Welcome, Guest: Register On Nairaland / LOGIN! / Trending / Recent / New
Stats: 3,153,447 members, 7,819,654 topics. Date: Monday, 06 May 2024 at 07:59 PM

Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity - Business - Nairaland

Nairaland Forum / Nairaland / General / Business / Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity (5910 Views)

Nigeria's Four Refineries To Begin Operation Next Month - NNPC / Nigerian Engineers To Repair Refineries For N99bn –NNPC / Nigeria Hits 39.5mmt Installed Capacity Of Cement Production (2) (3) (4)

(1) (2) (Reply) (Go Down)

Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by Kobojunkie: 4:48pm On Jul 09, 2012
[size=14pt]Two of Nigeria’s refineries pack up …others produce at 25% of installed capacity[/size]

http://www.punchng.com/news/two-of-nigerias-refineries-pack-up-others-produce-at-25-of-installed-capacity/


The four Federal Government-owned refineries in the country are producing refined petroleum products at an abysmally low level.

Investigations by SATURDAY PUNCH show that the refineries are producing at about 25 per cent of installed capacity.

The investigations show that only two of the refineries – the Warri and Kaduna refineries – are partially functional at the moment.

The remaining two located in Port Harcourt are struggling with faults that have prevented them from adding to the quantity of fuel produced locally.

The old refinery in Port Harcourt has not been in operation for several months, while the new refinery, which before now was contributing to the quantity of locally-refined products, has also stopped operation because of lack of electricity.

Specifically, the two refineries in Port Harcourt have not been working since January 2012, when the anti-subsidy removal protests spearheaded by organised labour and civil society groups took place.

SATURDAY PUNCH discovered that the new Port Harcourt refinery had struggled with epileptic operations because of the activities of vandals, who had damaged its pipeline at the Ogoni area of Rivers State. This had a serious impact on its operational capacity.

The National President of the Petroleum and Natural Gas Senior Staff Association of Nigeria, Mr. Babatunde Ogun, attributed the low level of productivity of the nation’s refineries to neglect by successive administrations.

[size=13pt][b]He said the performance of the refineries had become poor because of lack of deserved attention to their maintenance.

Ogun urged the Federal Government to take the issue of the Turn Around Maintenance of the refineries more seriously by engaging credible firms to handle them.

The unionist argued that the delay in the commencement of the Turn Around Maintenance of the refineries had made the nation to depend on imported refined petroleum products.

He lamented the alarming drop in the production capacity of the refineries, which is put at 25 per cent of their installed capacities and urged the government to embark on urgent steps to remedy the situation.

He said, “The refineries have been neglected for a very long time and it has affected the level of their capacities for production.

“I think the Federal Government should take the issue of the Turn Around Maintenance of these refineries more seriously.

“They should look for credible people with guarantee from the banks to do the Turn Around Maintenance of the refineries so that they would be sure of a credible job.

“The delay in carrying out the Turn Around Maintenance is only encouraging the continuous importation of fuel from outside the country.

“We are producing below capacity; we are producing between 20 and 25 per cent of installed capacity.

“The old Port Harcourt Refinery has been down for some time now. The new one too has been down for some time now because of lack of inadequate supply of electricity to power the plants. The government should look for a way to fix the power problem affecting the refineries.

“The issue of frequent removal of the Group Managing Director of the Nigerian National Petroleum Corporation is not also helping. The GMD and his team should be allowed to stabilise to carry out the maintenance.

“Another thing is that the ministry should not interfere with the operations of the GMD of NNPC and his team.

“The TAM should be done once in every 22 months or thereabout; so, they should start now because the more we wait, the longer it takes.

“One other thing is that it takes us too long a time to take decisions in this country and it has its effects on us.”
[/b][/size]


[size=13pt]However, the details on the refineries provided by the Acting Group General Manager, Public Affairs, Mr. Fidel Pepple, on Thursday, contradicted the claim by the PENGASSAN National President and others, who spoke on the state of the refineries.

Pepple put the production capacity of the Warri Refinery and Petrochemical Company at over 70 per cent of installed capacity.

According to his analysis, the WRPC has a production capacity with Crude Distillation Unit of 77 per cent; Vacuum Distillation Unit, 70 per cent; and Fluid Catalytic Cracking Unit, 80 per cent.

Pepple put the performance of the Kaduna Refinery at 60 per cent of installed capacity.

The NNPC acting spokesman said that the Port Harcourt refinery was “ready for a start-up after some repair work but awaiting crude supply.”
[/size]

According to him, the PHRC would undergo Turn Around Maintenance in the fourth quarter of 2012, the KRPC in the second quarter of 2013 and the WRPC in the fourth quarter of 2013 or the first quarter of 2014.

Pepple, who stated that TAM should be carried out every two years, noted that the last TAM was carried out on the PHRC in 1999/2000, WRPC in 2004 and KRPC in 2008.

Although the NNPC acting spokesman was silent on the cost implication of the TAM to the country, an online news agency, The Will, quoted the acting Managing Director of the WRPC, Mr. Samuel Babatunde, as having said that the TAM in the company would cost N94.2bn.

Babatude was also quoted as having said that the TAM for the Port Harcourt refinery would gulp $463m.

Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by blacksta(m): 4:51pm On Jul 09, 2012
The More you look the less you see - Yet TAM contracts was awarded , what about the 24 Months deadline - You people dont know Nigeria at all. You just like giving yourselves Mental mastu buation ( that everything is working alright) which differs from reality on ground.
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by Kobojunkie: 5:02pm On Jul 09, 2012
This comes only 4 months to the November Deadline for full capacity oo! If anyone remembers well, the Petroleum Minister promised Nigerians that all the Refineries would be working at full Capacity by November of 2012.

http://nnpcgroup.com/PublicRelations/NNPCinthenews/tabid/92/articleType/ArticleView/articleId/343/PH-refineries-to-work-at-full-capacity-November.aspx
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by Kobojunkie: 5:23pm On Jul 09, 2012
Port Harcourt Refineries are expected to work optimally from October this year after a Turn-Around Maintenance (TAM), the NNPC has announced. Group Executive Director, Refining and Petrochemicals, Engr Philip Chukwu, said this in Port Harcourt recently during an inspection of the refineries with officials of Maire Tecnimont, the contractors which the Federal Government engaged for the TAM. Chukwu, who decried the lack of maintenance of the twin Port Harcourt refineries in the last 12 years, commended the Federal Government for engaging the original constructors of the refineries for the TAM, the Chiyoda Group of Japan. "Everyone knows that the refineries have not been properly maintained over the years and we have had to manage things. What we are doing now is to have the TAM and complete rehabilitation of the refineries by the original contractors," he said. The two Port Harcourt refineries, which consist of the old refinery with capacity to process 60, 000 b/d and 150, 000 b/d, respectively, had been functioning at low capacity with the old one not working at the moment because of lack of maintenance. Chukwu explained that the TAM, which would start in October, would require a total shutdown of the plants for between 45 days and 60 days to ensure a thorough job. He said the TAM and rehabilitation process would also entail overhauling the supply chain and pipelines that bring crude oil and capacity building for staff so as to meet international best practice. He said the NNPC was also working with all stakeholders, including security operatives, to ensure the pipelines were safe and no longer vandalised. PHRC Managing Director, Engr Anthony U. Ogbuigwe, in his remarks after taking the contractors round the plants expressed optimism that the refinery would begin to work at 90 per cent capacity by November this year. He said preliminary work on the TAM started since late 2010 and the present stage would signal the return to full production of the refineries. He said that the NNPC had already placed order for all the equipment necessary for the TAM, noting that the inspection by the management of the construction company would help to fast-track the whole process. Managing Director, Maire Tecnimont Group of Italy, Mr Roberto Bertocco, said in his remarks that the company which had been on ground in Nigeria for the past 30 years would be working with JGC Engineering, Japan, original builders of the refinery. "I can assure you of a very good job on this project. We have been working with JGC in many parts of the world, so we are also collaborating with them on this project because we have been on ground in Nigeria for the past 30 years," he said. He expressed optimism that the refineries would be working at full capacity by the end of the year. It would be recalled that the old Port Harcourt refinery was built in 1965 with an initial capacity of 35,000 b/d which was later expanded to 60,000 bpd in 1972. The new wing of the refinery was built in 1989 with a 150,000 b/d capacity to meet local consumption of petroleum products and for export.A Memorandum of Understanding (MoU) is expected to be signed between the management of Maire Tecnimont, the Minister of Petroleum Resources, Mrs Dieziani Allison-Madueke and NNPC officials in Abuja.
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by 2mch(m): 5:26pm On Jul 09, 2012
grin grin grin grin grin

[size=18pt]WOW[/size]

What a shocker. Were they even working in the first place?
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by Kobojunkie: 6:25pm On Jul 09, 2012
^^^ Good question. Over the last 2 years, We have read of Government investing billions into "increasing capacity" of our existing refineries. So this news is counter to what is expected to have happened in that period. 25% Capacity is about where Nigeria was back in 2005.
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by Nobody: 7:02pm On Jul 09, 2012
Nothing new, the refineries have not been working up to its expected production levels for some years now. TAM contracts are given to highly connected politicians who need some cash to spend. I think the refineries should be to sold the highest bidder as soon as possible to avoid over bloated overhead expenses and maintenance costs
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by Gbawe: 7:14pm On Jul 09, 2012
This report does not surprise those who don't fool themselves or celebrate corruption and abject mediocrity. When we said GEJ was, more or less, deliberately and cynically, for his own agenda, killing off our Refineries by the mad act of conceding them into the hands of the grand home of corruption NNPC for 24 months, the immature children shouted and wept that we "hate" Mr. President.

The worst is yet to come. Every PDP President feels, automatically, that controlling refineries through chosen 'Oligarch' minions (Dangote, Otedola et al) is a licence to print money. OBJ tried to sell refineries to the usual AGIPS (Otedola et al) for pittance but Yar Adua reversed that.

No doubt, going by how he was leading, Yar Adua would have made his own pitch, at the right time, towards gaining control of our Refineries but fate intervened in my opinion.

GEJ, meanwhile, has started early. Conceding refineries to the most corrupt entity in the land is proof GEJ never really wanted our refineries working well because that was not in his 'masterplan'. The plan is to mire refineries in inefficiency till they can be sold off to GEJ's AGIP pals like Otedola, Dangote et al under a "privatisation scheme".

This will keep happening as long as we keep gaining vacuously greedy empty barrels, with no commitment at all to anything but crude self-enrichment, as Presidents. Our Refineries not working, on so many levels, abet the various avenues of easy wealth acquisition and I don't expect to see Nigerian refineries work optimally under anyone other than a leader with utmost integrity and little interest in garish wealth often accumulated for the sake of it.

1 Like

Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by dayokanu(m): 7:37pm On Jul 09, 2012
When you think retardeens govt cant get worse, It actually does
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by Gbawe: 8:35pm On Jul 09, 2012
dayokanu: When you think retardeens govt cant get worse, It actually does

My brother, what does this report convey if not a directly damning indictment of another colossal GEJ failure in a critical sector ?

The NNPC was given the task of reviving our refineries within 24 months even as the raving lunatic in the Streets shouted that this was an insane thing for Mr. President to do!!!! Why, even if GEJ wishes to defy logic with his crazy action, is anyone surprised the NNPC now only delivers failure? Over to you 40 laptop crew .
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by Kobojunkie: 9:24pm On Jul 09, 2012
I am more concerned about the lies, and worry that this might be more wide-spread of a problem than we are aware of.
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by Kobojunkie: 3:39am On Jul 10, 2012
Greenfield Refineries: Funding, FG’s Approval Stall New Take-off Date

http://www.thisdaylive.com/articles/greenfield-refineries-funding-fg-s-approval-stall-new-take-off-date/119712/


There are indications that the much-awaited three Greenfield Refineries billed for Lagos, Bayelsa and Kogi States, scheduled to come on stream by 2017 may not be realizable.

This, it was gathered, is because the construction earlier planned to begin this month has been put on hold due to the Nigerian National Petroleum Corporation’s (NNPC’s) inability to secure Federal Government’s approval to commence work.
THISDAY checks revaled that the NNPC, which is to provide 20 per cent of the amount budgeted for the project is still planning to put together a consortium for the purpose of raising the funds.


The NNPC and the China State Construction Engineering Corporation (CSCEC) Limited had in 2010 signed a Memorandum of Understanding (MoU) for the joint sourcing of funds for the construction of three new refineries and a petrochemical plant in Nigeria under a $28.5-billion provisional deal.

The project had been envisaged to increase Nigeria’s refining capacity to over one million barrels per day (bpd) from the current 445,000 bpd capacity and stem the flood of importation of refined products into the country.
The parties had fixed (this month as the new date for the commencement of construction, following the NNPC’s inability to meet the May 13, 2011 date.

Front End Engineering and Design (FEED), site preparation and infrastructure had been scheduled to start in February 2012 to be followed by construction works this month of July.

Under the agreement, the Industrial and Commercial Bank of China (ICBC), the world’s largest bank, was to provide 80 per cent of the $11.3 billion budgeted for the project, while the NNPC will provide 20 per cent equity, to be diluted for private sector participation later.

However, a source familiar with the project told THISDAY yesterday that the project will no longer come on stream as earlier planned because the NNPC is still awaiting Federal Government’s approval to begin construction. The source said aside from the delay in securing government’s approval to begin construction, two other major challenges were the issue of funding and the delay by the National Refinery Special Task Force to submit the report of its findings on the traditional refineries, located in Warri, Kaduna and Port Harcourt.

Commenting on the project, the General Manager at the NNPC’s Group Public Affairs department, Mr. Fidel Pepple, told THISDAY that the Final Investment Decision (FID) had been completed and soil analysis revealed that the project is viable.
He explained that commencement of construction could not take-off as scheduled because the NNPC is still awaiting government’s approval.

On the issue of funding, Pepple confirmed that NNPC plans to float a consortium to enable it raise enough funds for the project.
He said: “The issue of funding is not a problem. What we are waiting for is federal government’s approval to commence construction, once that is done, we will put together a consortium to raise the funds, as the NNPC alone cannot do it”.

The initial plan was that each of the Greenfield Refineries would be able to process around 250,000 barrels of oil a day, but their combined capacity was later downsized to 400,000 barrels per day. Under the new arrangement, the capacities of the plants to be built in Kogi and Bayelsa were reduced to 100,000 barrels per day (bpd) each, while the one to be located in Lagos, will now have the capacity for 200,000 bpd.

THISDAY gathered that the capacities of the plants were downsized based on the new Detailed Feasibility Study (DFS) prepared by Wood Makenzie & Foster Will.

The NNPC had repeatedly stated that the new refineries, when completed, would help to eliminate the country’s current reliance on imported petroleum products and position it (NNPC) to engage profitably in the international trading of refined petroleum products.
The delay in its take-off is considered a major setback to Nigeria’s plan to increase her refining capacity to over one million barrels per day by 2017.
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by OAM4J: 3:46am On Jul 10, 2012
Fresh air!
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by Nobody: 4:17am On Jul 10, 2012
Na wa ooo grin grin grin grin grin grin grin grin grin grin grin grin grin
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by Mandelaguy(m): 5:27am On Jul 10, 2012
Same reason why NNPC is being put up for sanity,probity and privatisation. The problem is that most of you read without proper analysis and news digestion. The corruption in that corporation was massive,just like in every key sector and establishment in this country. Anyway,enjoy your fruitless smear campaign.
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by Zutchy: 7:08am On Jul 10, 2012
Kobojunkie: Greenfield Refineries: Funding, FG’s Approval Stall New Take-off Date

http://www.thisdaylive.com/articles/greenfield-refineries-funding-fg-s-approval-stall-new-take-off-date/119712/


There are indications that the much-awaited three Greenfield Refineries billed for Lagos, Bayelsa and Kogi States, scheduled to come on stream by 2017 may not be realizable.

This, it was gathered, is because the construction earlier planned to begin this month has been put on hold due to the Nigerian National Petroleum Corporation’s (NNPC’s) inability to secure Federal Government’s approval to commence work.
THISDAY checks revaled that the NNPC, which is to provide 20 per cent of the amount budgeted for the project is still planning to put together a consortium for the purpose of raising the funds.


The NNPC and the China State Construction Engineering Corporation (CSCEC) Limited had in 2010 signed a Memorandum of Understanding (MoU) for the joint sourcing of funds for the construction of three new refineries and a petrochemical plant in Nigeria under a $28.5-billion provisional deal.

The project had been envisaged to increase Nigeria’s refining capacity to over one million barrels per day (bpd) from the current 445,000 bpd capacity and stem the flood of importation of refined products into the country.
The parties had fixed (this month as the new date for the commencement of construction, following the NNPC’s inability to meet the May 13, 2011 date.

Front End Engineering and Design (FEED), site preparation and infrastructure had been scheduled to start in February 2012 to be followed by construction works this month of July.

Under the agreement, the Industrial and Commercial Bank of China (ICBC), the world’s largest bank, was to provide 80 per cent of the $11.3 billion budgeted for the project, while the NNPC will provide 20 per cent equity, to be diluted for private sector participation later.

However, a source familiar with the project told THISDAY yesterday that the project will no longer come on stream as earlier planned because the NNPC is still awaiting Federal Government’s approval to begin construction. The source said aside from the delay in securing government’s approval to begin construction, two other major challenges were the issue of funding and the delay by the National Refinery Special Task Force to submit the report of its findings on the traditional refineries, located in Warri, Kaduna and Port Harcourt.

Commenting on the project, the General Manager at the NNPC’s Group Public Affairs department, Mr. Fidel Pepple, told THISDAY that the Final Investment Decision (FID) had been completed and soil analysis revealed that the project is viable.
He explained that commencement of construction could not take-off as scheduled because the NNPC is still awaiting government’s approval.

On the issue of funding, Pepple confirmed that NNPC plans to float a consortium to enable it raise enough funds for the project.
He said: “The issue of funding is not a problem. What we are waiting for is federal government’s approval to commence construction, once that is done, we will put together a consortium to raise the funds, as the NNPC alone cannot do it”.

The initial plan was that each of the Greenfield Refineries would be able to process around 250,000 barrels of oil a day, but their combined capacity was later downsized to 400,000 barrels per day. Under the new arrangement, the capacities of the plants to be built in Kogi and Bayelsa were reduced to 100,000 barrels per day (bpd) each, while the one to be located in Lagos, will now have the capacity for 200,000 bpd.

THISDAY gathered that the capacities of the plants were downsized based on the new Detailed Feasibility Study (DFS) prepared by Wood Makenzie & Foster Will.

The NNPC had repeatedly stated that the new refineries, when completed, would help to eliminate the country’s current reliance on imported petroleum products and position it (NNPC) to engage profitably in the international trading of refined petroleum products.
The delay in its take-off is considered a major setback to Nigeria’s plan to increase her refining capacity to over one million barrels per day by 2017.
If the fed govt relally is the one holding back the take off of the refineries then I want you all to read in between the lines,they are delaying the takeoff of a $28billion deal for three refineries that would add 400,000bpd to be completed in 2017 but then went ahead to sign a totally different deal for $4.8billion for six refineries that would add a total of 180,000bpd to be completed in 2014,what does this tell you,this was a fed govt deal now and not an NNPC deal,the federal govt is aware of the fact that Nigerians need their problems to be solved or want to see something being done to solve it,they did not cancel the NNPC,CSCEC MOU,that one still stands and will still be carried out,but they want to start alleviating our problems as soon as possible.
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by basher(m): 8:29am On Jul 10, 2012
Kobojunkie: Greenfield Refineries: Funding, FG’s Approval Stall New Take-off Date

http://www.thisdaylive.com/articles/greenfield-refineries-funding-fg-s-approval-stall-new-take-off-date/119712/


There are indications that the much-awaited three Greenfield Refineries billed for Lagos, Bayelsa and Kogi States, scheduled to come on stream by 2017 may not be realizable.

This, it was gathered, is because the construction earlier planned to begin this month has been put on hold due to the Nigerian National Petroleum Corporation’s (NNPC’s) inability to secure Federal Government’s approval to commence work.
THISDAY checks revaled that the NNPC, which is to provide 20 per cent of the amount budgeted for the project is still planning to put together a consortium for the purpose of raising the funds.


The NNPC and the China State Construction Engineering Corporation (CSCEC) Limited had in 2010 signed a Memorandum of Understanding (MoU) for the joint sourcing of funds for the construction of three new refineries and a petrochemical plant in Nigeria under a $28.5-billion provisional deal.

The project had been envisaged to increase Nigeria’s refining capacity to over one million barrels per day (bpd) from the current 445,000 bpd capacity and stem the flood of importation of refined products into the country.
The parties had fixed (this month as the new date for the commencement of construction, following the NNPC’s inability to meet the May 13, 2011 date.

Front End Engineering and Design (FEED), site preparation and infrastructure had been scheduled to start in February 2012 to be followed by construction works this month of July.

Under the agreement, the Industrial and Commercial Bank of China (ICBC), the world’s largest bank, was to provide 80 per cent of the $11.3 billion budgeted for the project, while the NNPC will provide 20 per cent equity, to be diluted for private sector participation later.

However, a source familiar with the project told THISDAY yesterday that the project will no longer come on stream as earlier planned because the NNPC is still awaiting Federal Government’s approval to begin construction. The source said aside from the delay in securing government’s approval to begin construction, two other major challenges were the issue of funding and the delay by the National Refinery Special Task Force to submit the report of its findings on the traditional refineries, located in Warri, Kaduna and Port Harcourt.

Commenting on the project, the General Manager at the NNPC’s Group Public Affairs department, Mr. Fidel Pepple, told THISDAY that the Final Investment Decision (FID) had been completed and soil analysis revealed that the project is viable.
He explained that commencement of construction could not take-off as scheduled because the NNPC is still awaiting government’s approval.

On the issue of funding, Pepple confirmed that NNPC plans to float a consortium to enable it raise enough funds for the project.
He said: “The issue of funding is not a problem. What we are waiting for is federal government’s approval to commence construction, once that is done, we will put together a consortium to raise the funds, as the NNPC alone cannot do it”.

The initial plan was that each of the Greenfield Refineries would be able to process around 250,000 barrels of oil a day, but their combined capacity was later downsized to 400,000 barrels per day. Under the new arrangement, the capacities of the plants to be built in Kogi and Bayelsa were reduced to 100,000 barrels per day (bpd) each, while the one to be located in Lagos, will now have the capacity for 200,000 bpd.

THISDAY gathered that the capacities of the plants were downsized based on the new Detailed Feasibility Study (DFS) prepared by Wood Makenzie & Foster Will.

The NNPC had repeatedly stated that the new refineries, when completed, would help to eliminate the country’s current reliance on imported petroleum products and position it (NNPC) to engage profitably in the international trading of refined petroleum products.
The delay in its take-off is considered a major setback to Nigeria’s plan to increase her refining capacity to over one million barrels per day by 2017.

D
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by Demdem(m): 8:30am On Jul 10, 2012
13. With regards to the 445,000 bpd allocation to NNPC , the Committee believes that with the current refining capacity of 53% and the SWAP/Offshore processing arrangement of the balance of 47%, it is sufficient to provide the nation with the following products:
a. 40 Million Litres Per Day (MLPD) of PMS,
b. 10 MLPD of Kerosene (HHK)
c. 8.97 MLPD of Diesel (AGO) ,
d. 0.62 MLPD of LPG and
e. 2.31 MLPD of FO
It is only AGO whose average daily consumption of 12 million Litres per day will not be achieved in full. Since AGO has been deregulated, other marketers can make up for the 3.03 MLPD AGO shortfalls. The implication of this finding is that if NNPC properly manages the allocation of 445 bpd efficiently, the availability of the products can be achieved by the NNPC alone. This contrasts the situation where in 2009-2011 NNPC got the daily allocation of 445,000bpd and the nation still had to import through Marketers.
Curiously, although NNPC confirmed that it makes some savings of about =N= 11.00 per litre refining locally than import, it could not be established that the Corporation reflects this cost differential in its claims to subsidy.
The Committee recommends

What exactly is the truth?
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by basher(m): 8:31am On Jul 10, 2012
Kobojunkie: Greenfield Refineries: Funding, FG’s Approval Stall New Take-off Date

http://www.thisdaylive.com/articles/greenfield-refineries-funding-fg-s-approval-stall-new-take-off-date/119712/


There are indications that the much-awaited three Greenfield Refineries billed for Lagos, Bayelsa and Kogi States, scheduled to come on stream by 2017 may not be realizable.

This, it was gathered, is because the construction earlier planned to begin this month has been put on hold due to the Nigerian National Petroleum Corporation’s (NNPC’s) inability to secure Federal Government’s approval to commence work.
THISDAY checks revaled that the NNPC, which is to provide 20 per cent of the amount budgeted for the project is still planning to put together a consortium for the purpose of raising the funds.


The NNPC and the China State Construction Engineering Corporation (CSCEC) Limited had in 2010 signed a Memorandum of Understanding (MoU) for the joint sourcing of funds for the construction of three new refineries and a petrochemical plant in Nigeria under a $28.5-billion provisional deal.

The project had been envisaged to increase Nigeria’s refining capacity to over one million barrels per day (bpd) from the current 445,000 bpd capacity and stem the flood of importation of refined products into the country.
The parties had fixed (this month as the new date for the commencement of construction, following the NNPC’s inability to meet the May 13, 2011 date.

Front End Engineering and Design (FEED), site preparation and infrastructure had been scheduled to start in February 2012 to be followed by construction works this month of July.

Under the agreement, the Industrial and Commercial Bank of China (ICBC), the world’s largest bank, was to provide 80 per cent of the $11.3 billion budgeted for the project, while the NNPC will provide 20 per cent equity, to be diluted for private sector participation later.

However, a source familiar with the project told THISDAY yesterday that the project will no longer come on stream as earlier planned because the NNPC is still awaiting Federal Government’s approval to begin construction. The source said aside from the delay in securing government’s approval to begin construction, two other major challenges were the issue of funding and the delay by the National Refinery Special Task Force to submit the report of its findings on the traditional refineries, located in Warri, Kaduna and Port Harcourt.

Commenting on the project, the General Manager at the NNPC’s Group Public Affairs department, Mr. Fidel Pepple, told THISDAY that the Final Investment Decision (FID) had been completed and soil analysis revealed that the project is viable.
He explained that commencement of construction could not take-off as scheduled because the NNPC is still awaiting government’s approval.

On the issue of funding, Pepple confirmed that NNPC plans to float a consortium to enable it raise enough funds for the project.
He said: “The issue of funding is not a problem. What we are waiting for is federal government’s approval to commence construction, once that is done, we will put together a consortium to raise the funds, as the NNPC alone cannot do it”.

The initial plan was that each of the Greenfield Refineries would be able to process around 250,000 barrels of oil a day, but their combined capacity was later downsized to 400,000 barrels per day. Under the new arrangement, the capacities of the plants to be built in Kogi and Bayelsa were reduced to 100,000 barrels per day (bpd) each, while the one to be located in Lagos, will now have the capacity for 200,000 bpd.

THISDAY gathered that the capacities of the plants were downsized based on the new Detailed Feasibility Study (DFS) prepared by Wood Makenzie & Foster Will.

The NNPC had repeatedly stated that the new refineries, when completed, would help to eliminate the country’s current reliance on imported petroleum products and position it (NNPC) to engage profitably in the international trading of refined petroleum products.
The delay in its take-off is considered a major setback to Nigeria’s plan to increase her refining capacity to over one million barrels per day by 2017.
put together a consortium for the purpose of raising the funds.[/size][/b]

Greenfield what!!

They should concentrate time & effort to get the ones on ground working to their fullest capacity before wasting money on politically motivated-flight of fantasy-appeasing-white elephant refineries!
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by onatisi(m): 8:48am On Jul 10, 2012
DONT WORRY WE ARE ON TOP OF THE SITUATION AND BY THE WAY I DONT GIVE A DAMM
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by enehaluh(m): 8:55am On Jul 10, 2012
Disseminated institutional Failure Sequel 2 Systematic Sabotage By d same Govt. Elected 2 Serve....Naija Cast abeg!!!
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by bakila: 8:58am On Jul 10, 2012
Gbawe:

My brother, what does this report convey if not a directly damning indictment of another colossal GEJ failure in a critical sector ?

The NNPC was given the task of reviving our refineries within 24 months even as the raving lunatic in the Streets shouted that this was an insane thing for Mr. President to do!!!! Why, even if GEJ wishes to defy logic with his crazy action, is anyone surprised the NNPC now only delivers failure? Over to you 40 laptop crew .
Is that forty laptop thing true? Come to thing of it each laptop will go for about two million naira.

On the topic, this Goverment does not care. Next year campaign will start and they will create varoius dramas to distract us. Only a small percentage of Nigerian pay attention to topics like these. Most are thinking of how to make money out of a pathetic situation. It matters less if the situation becomes worse.
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by alluson(m): 9:04am On Jul 10, 2012
what happened to the remaining 75%, do they develop wings and fly to south africa...in Nigeria, this is called ABRAKATABRA
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by Gbawe: 9:06am On Jul 10, 2012
onatisi: DONT WORRY WE ARE ON TOP OF THE SITUATION AND BY THE WAY I DONT GIVE A DAMM

My guy, Mr.President showed he did not "give a damn" the minute he conceded our refineries into the hideously corrupt hands of the NNPC for 24 months.

We have always known the NNPC to be one of, if not the most corrupt Government parastatal existing today. In light of the subsidy scam revelations , with heavy involvement of the NNPC, it is crystal clear Mr. President is deliberately sabotaging Nigeria's efforts of optimally refining its crude endowment which , if achieved, would genuinely bring an end to avenues of monumental corruption for a few and continuous suffering for the majority.
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by Babamide(m): 9:06am On Jul 10, 2012
Bleeping awesome. Dividend of subsidy removal. So Diezani lied to our face
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by onatisi(m): 9:12am On Jul 10, 2012
bakila:
Is that forty laptop thing true? Come to thing of it each laptop will go for about two million naira.

On the topic, this Goverment does not care. Next year campaign will start and they will create varoius dramas to distract us. Only a small percentage of Nigerian pay attention to topics like these. Most are thinking of how to make money out of a pathetic situation. It matters less if the situation becomes worse.

wht is there to pay attention in this topic?since the time of abacha TAM has been a major souce of revenue for our politicians gani cried nd shouted about it til he died wetting happened,tam david west has always been saying it.until u understand what corruption is in nigeri such news like this will still be sounding strange.maybe u should know that our refinenries have been in this camatose stage for 19 years,the baby born then is now inthe university nd u want ppl to still waste time on it.na wah ooo
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by BlackBaron: 9:20am On Jul 10, 2012
Jonathan should stop making promises he can never deliver.

Everyday, he strikes new lows yet his army of supporters would still throng here trying to justify the situation
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by onatisi(m): 9:23am On Jul 10, 2012
BlackBaron: Jonathan should stop making promises he can never deliver.

Everyday, he strikes new lows yet his army of supporters would still throng here trying to justify the situation

thou shall know the truth and the truth shall set u free
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by onatisi(m): 9:25am On Jul 10, 2012
BlackBaron: Jonathan should stop making promises he can never deliver.

Everyday, he strikes new lows yet his army of supporters would still throng here trying to justify the situation

infact u make me laugh u are relying or banking on promises made by a nigerian politician.
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by blacksta(m): 9:33am On Jul 10, 2012
When is the house going to impeach this president, people are dying in the north, Anti people policies is gradually killing the public.
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by onatisi(m): 9:39am On Jul 10, 2012
blacksta: When is the house going to impeach this president, people are dying in the north, Anti people policies is gradually killing the public.
who do u want to start the impechment process?PDP or ACN?or are u the one to start it.
Re: Two Of Nigeria’s Refineries Pack Up …others Produce At 25% Of Installed Capacity by alaoeri: 9:39am On Jul 10, 2012
And some people 'll be carrying a propaganda that the government have sign a contract with one Vulcan to build 6refineries when the ones ωε have aren't working.

(1) (2) (Reply)

Is Engineer Godson Sunday A Scam / Pictures Of P.o.p Ceiling Design / DIY Candle Making Business In Nigeria | Beginners Guide!

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 104
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.