Welcome, Guest: Register On Nairaland / LOGIN! / Trending / Recent / New
Stats: 3,151,157 members, 7,811,320 topics. Date: Sunday, 28 April 2024 at 09:17 AM

Construction Of Six Bedroom Duplex At Enugu - Properties (2) - Nairaland

Nairaland Forum / Nairaland / General / Properties / Construction Of Six Bedroom Duplex At Enugu (38032 Views)

Semi Detached Six Bedroom Duplex At Bodija Ibadan For Rent / Construction Of A 4-bedroom Bungalow For My Mom...all Bedroom Ensuite. / Construction Of My 3bedroom Flat All Ensuite (2) (3) (4)

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) ... (11) (Reply) (Go Down)

Re: Construction Of Six Bedroom Duplex At Enugu by abdulwastecx(m): 5:37pm On Apr 12, 2016
More pictures

Re: Construction Of Six Bedroom Duplex At Enugu by abdulwastecx(m): 5:47pm On Apr 12, 2016
Day four..
Casting of the foundation footings
These footings have two type
1. Strip footings
2. Isolated pad footings

The strip footings are 675mm (3 times the width of foundation block wall) and 225mm thick.

The total perimeter of the foundation is about 200m removing the column bases we leave us with about 145m

Volume of strip footings = 145x0.675x 0.225 = 22cubic meters.
Using a mix ratio of 1:2:4 by weight, we have about 6.25bags of cement per cubic meters = 6.25x22 =137bags (giving an allowance of 20% for wastage, occasionally wider strip footings) = 1.25x137 = 165bags.

For the column base : we have about 36 x1.1x1.1x0.45=
20cubic meters + 2.2x1.1x0.45x2 = 2cubic meters
We have a total of 22cubic meters = 165bags of cement.

Total calculated value required = 330bags of cement

1 Like 1 Share

Re: Construction Of Six Bedroom Duplex At Enugu by abdulwastecx(m): 5:54pm On Apr 12, 2016
more casting image

Re: Construction Of Six Bedroom Duplex At Enugu by abdulwastecx(m): 6:00pm On Apr 12, 2016
completion of casting work...
summary of materials used so far (note the client have a relative on ground that supply all the materials we need)
as a matter of fact we have many external supervisor coming in to check our job.

cement = 235 bags so far ( blinding, isolated footings and combined pad footings)
gravel = we cant really tell now
sand = will come back with this later.
Re: Construction Of Six Bedroom Duplex At Enugu by abdulwastecx(m): 6:05pm On Apr 12, 2016
laying of foundation column : according to my estimate, we will need about >=2500blocks for this foundation and since one bag of cement will lay between 40 to 50 blocks, we have = 2500/40 or 50 = 63 bags or 50 bags

Re: Construction Of Six Bedroom Duplex At Enugu by abdulwastecx(m): 6:08pm On Apr 12, 2016
more block work

Re: Construction Of Six Bedroom Duplex At Enugu by abdulwastecx(m): 6:10pm On Apr 12, 2016
more block works

Re: Construction Of Six Bedroom Duplex At Enugu by abdulwastecx(m): 6:13pm On Apr 12, 2016
More updates from the block work

Re: Construction Of Six Bedroom Duplex At Enugu by abdulwastecx(m): 6:17pm On Apr 12, 2016
More from block work

Re: Construction Of Six Bedroom Duplex At Enugu by abdulwastecx(m): 6:22pm On Apr 12, 2016
We are almost through with the block work, there are extension that we have to make. Some group of my workers are already warming up for the sand filling and compaction of the foundation.

The client is lucky that we have sand fill already on site from the debris of the demolished house and the existing dpc of the previous house.
Filling operation should take two days while compaction will take one day

Re: Construction Of Six Bedroom Duplex At Enugu by spyder880(m): 7:04pm On Apr 12, 2016
I love this, very good work as usual. Keep doing it good as we are enjoying the project. Welcome to Enugu my man. grin

2 Likes

Re: Construction Of Six Bedroom Duplex At Enugu by abdulwastecx(m): 7:30pm On Apr 12, 2016
spyder880:
I love this, very good work as usual. Keep doing it good as we are enjoying the project. Welcome to Enugu my man. grin

Thank you sir.. It is a privilege sir
Re: Construction Of Six Bedroom Duplex At Enugu by ObiOkpor(m): 9:53pm On Apr 12, 2016
abdulwastecx:
from this building line the other two corners of the building are set out using " 3 4 5 " right angle triangle method . in this case, we use multiple of this triangle (12, 16, 25).
these two other points were located and the profile was nailed after offset from these original four points
Bros,congrats. Can you give me the roofing aspect of the house? Am based in your sister state.
See my signature....
Thank you..
Re: Construction Of Six Bedroom Duplex At Enugu by smiley001(m): 11:29pm On Apr 12, 2016
Congrats and Weldone bro.

2 Likes

Re: Construction Of Six Bedroom Duplex At Enugu by Onuokwu: 5:23pm On Apr 14, 2016
We still dey follow and looking for updates o.
Re: Construction Of Six Bedroom Duplex At Enugu by abdulwastecx(m): 6:45pm On Apr 14, 2016
Rounding up foundation block work and filling

Re: Construction Of Six Bedroom Duplex At Enugu by abdulwastecx(m): 6:51pm On Apr 14, 2016
More updates from our ongoing job

Re: Construction Of Six Bedroom Duplex At Enugu by Nobody: 9:04pm On Apr 14, 2016
abdulwastecx:
check out this our combine footing....at harney project will follow the structure design to the later because i can hardly sleep if work are not done properly

This is over reinforced,
No need for top bars when you not going that far into the ground.
Re: Construction Of Six Bedroom Duplex At Enugu by abdulwastecx(m): 9:08pm On Apr 14, 2016
oapeleo:


This is over reinforced,
No need for top bars when you not going that far into the ground.

Since you are not the design engineer. .. . I don't think it is over reinforced.

Combine footings behave like a continuous beam and during the analysis you have both hogging and sagging moment which translates into a top reinforcement and bottom reinforcement

2 Likes 1 Share

Re: Construction Of Six Bedroom Duplex At Enugu by abdulwastecx(m): 9:12pm On Apr 14, 2016
oapeleo:


This is over reinforced,
No need for top bars when you not going that far into the ground.

Going far into ground depend on the location of strata where you have the required Geotechnical properties used for the design (bearing capacity). It has nothing to do with how you reinforced your footings
Re: Construction Of Six Bedroom Duplex At Enugu by abdulwastecx(m): 9:16pm On Apr 14, 2016
More filling and compaction work going on

1 Like

Re: Construction Of Six Bedroom Duplex At Enugu by abdulwastecx(m): 9:21pm On Apr 14, 2016
We mobilized to site last week Monday, making it 10days now.

Preparing for our waste plumbing pipe.
Re: Construction Of Six Bedroom Duplex At Enugu by abdulwastecx(m): 9:23pm On Apr 14, 2016
The client has decided that he want surface piping because of Maintenance, he is of the option that conduit waste pose lot of repair challenges
Re: Construction Of Six Bedroom Duplex At Enugu by kopell: 12:45am On Apr 15, 2016
abdulwastecx:
We mobilized to site last week Monday, making it 10days now.

Preparing for our waste plumbing pipe.
Great job, who says this young guys are not talented?

1 Like

Re: Construction Of Six Bedroom Duplex At Enugu by twinskenny(m): 7:31am On Apr 15, 2016
abdulwastecx:
The client has decided that he want surface piping because of Maintenance, he is of the option that conduit waste pose lot of repair challenges

oga mi well done oo and i was in Enugu last week oo would have love to come and say hello...

good job you are doing sir. keep it up
Re: Construction Of Six Bedroom Duplex At Enugu by abdulwastecx(m): 8:27am On Apr 15, 2016
twinskenny:


oga mi well done oo and i was in Enugu last week oo would have love to come and say hello...

good job you are doing sir. keep it up

Thanks Thanks boss
Re: Construction Of Six Bedroom Duplex At Enugu by podosci(m): 10:19am On Apr 15, 2016
We have dug the trench for the staircase starter bar,soon we would place the starter bars for the staircase after blinding of 50mm
while the capenter is busy placing the formwork the the dpc with a brace of 3f center to center ... Abdulwastecx will update you all with pictures

1 Like

Re: Construction Of Six Bedroom Duplex At Enugu by Onuokwu: 5:19pm On Apr 15, 2016
podosci:
We have dug the trench for the staircase starter bar,soon we would place the starter bars for the staircase after blinding of 50mm
while the capenter is busy placing the formwork the the dpc with a brace of 3f center to center ... Abdulwastecx will update you all with pictures

Okay na...we dey wait for the pictures.

Apart from the aesthetics, is there any advantage of conduit piping over surface piping for plumbing?
Re: Construction Of Six Bedroom Duplex At Enugu by Nobody: 7:25pm On Apr 15, 2016
Onuokwu:


Okay na...we dey wait for the pictures.

Apart from the aesthetics, is there any advantage of conduit piping over surface piping for plumbing?

Servicing.
Wires can easily be pulled out and replaced when the need arises.
Re: Construction Of Six Bedroom Duplex At Enugu by Miscellaneous(m): 8:02pm On Apr 15, 2016
@op Are u the one that made the structural & architectural drawings ?
Re: Construction Of Six Bedroom Duplex At Enugu by abdulwastecx(m): 8:20pm On Apr 15, 2016
[quote author=Miscellaneous post=44735790]@op Are u the one that made the structural & architectural drawings ?[/quote

For this job no. The architectural and structural drawings were done by a different consultancy film.

1 Like

Re: Construction Of Six Bedroom Duplex At Enugu by abdulwastecx(m): 8:21pm On Apr 15, 2016
Onuokwu:


Okay na...we dey wait for the pictures.

Apart from the aesthetics, is there any advantage of conduit piping over surface piping for plumbing?

Cost is another advantage, it cost more to conseal surface plumbing pipes because of extra money for vent.

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) ... (11) (Reply)

My Portharcourt Eneka 6 Flats Project. / New Construction Of A Block Of 6 Flats Of 2 Bedrooms In Enugu East. / Supreme Court Upholds Right Of Female Child To Inherit Properties In Igboland

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 29
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.