₦airaland Forum

Welcome, Guest: RegisterLoginWith GoogleTrendingRecentNew

Stats: 3,330,882 members, 8,447,513 topics. Date: Saturday, 18 July 2026 at 12:42 PM

Toggle theme

Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark - Politics (4) - Nairaland

Nairaland ForumNairaland GeneralPoliticsWhere Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark (12706 Views)

1 2 3 4 Reply (Go Down)

Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by franvincoop: 5:56pm On Apr 25
I agree with you but what I have not understood is where the 25000MW will come from.
I don't play with words
Can the generation companies produce 25000MW?
What is their production capacity in MW as of today?
Where will 25000MW come from? because it's not in the Siemens deal to generate even 1MW.

This is my question.
Upgrade, transport, distribute, transmit are not my problem, Siemens will handle that.
But how will the Siemens deal not be stalled or slow when there is not enough MW generated to be transported, distributed or transmitted?
Don't you think it's putting the cart before the horse?

I personally believe Siemens should be allowed to generate its own electricity, transmit and distribute alongside the upgradation of our transmission and distribution grid.
This Siemens deal, the way it is structured will have them relying on power generation companies.

I say this because this same Siemens was involved in the 16 billion USD OBJ National Integrated Power Project (NIPP) deals to build transmission lines.
Nigerians have very short memories.

Here are the list of companies involved in that project with nothing to show for it today including Siemens.

Pivot Engineering Ltd was awarded contracts in the sum of $78,625,736.54 for the construction of Owerri-Ahoada-Yenagoa 132 KVA DC lines and substations. It is to be noted that out of this, $73,023,521.36 has been paid to the contractor.
ABB {Nig] Ltd [SAE] received a contract in the sum of $21,489,644.79million and Nl, 489,271,079.60billion for the construction of second Benin-Onitsha 330 kva SC lines. So far, the contractors have been paid the sum of Nl, 675,225,734:40billion
Siemens Ltd also benefited from a contract of Euro l5, 032,410.65million (Euros) and N200, 000,000million to provide Onitsha 150 Mva, 330/132/33 kva, T/F and 330 KV base at Onitsha and Benin. Out of this contract sum, it has received a total payment of El2, 499,567.00million( Euros)and N49, 979,258.00million
Energovod Src was awarded a project of Alaogi-Calabar 330 kva DC lines in the sum of $42,382,351.30million and N900, 000,000 for which payments to the tune of $23,851,466.58million and N431, 056,721.00million have been made.
AREYVA T/D SPR-and -MBH power-for offshore works for construction of bays got £8,987,322.00million and N600, 000,000million. The foreign payments have been fully made while only N161, 704,254.50million on the Naka was paid.
Chrome Consortium was awarded contracts for the provision of Gombe-Yola-Jakngo 330kva SC lines at $74,872,154.04million. It has been paid $50,000,000.
News Engineering Ltd got a contract valued at $3,485,113.50million and N250, 000,000million for the construction of Jalingo 2×30/40 mva; 132/33kv sub-station. It received $2,670,679.36million and N100, 850,347.04million.
Allaogi-Umuahia 132 kva DC line was awarded to Pivot Engineering at $4,067,940.00million; it got $3,978,676.10million and N406, 528,365million.
Valenz Holdings [Nig] Ltd got the contract for Umuahia 2×30/40 mva, 132/33kv substation at $7,083,399.48 million and N489, 704,091.00million.It was not clear if the company had been paid.
Kec/News Engineering handled Gombe-Damatru-Maiduguri 330kv lines at $30, 172, 772million and N2.5 billion
JKN Limited did Ado -Ekiti 132/33kva sub-station and Akure 132kva Liangbe extension at N822 million. It received N521million.
Kano- Dutse 132 kva DC and Dutse-Azare 132 kv SC line were done by LCEP at $50, 294, 388million.
ABB did Dutse- Azare 2×30/40MVA, 132/33KV Sub -stations cost $12,500,000:00million and €1,771,582:83million. The company received $11,074,967:81million and €354,316:40million /*
The Egbin-Ikeja West/Benin Main 330kv DC line and sub-station was handled by Energo (Nig) Limited at $8,437,687 million and N141, 967,775:92million; it was paid $6,475,037:18 and Nl7, 488,890:06million .
NEPA-ACEB Power Interconnection Project (Counterpart Funding) was handled by SAE Power Lines and Areva (SIS) (Counterpart Funding on ADB Loan on senders) at Nl,194,500,000:00; Nl,043,800,000:00 was paid.
News Engineering Nig Limited got the contract for the construction of lx30MVA, 132/33W substation at Keffi at N441,534,004:50; N251,700,000:00 was paid to the contractor.
Continental Engineering Nig Limited was awarded Talata Mafara 2×30/40MVA, 132/33kv substation ( N453, 532, 829:20) . The company was paid N420, 323,334:57.
Amukpe (Sapele) lx30/40MVA, 132/33kv sub station was handled by News Engineering Limited at $1,194,482:34 and N219,920,252:71. The company received $1,014,276:14 and N78,303,339:54.
ABB Power Katempe got National Stadium 132kv DC line for N347,000,000:00; it was paid N 173,500,000:00.
Twenty-six companies carried out FY2000 substation reinforcement projects (N2,679,487,010:00) They received N2.3billion, representing 90% of the contract sum.
ABB Nigeria Limited handled rehabilitation of Delta TV Switchyard (€2,879,811:11 and N109,899,233:00); N36,822,340 was paid.
Nnewi 2x60MVA 132kv sub- station was awarded to Valenz Holdings Nigeria Ltd (€4,421,811:72 and N251, 833,400:00). It received N191, 734,122:52 .
CMC was awarded New 33kv substation at Omotosho ($30,325,386:00); $3,115,453:00 was paid.
Steers Int’l Ltd was awarded $1,395,353:83 and Nl 52,092,929:50 for the construction of New 330kv line at Ornotosho/Benin/ Ikeja West in which a down payment of $596,137:71 and N34,465,000:00 have been made to the contractor.
SEPCO got the $30,325,366:00 New 330kv substation at Papalanto. It was paid $8,915,453:00.
Kukwaba 2x60MYA, 132/33kv sub- station was awarded to NCEP at $5,252,932:61 and N272,237,433.25; 20% payment was made, which comes up to $1,050,586:52 and N54,447,486:65.
CCC Int’l Ltd is a company was awarded Onitsha-Nniwe-Ihiala 132kv DC line at $2, 631,003:58 and N 198,049,270:00.


My source is below.

https://thenationonlineng.net/revealed-who-got-what-in-16b-obasanjo-power-deals/

sonofthunder:
Siemens main duty is to upgrade our transmission and distribution capabilities..... And yes to that 25,000mw.

But problem is more than that.

Even though our transmission capacities are very poor compared to the already poor generation capacity, the distribution arm of electric power has been reported to be in the business of rejecting power from generation companies.
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by April4th(m): 6:12pm On Apr 25
SixSeven:
.
What is the generating capacity today?
I love this your question.
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by Vision101(m): 6:29pm On Apr 25
PHIPEX:
Once Obi goes to Egypt again to understudy their power revolution, APC will restart the Siemens deal propaganda.

Propaganda does not give light, does not build roads and will never win the insecurity war.
Na now Obi wake up? Na Egypt be Obi study center? Why didn't Obi go to Egypt and study them when he was governor of Anambra state? Tinubu brought the first IPP to Lagos when he was governor but OBJ frustrated it. Obi too dey act jare.
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by Josywhyte: 6:38pm On Apr 25
Audio deal..... God, I wish PO will win 2027 election so all this audio project/deals go stop. Then we'll start enjoying the dividends of democracy
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by DuttyChuks: 7:12pm On Apr 25
You people are making the work of yarimo, Madridguy, legendhero, Ngenekwensu very difficult 😂
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by Hassanmaye(m): 7:27pm On Apr 25
Nigeria is a scam country
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by ceejay80s(m): 7:42pm On Apr 25
we have to do something about all these rubbish happening in Nigeria
even Seun can't stop my voicing out,
it's getting out of hand, we no be iti nowww haba,
it's becoming unbearable
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by Choiceone1: 7:51pm On Apr 25
Flangelo12:
The $2.3 billion Siemens-Nigeria Power Deal (Presidential Power Initiative - PPI) is active and in its second phase as of early 2026, aimed at modernizing Nigeria's power grid and improving reliability.

Following a period of stagnation, the project was revived by President Tinubu's administration. It has successfully delivered and commissioned multiple mobile substations and transformers, yielding roughly 984 MW in additional capacity. The overall target is to reach 25,000 MW with projects ongoing to reduce grid outages.


Key status updates include:

Revival and Status: The partnership was stalled but was revived and accelerated, with, as of early 2026, the project is moving forward under President Tinubu, having seen increased momentum.

Infrastructure Progress: Siemens has delivered and installed 132/33 KV mobile substations and several 75/100 MVA and 60/66 MVA transformers nationwide.

Phase 2 Goals: The project is currently focused on upgrading seven lines and installing 10 transmission lines covering 554 km to boost capacity to 7,140 MW.
.
Key Focus: The deal seeks to mitigate grid failure, increase electricity access, and upgrade key transmission substations.

Timeline: The project timeline was extended, with some critical project components (substations) expected to be finalized around 2026.
U people keep lying is working and Tinubu go for Billions of solar in Also rock. What type of human being are u people?
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by Flangelo12: 7:52pm On Apr 25
Choiceone1:
U people keep lying is working and Tinubu go for Billions of solar in Also rock. What type of human being are u people?
So, I told Google what it should write?

grin
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by Choiceone1: 7:54pm On Apr 25
Flangelo12:
So, I told Google what it should write?

grin
Is it not human being like u that put it on Google? Our education has really gone bad
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by Flangelo12: 7:55pm On Apr 25
Choiceone1:
Is it not human being like u that put it on Google? Our education has really gone bad
Your education is really of concern.

Mine's allowed me to work around the world.
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by Choiceone1: 7:58pm On Apr 25
Flangelo12:
Your education is really of concern.

Mine's allowed me to work around the world.
Buala is always right so I can't blame u
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by Flangelo12: 7:59pm On Apr 25
Choiceone1:
Buala is always right so I can't blame u
Use punctuations for clarity.
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by Mrexcell(m): 8:29pm On Apr 25
markfem2:
Just like every unsuccessful/failed project, the Siemens deal has entered voicemail
Including all the billions invested in it?
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by sprints1: 8:53pm On Apr 25
Deal don turn to Omosimesime Ngozi simesime CDQ yeye
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by paxonel(m): 8:57pm On Apr 25
markfem2:
Just like every unsuccessful/failed project, the Siemens deal has entered voicemail
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by Oxygen1998: 9:19pm On Apr 25
As the OP said, power is no propaganda it's either in you sockets or not. All this AI gibberish is absolute nonsense
Flangelo12:
The $2.3 billion Siemens-Nigeria Power Deal (Presidential Power Initiative - PPI) is active and in its second phase as of early 2026, aimed at modernizing Nigeria's power grid and improving reliability.

Following a period of stagnation, the project was revived by President Tinubu's administration. It has successfully delivered and commissioned multiple mobile substations and transformers, yielding roughly 984 MW in additional capacity. The overall target is to reach 25,000 MW with projects ongoing to reduce grid outages.


Key status updates include:

Revival and Status: The partnership was stalled but was revived and accelerated, with, as of early 2026, the project is moving forward under President Tinubu, having seen increased momentum.

Infrastructure Progress: Siemens has delivered and installed 132/33 KV mobile substations and several 75/100 MVA and 60/66 MVA transformers nationwide.

Phase 2 Goals: The project is currently focused on upgrading seven lines and installing 10 transmission lines covering 554 km to boost capacity to 7,140 MW.
.
Key Focus: The deal seeks to mitigate grid failure, increase electricity access, and upgrade key transmission substations.

Timeline: The project timeline was extended, with some critical project components (substations) expected to be finalized around 2026.
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by Flangelo12: 9:20pm On Apr 25
Oxygen1998:
As the OP said, power is no propaganda it's either in you sockets or not. All this AI gibberish is absolute nonsense
So, Google is writing rubbish.
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by meobizy(m): 9:59pm On Apr 25
I have solved my electricity problem — solar. I have solved my water problem — a borehole. Since medical issues here are usually malaria and the common cold, that is under control. I can’t do much about security. For education, my children will either go the best of private schools or japa when the time comes.

I provide for myself. My government doesn’t see why I should enjoy the basics of life.
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by olusipimp(m): 10:36pm On Apr 25
Flangelo12:
The $2.3 billion Siemens-Nigeria Power Deal (Presidential Power Initiative - PPI) is active and in its second phase as of early 2026, aimed at modernizing Nigeria's power grid and improving reliability.

Following a period of stagnation, the project was revived by President Tinubu's administration. It has successfully delivered and commissioned multiple mobile substations and transformers, yielding roughly 984 MW in additional capacity. The overall target is to reach 25,000 MW with projects ongoing to reduce grid outages.


Key status updates include:

Revival and Status: The partnership was stalled but was revived and accelerated, with, as of early 2026, the project is moving forward under President Tinubu, having seen increased momentum.

Infrastructure Progress: Siemens has delivered and installed 132/33 KV mobile substations and several 75/100 MVA and 60/66 MVA transformers nationwide.

Phase 2 Goals: The project is currently focused on upgrading seven lines and installing 10 transmission lines covering 554 km to boost capacity to 7,140 MW.
.
Key Focus: The deal seeks to mitigate grid failure, increase electricity access, and upgrade key transmission substations.

Timeline: The project timeline was extended, with some critical project components (substations) expected to be finalized around 2026.
Thunder from benue fire ur thinking there…data boy
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by Flangelo12: 10:47pm On Apr 25
olusipimp:
Thunder from benue fire ur thinking there…data boy
Back to thy generation.

Wasn't the answer you wanted.

Why not cuss Mark Zuckerberg for allowing Google give that answer?
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by sonofthunder: 10:49pm On Apr 25
franvincoop:
I agree with you but what I have not understood is where the 25000MW will come from.
I don't play with words
Can the generation companies produce 25000MW?
What is their production capacity in MW as of today?
Where will 25000MW come from? because it's not in the Siemens deal to generate even 1MW.

This is my question.
Upgrade, transport, distribute, transmit are not my problem, Siemens will handle that.
But how will the Siemens deal not be stalled or slow when there is not enough MW generated to be transported, distributed or transmitted?
Don't you think it's putting the cart before the horse?

I personally believe Siemens should be allowed to generate its own electricity, transmit and distribute alongside the upgradation of our transmission and distribution grid.
This Siemens deal, the way it is structured will have them relying on power generation companies.

I say this because this same Siemens was involved in the 16 billion USD OBJ National Integrated Power Project (NIPP) deals to build transmission lines.
Nigerians have very short memories.

Here are the list of companies involved in that project with nothing to show for it today including Siemens.

Pivot Engineering Ltd was awarded contracts in the sum of $78,625,736.54 for the construction of Owerri-Ahoada-Yenagoa 132 KVA DC lines and substations. It is to be noted that out of this, $73,023,521.36 has been paid to the contractor.
ABB {Nig] Ltd [SAE] received a contract in the sum of $21,489,644.79million and Nl, 489,271,079.60billion for the construction of second Benin-Onitsha 330 kva SC lines. So far, the contractors have been paid the sum of Nl, 675,225,734:40billion
Siemens Ltd also benefited from a contract of Euro l5, 032,410.65million (Euros) and N200, 000,000million to provide Onitsha 150 Mva, 330/132/33 kva, T/F and 330 KV base at Onitsha and Benin. Out of this contract sum, it has received a total payment of El2, 499,567.00million( Euros)and N49, 979,258.00million
Energovod Src was awarded a project of Alaogi-Calabar 330 kva DC lines in the sum of $42,382,351.30million and N900, 000,000 for which payments to the tune of $23,851,466.58million and N431, 056,721.00million have been made.
AREYVA T/D SPR-and -MBH power-for offshore works for construction of bays got £8,987,322.00million and N600, 000,000million. The foreign payments have been fully made while only N161, 704,254.50million on the Naka was paid.
Chrome Consortium was awarded contracts for the provision of Gombe-Yola-Jakngo 330kva SC lines at $74,872,154.04million. It has been paid $50,000,000.
News Engineering Ltd got a contract valued at $3,485,113.50million and N250, 000,000million for the construction of Jalingo 2×30/40 mva; 132/33kv sub-station. It received $2,670,679.36million and N100, 850,347.04million.
Allaogi-Umuahia 132 kva DC line was awarded to Pivot Engineering at $4,067,940.00million; it got $3,978,676.10million and N406, 528,365million.
Valenz Holdings [Nig] Ltd got the contract for Umuahia 2×30/40 mva, 132/33kv substation at $7,083,399.48 million and N489, 704,091.00million.It was not clear if the company had been paid.
Kec/News Engineering handled Gombe-Damatru-Maiduguri 330kv lines at $30, 172, 772million and N2.5 billion
JKN Limited did Ado -Ekiti 132/33kva sub-station and Akure 132kva Liangbe extension at N822 million. It received N521million.
Kano- Dutse 132 kva DC and Dutse-Azare 132 kv SC line were done by LCEP at $50, 294, 388million.
ABB did Dutse- Azare 2×30/40MVA, 132/33KV Sub -stations cost $12,500,000:00million and €1,771,582:83million. The company received $11,074,967:81million and €354,316:40million /*
The Egbin-Ikeja West/Benin Main 330kv DC line and sub-station was handled by Energo (Nig) Limited at $8,437,687 million and N141, 967,775:92million; it was paid $6,475,037:18 and Nl7, 488,890:06million .
NEPA-ACEB Power Interconnection Project (Counterpart Funding) was handled by SAE Power Lines and Areva (SIS) (Counterpart Funding on ADB Loan on senders) at Nl,194,500,000:00; Nl,043,800,000:00 was paid.
News Engineering Nig Limited got the contract for the construction of lx30MVA, 132/33W substation at Keffi at N441,534,004:50; N251,700,000:00 was paid to the contractor.
Continental Engineering Nig Limited was awarded Talata Mafara 2×30/40MVA, 132/33kv substation ( N453, 532, 829:20) . The company was paid N420, 323,334:57.
Amukpe (Sapele) lx30/40MVA, 132/33kv sub station was handled by News Engineering Limited at $1,194,482:34 and N219,920,252:71. The company received $1,014,276:14 and N78,303,339:54.
ABB Power Katempe got National Stadium 132kv DC line for N347,000,000:00; it was paid N 173,500,000:00.
Twenty-six companies carried out FY2000 substation reinforcement projects (N2,679,487,010:00) They received N2.3billion, representing 90% of the contract sum.
ABB Nigeria Limited handled rehabilitation of Delta TV Switchyard (€2,879,811:11 and N109,899,233:00); N36,822,340 was paid.
Nnewi 2x60MVA 132kv sub- station was awarded to Valenz Holdings Nigeria Ltd (€4,421,811:72 and N251, 833,400:00). It received N191, 734,122:52 .
CMC was awarded New 33kv substation at Omotosho ($30,325,386:00); $3,115,453:00 was paid.
Steers Int’l Ltd was awarded $1,395,353:83 and Nl 52,092,929:50 for the construction of New 330kv line at Ornotosho/Benin/ Ikeja West in which a down payment of $596,137:71 and N34,465,000:00 have been made to the contractor.
SEPCO got the $30,325,366:00 New 330kv substation at Papalanto. It was paid $8,915,453:00.
Kukwaba 2x60MYA, 132/33kv sub- station was awarded to NCEP at $5,252,932:61 and N272,237,433.25; 20% payment was made, which comes up to $1,050,586:52 and N54,447,486:65.
CCC Int’l Ltd is a company was awarded Onitsha-Nniwe-Ihiala 132kv DC line at $2, 631,003:58 and N 198,049,270:00.


My source is below.

https://thenationonlineng.net/revealed-who-got-what-in-16b-obasanjo-power-deals/
The things you said are not the problem are equally as big a problem as generation if not worse. What is the use of wasting resources to produce electricity that just cannot be consumed?
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by Whois(m): 2:02am On Apr 26
SaiOba:
Una go cry tire
u don't know holding government accountable will favour you as well?
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by Druss(m): 7:02am On Apr 26
keemsleek:
How much mw did pdp deliver in 16yrs? And for your lies that Siemens built 25MW while it was actually 14,400mw in 2yrs 5months. Here's the break down.

The difference between Egypt’s Siemens project and Nigeria’s own deal comes down to speed of execution, structure, and consistency.
🇪🇬 Egypt (Fast – about 2.5 years)
Handled by Siemens
Why it moved quickly:
Central control: Decisions came directly from Abdel Fattah el-Sisi and were executed without delays
Full funding ready upfront: Egypt secured financing immediately (billions of dollars arranged quickly)
Single focus: Build new power plants from scratch (3 massive stations at once)
Minimal bureaucracy: Fewer approvals, less political back-and-forth
Strong transmission planning: They upgraded generation and grid together
👉 Result: 14,400 MW delivered in ~2.5 years
🇳🇬 Nigeria (Slower – ongoing since 2019)
Known as the Nigeria Electrification Roadmap
Why it’s slower:
Complex problem: Not just building new plants — Nigeria is fixing:
Transmission
Distribution
Metering
Funding delays: Loans (from Germany and others) took time to finalize
Multiple stakeholders: Federal Govt, DISCOs, TCN, regulators — all must align
Policy & leadership changes: Government transitions slow momentum
Existing infrastructure issues: Old, weak grid needs upgrades before adding big power
Phases in Nigeria
Phase 1: Improve existing grid to reach ~7,000 MW (ongoing)
Phase 2: Expand to ~11,000 MW
Phase 3: Target ~25,000 MW long term
👉 This is planned over many years (possibly 8–10+ years total)
The Real Difference (Simple)
Egypt: “Build big, fast, from scratch”
Nigeria: “Fix a broken system while upgrading it”
Straight truth
Egypt’s project was easier to execute because it was a clear, single mission with full money and control.
Nigeria’s is harder because it’s rebuilding an entire power ecosystem, not just adding capacity.

Pdp did not add one single mw to the grid for 16yrs. Arlt least Apc added 700mw... all of them have messed up but apc did little. Olu Agunloye of pdp stole almost 10 billion dollars for nepa and obj denied signing any paper this same pple are all in ADC una new campion. We need new Brains like bianca ojukwu, soludo, otti, as vice president
PDP didn't add what? Where my Afam people at? Could you educate this person!!
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by SmartPolician: 8:10am On Apr 26
Flangelo12:
You tried.

Most of them don't really care to know nor ask with good intentions.

Watch how they'll start disputing what you've posted.
That rubbish is from an AI tool
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by Flangelo12: 8:15am On Apr 26
SmartPolician:
That rubbish is from an AI tool
Yeah, we should just do guess work.
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by kcbaba007: 2:59pm On Apr 26
OredoPikin:
Back in 2022/23, during the campaign run up to the 2023 elections, Peter Obi traveled to Egypt to study how they solved their power crisis, a fix so successful they now run a surplus. He wanted to see if that model could work for Nigeria.

What did he get for it? Attacks.
APC supporters mocked him, insisting the Buhari led APC government had already signed a deal with the same Siemens that handled Egypt’s turnaround. Photos of transformers circulated. “It’s done,” they said. “Obi is late.”

Fast forward to 2026. Four years have passed. Another election cycle is here. APC is still in power.

for context, the deal was signed in 2018 to add 25,000MW to our electricity generation. It's been 8yrs since that deal was signed.

So, where is the Siemens deal?
Where is the electricity?

Where are the transformers we were shown back then? Where is the megawatt increase Nigerians were promised under the Presidential Power Initiative with Siemens?

If the deal was real and executed, why are we still battling the same grid collapses and poor supply? If it failed, why the silence?

We can’t pretend this is not a question worth asking. Before we start debating 2027, Nigerians deserve an account of the last promises made.

To the APC supporters and defenders who told us the Siemens deal was already "settled" in 2022: where is it?

Power is not propaganda. It’s either in your sockets or it is not. And right now, the only thing Nigerians can see clearly is darkness.

Where is the Siemens deal?
Where is the electricity?
All we are getting is the falling and collapsing of the grid like bulabulu
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by brightleave(m): 4:05pm On Apr 26
It is a vitual deal grin
Re: Where Is The Siemens Deal? 4 Years Later, Nigerians Are Still In The Dark by Kingbuhari(m): 4:14pm On Apr 26
Putinofrussia:
Not all Aba is getting 24/7 power supply.
It is just like in Lagos where some specific areas and specialized, high-end, or commercial locations are receiving between 20 and 24 hours of power supply daily, often classified under the "Band A" tariff category.
These areas are typically served by dedicated feeders or independent power projects (IPPs) and involve higher electricity tariffs.
Some of these areas include...
Ikeja Business Unit: Areas include parts of Ojodu (River Valley), Opebi (Awuse, General Hospital, Oba Akinjobi), and Secretariat Estate (Agidingbi).
Akowonjo Business Unit: Locations include parts of Egbeda and Anifowoshe (Siyanbola, Awolowo).
Island Business Unit: High-consumption areas such as 1004 Estate, 2nd Avenue, Corporation Drive, Federal Palace Express, Federal Secretariat, Foreshore, ICON, Idowu Martins, Kingsway, Parkview, and parts of Victoria Garden City (VGC).
Other Areas: Parts of Abule-Egba (Ijaiye), Oshodi (Ajao Estate, Canal), and Shomolu (Ilupeju, Magodo, Maryland, Ogudu) also feature locations with high-hour supply.
Commercial/Market Zones: Select commercial hubs like the Sura Shopping Complex and Iponri Market have independent power solutions providing 24/7 electricity.
this is why they want Alex otti desperately.. maybe to use his achievement boast their CV 🤣 apc are economic bandits
1 2 3 4 Reply

National Grid Collapse: What Has Happened To All The SIEMENS Power DealsThe Truth About The Siemens DealGoodluck Jonathan Reconnects With Former UNIPORT School Mates 40 Years Later234

We’ll Regain Power In 2019 – PDPPDP Leaders Visit Fani-kayode, OthersDangote Refinery Begins Polypropylene Production In October, Saving $268m Forex