Construction Of A 4 Bedroom Duplex At Otolo, Nnewi, Anambra State - Properties - Nairaland

Nairaland Forum / Nairaland / General / Properties / Construction Of A 4 Bedroom Duplex At Otolo, Nnewi, Anambra State (827 Views)

60 Plots Of Land At Otolo Nnewi Anambra State / Erosion Swallows A Building In Nnewi Anambra State (Video) / Land For Sale At The Unizik Campus Street Otolo Nnewi Anambra State (2) (3) (4)

(1) (Reply) (Go Down)

Construction Of A 4 Bedroom Duplex At Otolo, Nnewi, Anambra State by SOCHDESIGNS(m): 9:16am On Jun 03, 2022
Facilities:
GROUND FLOOR:
*Entance porch
*Ante room (with visitors' toilet)
*Living Room
*Dining
* A large kitchen with store and terrace
* Bedroom 1 (ensuite)
* Service exit.

UPPER FLOOR:
*Bedroom 2&3(all ensuite)
* Master bedroom (with a large bath, walk_in closet and a private balcony)
*Family lounge(with a front balcony).

Architects: Sochdesigns
Project contractor: Soch designs.
Duration:

Re: Construction Of A 4 Bedroom Duplex At Otolo, Nnewi, Anambra State by SOCHDESIGNS(m): 9:20am On Jun 03, 2022
Arrived on 20th may ..after the demolition and evacuation of an existing structure at the site.. setting out was done that same day

Re: Construction Of A 4 Bedroom Duplex At Otolo, Nnewi, Anambra State by SOCHDESIGNS(m): 9:44am On Jun 03, 2022
On Saturday may 21st, we started and finished the excavation of the major walls and proceeded to foot areas that kept collapsing during excavation

Re: Construction Of A 4 Bedroom Duplex At Otolo, Nnewi, Anambra State by SOCHDESIGNS(m): 9:48am On Jun 03, 2022
Proceeded with the full footing on Monday 23rd may

Re: Construction Of A 4 Bedroom Duplex At Otolo, Nnewi, Anambra State by SOCHDESIGNS(m): 9:57am On Jun 03, 2022
On the Tuesday, may 24th, the substructural masonry works began

Re: Construction Of A 4 Bedroom Duplex At Otolo, Nnewi, Anambra State by SOCHDESIGNS(m): 10:03am On Jun 03, 2022
0n Thursday, 26th of may, the substructural works were completed..ready for filling

Re: Construction Of A 4 Bedroom Duplex At Otolo, Nnewi, Anambra State by SOCHDESIGNS(m): 10:14am On Jun 03, 2022
The filling was completed on Monday the 30th, while the compacting (with flat plate compactor) was done on the 31st of may

Re: Construction Of A 4 Bedroom Duplex At Otolo, Nnewi, Anambra State by SOCHDESIGNS(m): 10:18am On Jun 03, 2022
Mass concrete/ German floor on 1st of June

Re: Construction Of A 4 Bedroom Duplex At Otolo, Nnewi, Anambra State by SOCHDESIGNS(m): 10:23am On Jun 03, 2022
And then, by yesterday, 2nd June ...the super-structural works began

Re: Construction Of A 4 Bedroom Duplex At Otolo, Nnewi, Anambra State by SOCHDESIGNS(m): 10:35am On Jun 03, 2022
Duration so far: 12 days ..
.....
(Major)Materials used for the foundation (to DPC/ german floor):
23pcs of 16mm(for column starters)
33pcs of 12mm(for baskets)
150bags of cement
45tons of 1 inch granite.
11 trips of sand.
1,400pcs of 9inches blocks.
#Otolo, Nnewi, Anambra state
#Sochdesigns
Re: Construction Of A 4 Bedroom Duplex At Otolo, Nnewi, Anambra State by XaeV2(f): 12:23pm On Jun 04, 2022
Interesting, and great updates so far.

I already bought a two plots for a combination of a room self con, room & parlor sef con, and two bedroom apartment, in 10 : 10 : 5 respectively, all in a single building (commercial property).

Have you done such project before? How much do you think will complete that?
Re: Construction Of A 4 Bedroom Duplex At Otolo, Nnewi, Anambra State by SOCHDESIGNS(m): 6:08pm On Jun 04, 2022
XaeV2:
Interesting, and great updates so far.

I already bought a two plots for a combination of a room self con, room & parlor sef con, and two bedroom apartment, in 10 : 10 : 5 respectively, all in a single building (commercial property).

Have you done such project before? How much do you think will complete that?
.. Good day. Hope you are doing great....do reach us on 07032308415 for any inquiry
Re: Construction Of A 4 Bedroom Duplex At Otolo, Nnewi, Anambra State by hopman98: 10:48am On Jun 05, 2022
I go follow this thread bumper to bumper. Pls was soil test carried out b4 work began? And why was pad footing used in the foundation?
Re: Construction Of A 4 Bedroom Duplex At Otolo, Nnewi, Anambra State by SOCHDESIGNS(m): 6:25pm On Jun 12, 2022
hopman98:
I go follow this thread bumper to bumper. Pls was soil test carried out b4 work began? And why was pad footing used in the foundation?
...no there was no need for a soil test as we are already conversant with the locality.
Re: Construction Of A 4 Bedroom Duplex At Otolo, Nnewi, Anambra State by SOCHDESIGNS(m): 6:27pm On Jun 12, 2022
......lintel formwork

Re: Construction Of A 4 Bedroom Duplex At Otolo, Nnewi, Anambra State by SOCHDESIGNS(m): 9:25pm On Jun 16, 2022
Leveling underway

Re: Construction Of A 4 Bedroom Duplex At Otolo, Nnewi, Anambra State by FromZeroToHero(m): 8:42pm On Feb 08
Soch please what is the essence of this circled place.

(1) (Reply)

See The N30,000,000 Luxury 3 Bedroom Bungalow Trending In Lagos Now / 10 Acres Available Fully Fenced And GAZETTED At Igbekodo Town Ibeju-lekki / Half A Plot Of Land Needed In Fully Developed Area Of Lagos

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)