Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 11:21pm On Jan 03, 2012 |
large concrete cap has finally been poured,
|
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 5:03pm On Dec 22, 2011 |
hbrednic: welldone, very nice job Thank you by brother, i appreciate all the words of encouragement. |
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 8:37pm On Dec 21, 2011 |
Installation of structural steel at 2 story area.
|
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 5:10pm On Dec 19, 2011 |
Reinfocing steel has been installed , nice work
|
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 4:31pm On Dec 16, 2011 |
Piles have been chipped down completely. It is now ready for reinforcing steel and formwork. Pictures to come ,
|
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 5:38pm On Dec 15, 2011 |
Another view
|
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 5:37pm On Dec 15, 2011 |
Installation of structural steel at the 2-story portion of the project has started. This process should last for two weeks pending weather conditions. The picture shows the steel members on the ground and the small crane used for installation. Some of the steel members are already standing on the slab.
|
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 3:27pm On Dec 13, 2011 |
We have uncovered all the piles that support one set of elevators. The next step is to chip the piles down to the bottom, then reinforcing steel will be installed for this huge cap.
|
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 4:56pm On Dec 12, 2011 |
Excavation to uncover piles in progress.
|
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 10:13pm On Dec 11, 2011 |
Formwork for shear walls have arrived on site. |
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 4:19pm On Dec 09, 2011 |
Excavation for the largest pile cap is in progress. So as you can see, the piles are drilled from grade, and then they are uncovered up to the depth of the pile cap. The most labor intensive part of this installation is chipping the piles down to the bottom of the cap. See pictures.
|
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 7:52pm On Dec 08, 2011 |
Slab for 2 story portion has been poured and covered with a curing blanket.
|
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 3:48pm On Dec 05, 2011 |
aseju: Oga, thank you o. Some observations - it seems like no below grade occupiable space, 1st floor will be slab on grade? Guessing that is what obtains in that neck of the wood because of water level. I may also want to ask about distances to adjacent buildings, some have openings now and is that going to remain as such along with yours in place? Some existing columns are protected in that foto and I am thinking separation (or none) with those buildings (existing)? Thank you for taking us through this. First i should point out that this slab is for a 2 story portion of the project that adjoins the 10 story building. It is a slab on grade, and the existing openings will remain. The two building will be separated by a rubber expansion joint to allow for potential movement. The 10 story portion is still at the foundation stage as shown in the attached pictures.
|
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 3:24pm On Dec 02, 2011 |
Slab ready to be poured.
|
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 3:48pm On Dec 01, 2011 |
Tower crane complete. 
|
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 2:57pm On Nov 30, 2011 |
@ Aventures, Wonderfiul questions, All partitions will be constructed with metal studs/ frame with gypsum board surfaces. This is typical for most commercial projects. For special areas where radio activity or infra red rays will be present, a solid high density concrete wall will be used for containment. These area include MRI, Linear accelerators etc. |
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 12:31am On Nov 30, 2011 |
aseju: kez007 along with other construction gurus, I salute o. May God bless you all for this and other like-threads. To me it does not matter where this project is. The process itself is a lot to learn from. Me sef I be laborer in Naija terms, however, I don register for the class even though I too dey skip class. My first question is, is this going to be a "steel and concrete" or "reinforced concrete" structure? Thank you. This will be a steel framed building with conrete slabs and concrete shear walls for elevators and stairwells. As you can see in the picture, excavation for the elevator pile cap has began,
|
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 12:16am On Nov 30, 2011 |
Behind bobo: What type of form work do u guys use?? For good quality construction in naija we use steel shuttering or doca wood panels(or any similar machine cut panels).though most peeps use common untreated panels as this is cheaper.but i love the quality of construction right from the foundation.that s the real difference between construction in naija and foreign countries.though i must add that there are a couple of construction companies doing well here too There are a variety of forms that are used here, but for large projects, steel and wood are the norm. Permanent metal forms are also used in cases where form removal may be unproductive. |
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 7:25am On Nov 22, 2011 |
Thanks for all the compliments, I was away last week, I will provide an update by tomorrow, |
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 5:48pm On Nov 13, 2011 |
Behind bobo: "Ground beam reinforcement in progress" u mean Nope, I actually mean "grade beam" installation. That is what it is called here, but I would still like to know the different construction terminologies that prevail in different parts of the world, I assume it it. Called "ground beam" in Naija. Interesting, thanks for the insight. |
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 6:27pm On Nov 11, 2011 |
Finally, aerial view of site. We notice that the pile caps have been covered completely with only the column pedestals exposed. , Enjoy the weekend!!
|
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 6:24pm On Nov 11, 2011 |
Grade beam reinforcing in progress,
|
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 6:23pm On Nov 11, 2011 |
Preparing for crane erection tomorrow.
|
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 6:22pm On Nov 11, 2011 |
Compacting backfill with a remote controlled vibrating compactor,
|
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 6:20pm On Nov 11, 2011 |
Backfilling around pile cap,
|
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 6:18pm On Nov 11, 2011 |
Wow, Another Friday, As of today, the pile caps have been backfilled and covered. Drilling is continuing and is scheduled to end next week, and the tower crane will be erected over the weekend. |
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 7:57pm On Nov 10, 2011 |
|
Properties › Re: Building Of A 5 Bedroom Executive Duplex In Enugu by kez007: 7:51pm On Nov 10, 2011 |
Fhemmmy: When i am ready, I am sure you would not leave your brother hanging, i am sure you would travel for my sake oh to my own site, cos you are my brother from the other mother At least my own is in Nnewi, so i'm covered  |
Properties › Re: Building Of A 5 Bedroom Executive Duplex In Enugu by kez007: 4:53pm On Nov 10, 2011 |
Nice job man!! spyder880: ^^^ I will ship them like those your neat cars, my workers are that precious, lolz. Make man catch 4 hours of sweet sleep joo. I thought you only worked in Enugu, Do you have a limit on how far you travel for work?,  |
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 4:45pm On Nov 10, 2011 |
Another day on the grind. Augered piles, and excavation of pile caps continue,
|
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 4:43pm On Nov 10, 2011 |
Excavated Grade beam, supported by drilled piers.
|
Properties › Re: Construction Of A 10 Story Office Building by kez007(op): 8:07pm On Nov 09, 2011 |
Aventures: I cld have asked this at the begining of this tread. Hw do you set out your column points. well i know in some Big construction like this GPS or total station is always used to locate the coordinates of the piers as specified in the drawing. Can you pls shed more light on this or rather give us your method. Thanks You are correct, the use of a total station is pretty much the norm. It's basically a stake out process where you set a benchmark off an existing structure, then set building corners and eventually the entire footprint. All the piers are located off the benchmark, and then a licensed surveyor is hired to determine variances. At the end of the pier drilling operation, the land surveyor produces and as built drawing indicating actual pile/pier locations. This report is submitted to the engineer for review and approval. In the case where the variance of a pier location exceeds the allowable variance in the specifications, the engineer may elect to add one more pier to the set to guarantee the structural integrity of the system. |