Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 1:15pm On Jan 17, 2024 |
Planks have also been bought which the carpenter will use in boarding the pillars in the building
|
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 1:10pm On Jan 17, 2024 |
The staters pillars are also been tied..
We'll first run the pillars from foundation to dpc level afterwhich we'll join when doing lintel
|
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 1:08pm On Jan 17, 2024 |
Styropes are been tied
|
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 1:07pm On Jan 17, 2024 |
We've started with iron work already as iron benders have commenced with their trade.. |
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 5:18am On Jan 17, 2024 |
erico2k2: OK I was just generalising the whole Edo north my bad, I have beeen to Sabo Ginda ora and its environs back in the days. PS how do you guys upload YouTube videos? I have tried it won't let me Send a message on WhatsApp. This thread is mainly for our ongoing construction project as I wouldn't want to derail it. |
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 10:22pm On Jan 16, 2024 |
erico2k2: Well one following. How do you manage with water cos those areas are no go areas for water. Welcome bro.. Water isn't an issue here in "Afuze emai" as there are boreholes in this area.. Only place where water is difficult is in "Esan" were we rely on either water gathered from rain that falls into a reservoir or tanks going to streams to supply water to construction sites... Though there is some places were there are bore holes like "Irrua" etc |
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 6:24pm On Jan 16, 2024 |
|
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 6:23pm On Jan 16, 2024 |
More photos :
|
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 6:22pm On Jan 16, 2024 |
Photos from the work progress today..
|
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 6:21pm On Jan 16, 2024 |
Good evening my people, we've been able to achieve dpc level today...
We're to commence with iron work and carpentry work by tomorrow as we're set for the next phase which is tying and boarding the pillars |
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 5:54pm On Jan 15, 2024 |
|
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 5:40pm On Jan 15, 2024 |
More pictures :
|
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 5:39pm On Jan 15, 2024 |
Good evening my people...
It's evening already and we've taken part of the building to dpc level...
We give God all the Glory for the progress so-far...
Photos of work progress below :
|
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 10:53am On Jan 15, 2024 |
Work progress
|
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 9:51am On Jan 15, 2024 |
Forming ongoing
|
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 8:49am On Jan 15, 2024 |
|
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 8:06am On Jan 15, 2024 |
Good morning my people, It's Monday morning and we're on site today as we're set to commence with forming and blocks laying |
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 4:25pm On Jan 14, 2024*. Modified: 7:12pm On Jan 14, 2024 |
|
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 4:15pm On Jan 14, 2024 |
It's evening already and we're about rounding up with the foundation blinding...
We'll be commencing with forming tomorrow |
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 10:50am On Jan 14, 2024 |
We've commenced with foundation blinding...
|
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 10:48am On Jan 14, 2024 |
Leemekzy: Following. You're welcome onboard my brother  |
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 9:50am On Jan 14, 2024 |
Concerete is been mixed as we'll kick start with foundation blinding soon
|
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 9:37am On Jan 14, 2024 |
We're rounding up with foundation digging as we're preparing to start foundation blinding |
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 9:36am On Jan 14, 2024 |
Good morning and happy Sunday my people...
We're on site this morning as we've commenced work already |
Properties › Re: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 9:36am On Jan 14, 2024 |
[quote author=floshady02 post=127862161][/quote]10m is quite on a high side |
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 4:59pm On Jan 12, 2024 |
|
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 4:48pm On Jan 12, 2024 |
We're making progress on our ongoing construction...
Closer view of the foundation...
|
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 12:18pm On Jan 12, 2024 |
More photos:
|
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 12:16pm On Jan 12, 2024 |
We've commenced digging of foundation trenches..
|
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 9:41am On Jan 12, 2024 |
Squaring the building
|
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 9:09am On Jan 12, 2024 |
Materials are on ground already as we're set to kick start with our construction project
|
Properties › Re: Construction Of A 3bedroom Bungalow Semi Detached Building In Afuze Owan East by AsomArchitectNG(op): 9:05am On Jan 12, 2024 |
Site view this morning...
|