Properties › Re: Construction Of 4bedroom Duplex And 2unit 2bedroom Flat by Nora93(op): 8:38am On Mar 08, 2017 |
Ajewealth123: people no longer use plank for decking,we are in the new age,mbf as it is fondly called is what is in vogue now. It gives you smooth job and and can re-use it again and again thanks for the comment, but I had to made do with what is available. moreover cost is a driving factor, cos I still needed to sell off the woods after 21days of curing |
Properties › Re: Construction Of 4bedroom Duplex And 2unit 2bedroom Flat by Nora93(op): 8:35am On Mar 08, 2017*. Modified: 8:52am On Mar 08, 2017 |
victorazy: The quality of the work is poor. First, the foundation is shallow and I didn't see any hardcore. you are are making a mistake. the foundation was 3feet 6inches deep and nothing less than 6 couches of block was used. so I don't get you. like I said this is a dry land and the foundation footing was solid.
|
Properties › Re: Construction Of 4bedroom Duplex And 2unit 2bedroom Flat by Nora93(op): 9:31pm On Mar 07, 2017 |
Eledan: I have something like this in mind. Nora93, how far do you think a budget of 25M will go on this project with a raft foundation in Isheri North GRA ? 25m would go far, at least, you should be able to roof, plaster,fix electrical works, doors , windows, if possible tiling too |
Properties › Re: Construction Of 4bedroom Duplex And 2unit 2bedroom Flat by Nora93(op): 8:35pm On Mar 07, 2017 |
more pix from today's job
|
Properties › Re: Construction Of 4bedroom Duplex And 2unit 2bedroom Flat by Nora93(op): 7:37pm On Mar 07, 2017 |
|
Properties › Re: Construction Of 4bedroom Duplex And 2unit 2bedroom Flat by Nora93(op): 7:35pm On Mar 07, 2017 |
Badgers14: Congratulations on your new project.. More grease to your wallet..
Do you mind sharing how much you have spent up to this stage? foundation work- 2.1m German floor casting- 715k block work for ground floor including plumbing- 2.4m decking- 4m block work for first floor still ongoing but about 2.2m spent, and all materials needed bought already |
Properties › Re: Construction Of 4bedroom Duplex And 2unit 2bedroom Flat by Nora93(op): 10:15pm On Mar 06, 2017 |
this is the current stage we are right now, would keeping u updated as the work progresses. feel free to throw in questions. |
Properties › Re: Construction Of 4bedroom Duplex And 2unit 2bedroom Flat by Nora93(op): 10:00pm On Mar 06, 2017 |
decided to use 9inches block for the outer perimeter walls, and a 6inches block for inner walls partition. This is to reduce load on the deck and cost effectiveness.
|
Properties › Re: Construction Of 4bedroom Duplex And 2unit 2bedroom Flat by Nora93(op): 9:55pm On Mar 06, 2017 |
commenced setting of blocks for the first floor
|
Properties › Re: Construction Of 4bedroom Duplex And 2unit 2bedroom Flat by Nora93(op): 9:44pm On Mar 06, 2017 |
outcome of slab work
|
Properties › Re: Construction Of 4bedroom Duplex And 2unit 2bedroom Flat by Nora93(op): 9:39pm On Mar 06, 2017 |
casting job
|
Properties › Re: Construction Of 4bedroom Duplex And 2unit 2bedroom Flat by Nora93(op): 9:30pm On Mar 06, 2017 |
5tons of 12mm and 2tons 16mm used for deck reinforcements
|
Properties › Re: Construction Of 4bedroom Duplex And 2unit 2bedroom Flat by Nora93(op): 9:20pm On Mar 06, 2017 |
carpentry work completed ,awaiting iron Bender to commence work
|
Properties › Re: Construction Of 4bedroom Duplex And 2unit 2bedroom Flat by Nora93(op): 9:11pm On Mar 06, 2017 |
ready for deck work
|
Properties › Re: Construction Of 4bedroom Duplex And 2unit 2bedroom Flat by Nora93(op): 9:09pm On Mar 06, 2017 |
more pix
|
Properties › Re: Construction Of 4bedroom Duplex And 2unit 2bedroom Flat by Nora93(op): 8:33pm On Mar 06, 2017 |
setting of block work for the ground floor
|
Properties › Re: Construction Of 4bedroom Duplex And 2unit 2bedroom Flat by Nora93(op): 8:27pm On Mar 06, 2017 |
125bags of cement ,30ton granite, 2trip of 20tons sharp sand was used for the DPC concrete work |
Properties › Re: Construction Of 4bedroom Duplex And 2unit 2bedroom Flat by Nora93(op): 8:24pm On Mar 06, 2017 |
|
Properties › Re: Construction Of 4bedroom Duplex And 2unit 2bedroom Flat by Nora93(op): 8:20pm On Mar 06, 2017 |
great outcome of the DPC work
|
Properties › Re: Construction Of 4bedroom Duplex And 2unit 2bedroom Flat by Nora93(op): 7:54pm On Mar 06, 2017 |
men at work
|
Properties › Re: Construction Of 4bedroom Duplex And 2unit 2bedroom Flat by Nora93(op): 7:46pm On Mar 06, 2017 |
filling and compaction completed in readiness for German floor work
|
Properties › Re: Construction Of 4bedroom Duplex And 2unit 2bedroom Flat by Nora93(op): 7:34pm On Mar 06, 2017 |
digging of foundation trench
|
Properties › Construction Of 4bedroom Duplex And 2unit 2bedroom Flat by Nora93(op): 7:26pm On Mar 06, 2017*. Modified: 10:39pm On Mar 06, 2017 |
Location : Lagos mainland dry land good location. The duplex consist of; 4bedroom 2 living room ante-room laundry gym room kitchen/store room commencement date: January 2017
|