Some more picture updates from this site. The building has been powered...
|
Final leveling commenced already from the back of the building. We are now doing a Total of 14 coaches excluding the decking beam which will make it 15 coaches before the decking slab. This is our standard. And it gives us a very nice headroom for POP finishing when the time comes.
|
STINEKPROJECTS1:No sir. Not at all I maintain a minum of 600 - 1200mm for colum lapping at all projects as you can see the one the attached picture is still this same project.
|
More picture views from here. Some of the form works have been removed from the Colums and Beams. Block work will commence ASAP for the final de king leveling...
|
More picture updates from the works here. Mainly from the furniture aspect. 1st Picture - 6th Bedroom Wardrobe and dresser area. 2nd Picture - Kitchenette At the Pent House 3rd Picture - Family Lounge TV area 4th Picture - Same as Picture 3.
|
View from the top. Lintel (Beam), and Colum (Pillars) concrete works... Our concrete works are pure and very neat...
|
More external view of the building... 3 Units of 6 Bedroom Luxury Duplex.
|
We continue the lintel and colum concrete works today.
|
We have more views from this design. We shall be posting them soon. |
We walk the talk. We don't just say it. We do it. |
More views from the furniture Works we are doing here. A look at the Master's bedroom area. The walk in closet and the TV Console area.
|
Work progress from site today. We have commenced the lintel and colum concrete works today.
|
Our work speaks volume. We walk the talk. We don't just say it. We do it. |
Some site pictures from this location. We are doing Finishing Works which include the following: - Electrical Fittings - Furniture Works - POP Final finishing and wall screeding - Paint Works
|
We are already at the Lintel level now... We are doing our routine - 10 Coaches.
|
More site updates on this site is coming tomorrow. Stay tuned as we hope to show you how far we have come especially with the furniture Works. |
We have started the block forming and layout. We hope to achieve lintel in maximum of 4 days all road.
|
German floor is completed. Find attached pictures for your perusal. We are starting the block laying immediately.
|
engrwilliam5000:Good day. No sir. We have gone past that stage already |
Back View of the building. We have the swimming pool and sitout areas with water fountains.
|
Our works speaks for itself. Keep following up with us. |
Our works speaks for itself. Keep following up with us. |
Our works speaks for itself. Keep following up with us. |
Semi Detached - 4 Bedroom Duplex on 630sqm. Features: Ground Floor - Main Living Room - Dinning - Visitor's Toilet - Kitchen and Store - Guest Room ensuite First Floor - 2 Bedrooms ensuite - Family Lounge with Terrace - Master's Bedroom with Terrace. External Features - Security House - Gen House - Car Parks for 2 Cars. All Drawings are available for the Design - Architectural Design - Structural Design - Mechanical Design - Electrical Design - Plumbing Design DM Us for your Building designs and construction services.
|
Some more photo updates from This site. Furniture Works are ongoing. Site pictures to follow. Stay tuned.
|
We are now ramming and compacting the foundation now after watering has been done. Picture updates to follow today. Stay tuned. |
More filing updates and the fence works.
|
michlins:Yeah, it is for very good reasons. It will be of good when it's time for landscaping and the type of staircase that we want to do for the entrance. |
kopell:Thanks alot sir. Well appreciated |
We have filled this project foundation with about 32 Trips of Filling Sand. |