

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 6:05pm On Feb 07, 2019
Parapet plastering

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 8:36pm On Feb 08, 2019
Progress

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 8:45pm On Feb 08, 2019
Electrical works for stairway

1 Like

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 11:15pm On Feb 11, 2019
More

Re: Construction Of A 4bd/rm Duplex With A Bq @Abeokuta by Dioritestructures by Timtol(m): 9:40am On Feb 13, 2019
Always perfect

(1) (2) (3) (4) (5) (6) (7) (8) (Reply)

Federal Mortgage Bank Approves 3,000 Housing Scheme For Workers / Fire Burns Down Edo Police Outpost (Photo) / Choosing Aluminum Windows

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 21
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.