Edshaf's Posts
Nairaland Forum › Edshaf's Profile › Edshaf's Posts
mrmikey101:Hard to remember the full details now, looking back, but it cost about 18m getting the building up (including the interlock) and about 10m on fittings and finishing |
I think the bottom line is that you can make more on uber than working in some companies. I ran a test on uber one time from 7am till 8pm and made an ok money. I spent 5k on fuel and didn't do much calling (which you won't need if you can follow the map very well). dckng16:
|
folmus:Oh... Yes, per bag. Thanks |
Plow:That's correct. It includes the cost of stacking as well. Do you think it is too expensive? I need feedbacks like this to ease future bargaining. |
folmus:I forgot to mention that I had to deal with LABSCA as well in which case I was fined. |
folmus:I couldn't say exactly but I had to pay about #1.7 million for 648 sq. mtr (that's about #2,500 per sq.mtrs plus other charges). The team of field agents that came took pictures and wrote reports of what was on ground. How that affected the charges, I don't know. I received a CofO for 99 years at the end anyways. |
Connoisseur:I understand your confusion but I didn't say I will gather the money for the whole building neither did I say in a month. Nigerian system takes time and rather than spending the little money I have now doing small section of work, I will be able to combine all that money with those yet to be earned (God willing) to do all the section of work, that I would have otherwise done if approval was not a problem, at the same time (quick progression). As far as my statement goes, completing the foundation once can be *quick progression" for sake of argument. Anyhow, I will take note for next time to avoid confusion. Thanks. |
folmus:I am not an authority in the process but I will share my understanding. Land under government acquisition that has been granted consent to regularize would normally have such consent number on the survey plan with a stamp of the land status. With your survey plan, you can obtain the land information (#10,000 for 1 plot) from the surveyor general's office. Only survey plan will red copy lodged in the Surveyor General's office can have the land information. With that and the completed application form (#5,000) obtained from Lagos State Ministry of Lands and Housing, you submit your application for land regularization to the directorate of land regularization. Anyways, in your case, all you need is to verify by conducting Land Information to start with. Be wary, estate or not! |
ArcFresky:No smallest room is 3000 x 3600 in dimension |
RobbStark:That's what I got it for, full volume. From Ikorodu to Boknor (near Okota). I am open to better or equal product & service at a reduced rate if available. What rate is a good rate sir? |
ArcFresky:We had the challenge of space. The plot is slightly skewed resulting in smaller buildable area. My archi suggested all ensuite in flats on the upper floors but after careful deliberations putting all factors into play, we decided to go with the plan as is. |
meezynetwork:Not that I know of. Unless the person was using well water |
Connoisseur:Yes. The normal trend in Lagos is to commence building before paper work (if at all). With Lagos drive for revenue generation, several penalties are now levied if you build without building approval (and get caught). Sadly, you cannot get building approval without a title on the land. Since the location is under government acquisition with consent to regularize, the Regularization process takes about 6 months to complete. But one can still get building plan approved with the letter of regularization, which takes about 3 month or less to be ready. |
Demolition in progress...
|
KingMicky3286:Lol |
Block molding completed (for now) with a total of 4000 6" blocks and 6600 9" done. Currently preparing the bungalow for demolition by removing the roof and roof structure. With CofO process on the way for the land, I was advised not to start any form of construction work pending government site visitation. Infact I now intend on waiting to get all necessary approvals before commencing work. The wait should grant me the opportunity to raise money for quick progression.
|
Final plan and one of the 3D perspective...
|
jiday4:Amen. Between 30 and 33 9" blocks per bag. I was advised to introduce plaster sand but I don't know exact reason. Maybe there is an added strength based on the fact that the finer plaster sand fills up the spaces left caused by the coarser sharp sand... I don't know. I will ask and get back. Regards, Dapo |
Block molding operation in progress...
|
samnaija:SIKJ Investment along Isheri Oshun Road after Jakande Estate, Oke-Afa. |
So far, with 1 trip of sharp (20 tonnes) sand + 1/2 trip (10 tonnes) of plaster sand and 50 bags of cement, we were able to produce 1600 9" blocks. 20 tonnes of sharp sand delivered to site: #65,000 10 tonnes of plaster sand: #30,000 50 bags of Cement @ #2600 per bag: #130,000 Molding Labor @ #900 per block: #45,000 Total Cost: #270,000 Effectively, each block cost #270,000 / 1600 = #168.75 to produce. |
snakebeat:Yes 42.5 |
snakebeat:-We targeted between 28 and 32 blocks per bag sir. -Dangote 3x -9 inches for now Thank you sir |
Block molding on going on site...
|
...
|
The picture of the project site While awaiting all documentation and approval, I will use the spare time to mold some blocks
|
Price of some building ,aterial from one of the local suppliers close to Isolo in Lagos: Dangote Cement: #2,600 Elephant Cement: #2,550 Iron Rod (16mm / 12mm) per tonne: #210,000 Iron Rod (10mm) per tonne: #215,000 Iron Rod (8mm): #170,000 |
iiiyyyk:I am no expert but it might be a too tight trying to slot a bq and a main with two flat into such space although I know of some places in Lagos where this has been done (but on 60 by 120ft). |
The land didn't come cheap but thank God that's done. The land acquired is a corner piece with an existing bachelor quarters, a hand-dug well and an existing foundation without German floor. The plan would however require levelling all existing structures - that would be the first thing first. |
spyder880:Oh my. I really envy you sir. All I keep thinking about is how much more I will have to spend on my project with prices going up like Elijah ascending to heaving in chariot of fire. I don't even want to know how much materials cost until I am ready .But then, how else can one be ready! |
spyder880:Oga Spyder880, I take it you would have reviewed the budget. For the stated budget, what stages of work would you be able to complete (suppose inflation rate hasn't affected the budget). Is plastering and electrical wiring included? |
Heymus:Thanks Heymus, Visitor's toilet, got it. As I must have indicated, I am not an architect, so the plan you see is just my own draft (made by me). I will consider posting the real one once I have it. |
.