PropertiesRe: Construction Of A 3bedroom Bungalow With Bq In Oron Akwa Ibom by AsomArchitectNG(op): 9:44am On Apr 12, 2023
geladinho1:
Nice one i love ur explanation. I have 100 / 100 piece of plot can i have 4 bed room and 4 self contains on the land
Thanks alot

Yes.. A 100ft by100ft can contain a 4-bedroom bungalow and 4-self contain
PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 9:42am On Apr 12, 2023
Block work also ongoing on the bush- bar
PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 9:39am On Apr 12, 2023
The form work used in the concrete fascia(parapet)are been removed so dressing can start..

PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 9:37am On Apr 12, 2023
Morning my people, we're on site already this morning as work commences again today
PropertiesRe: About To Build? Check Out Some Of Our Building Designs And Projects Executed. by AsomArchitectNG(op): 10:27pm On Apr 10, 2023
Contact our expert design and construction team Let's discuss your next building project...

Tel/whatsapp: 081 441 81499

PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 4:58pm On Apr 10, 2023
More photos :
Yes!!! It's coming out really great

PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 4:57pm On Apr 10, 2023
Good evening my people, here's the work progress on the roofing today as we'll be rounding up tomorrow and also commence with dressing of the parapet(concrete fascia)

PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 7:52am On Apr 10, 2023
Good morning my people, we're on site this morning to commence with the day's work as roofing of the house continues.... I'll bring in pictures updates much later
PropertiesRe: Design And Construction Of A Mini 2-bedroom Flat by AsomArchitectNG(m): 8:28pm On Apr 09, 2023
It's a good design
PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 6:36pm On Apr 08, 2023
HathawayStark:
Boss, i have an upcoming building project at owan west. I love your works.
Thanks boss... We'll be glad to handle your upcoming project
PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 5:25pm On Apr 08, 2023
We're grateful to God Almighty for the work progress today...

We're still on the roofing as work is moving gradually

PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 11:28am On Apr 08, 2023
Dancebreaker:
This is really good!

What is the total budget for this project?

How much spent so far?
Total budget for the project is 15m naira
PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 10:17am On Apr 08, 2023
Good morning y'all..... We're on site already this morning as roofing of the building continues.. I'll bring in pictures updates much later.
PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 6:22pm On Apr 07, 2023
folmus:
Well done!!
Thanks chief!!
PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 5:47pm On Apr 07, 2023
Work progress on the roofing...

We thankGod for the productive day as we'll be closing for the day until tomorrow again..

Thanks y'all

PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 3:32pm On Apr 07, 2023
We've lined and locked the wall plate round the block wall..

Also, we've erected the king post which is 22ft in height

PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 12:21pm On Apr 07, 2023
Roofing woods have arrived site... We're set to start up with work as workers are on site already

PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 8:35am On Apr 07, 2023
Good morning my people, we're all set for roofing of the house as we'll be buying roofing woods today and then commence with work....

I'll bring in pictures updates much later...
PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 5:09pm On Apr 05, 2023
Meanwhile, we're also doing form work for the well as we'll cast tomorrow as well

PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 5:07pm On Apr 05, 2023
Form work and reinforcement ongoing on the second soak-away. We sure to casting this by tomorrow

PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 5:05pm On Apr 05, 2023
Also we're done with the beam casting for the first soak away....

Pictures below :

PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 5:01pm On Apr 05, 2023
Casting for the concrete fascia has been completed.

We'll be preparing for roofing next as we're all set to procure roofing woods for the house

PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 4:56pm On Apr 03, 2023
Also, plastering for the underground water storage tank has commenced...

Those familiar with Esan, certainly knows that there's no water underground so there's no way you can get borehole water..

So what is normally done is we dig a well of about 8ft-10ft round and 16ft-20ft depth.. This is for the sole purpose of storing water as water is been gotten from a neighboring town with a water tanker and offloaded into the well or water gathered from rain is been stored there

The well is to be plastered 3 consecutive times so it can be able to retain water

1st tapping is been done with around 8-11 bags of cement depending on the size of the well

2nd tapping is been done with around 10bags of cement. (At this point the well is able to retain water for construction purposes)

3rd And final tapping is done after the project is been completed though some persons do theirs at a go.

PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 4:53pm On Apr 03, 2023
We've started with block work for the soak-away..

We dug two soak-away which is to serve the entire building.

PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 7:29am On Apr 03, 2023
Morning my people, it's Monday again and we're back on site to commence with the day's work....
BusinessRe: Nigerian Tech Entreprenuer Favour Ori's Payday Raises $3m Led By Moniepoint Inc by AsomArchitectNG(m): 7:47pm On Apr 02, 2023
Nice
PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 4:56pm On Apr 01, 2023
More photos from site today...

We thankGod for work progress so-far

PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 4:55pm On Apr 01, 2023
Work progress on the concrete fascia(parapet) as the iron bender begins their trade today... Meanwhile formwork still ongoing...

PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 8:20am On Apr 01, 2023
Happy new month my people, we're on site again this morning to commence with the day's work.. I'll bring in pictures updates much later
PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 6:07pm On Mar 31, 2023
More photos:

PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 6:07pm On Mar 31, 2023
Photos of the work progress today...

PropertiesRe: Construction Of A 4bedroom Bungalow In Uromi Edo State by AsomArchitectNG(op): 6:02pm On Mar 31, 2023
Good evening my people, trust we're doing great.

Work intensifies as we've started with the concrete fascia(parapet) form work..

We took the top level for the house earlier this week after the lintel boarding/casting was done..

Also, we had to pause work for a while because of the shortage of cash and election but we're back now on site😎😎😎