| Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by 989900E(op): 11:01pm On Jul 13, 2016 |
The Shiroro Hydro Power Station has expended about N2.4 billion for the repairs of its four turbine generators to bring the plant to full capacity of 600 megawatts.http://punchng.com/shiroro-power-plant-operate-full-capacity-repairs/
|
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by LRNZH(m): 11:38pm On Jul 13, 2016*. Modified: 1:25am On Jul 14, 2016 |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by slimfit1(m): 11:42pm On Jul 13, 2016 |
Solar time na him we dey so. |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by Nobody: 11:44pm On Jul 13, 2016 |
I hear |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by Femich18(m): 12:24am On Jul 14, 2016 |
Alryt we don hear...I hope the MW generated will rise to about 10000 if possible second quarter of next year. |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by Israel5(m): 1:02am On Jul 14, 2016 |
Thank God. God is working on Nigeria. |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by KINGwax007(m): 1:13am On Jul 14, 2016 |
Don't worry oga, we knw who dey cause the power failure and we urge them to continue. |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by EazyMoh(m): 2:16am On Jul 14, 2016 |
I think we shall consider either upgrading kainji if possible, or try build a bigger hydro plant similar to that China own. Since these people wouldn't allow us use the gas which is the cheapest and simplest form of power generation. |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by adconline(m): 2:50am On Jul 14, 2016 |
Key word : TO OPERATE |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by TPAND(f): 6:13am On Jul 14, 2016 |
Companies are just scamming the gullibility out of Nigerian ministers. It's a know fact in the world, no amount of turn around maintenance can bring back. Machine to a 100% efficiency. Anyway I hope someone communicates this to the SAN Minisiter of Darkness. He should stop going to the press to impress that he is working, we see no work |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by AntiWailer: 6:15am On Jul 14, 2016*. Modified: 6:45am On Jul 14, 2016 |
TPAND:You are 'The pained' right? I sense it from ur submission. ![]() |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by sarrki(m): 6:19am On Jul 14, 2016 |
Pls start work on mambilla hydro 6000MW and live our oyel money people Nigeria is moving forward. |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by sarrki(m): 6:21am On Jul 14, 2016 |
TPAND:Chai chai wailers association regional manager spotted |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by ConqueredWest: 6:32am On Jul 14, 2016 |
EazyMoh:You mean the 5% |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by Almajiri1: 6:33am On Jul 14, 2016 |
TPAND:You can imagine the once celebrated turn around maintenance of kaduna refinery with billions gone yet no show. |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by captleonerd(m): 6:42am On Jul 14, 2016 |
TPAND:how will you see when you keep encouraging NDA to blow up more pipelines. |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by 989900E(op): 7:25am On Jul 14, 2016 |
sarrki:Mambilla will give us roughly 3000 MW, but that is a big boost too -- it takes us to 9-10,000 MW! We need to review our energy and power laws, and transmission issues though. |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by fyneguy: 7:37am On Jul 14, 2016 |
EazyMoh:Hydro is the cheapest |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by Beremx(f): 7:51am On Jul 14, 2016 |
Highly applauding. I am impressed! |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by plux4: 8:35am On Jul 14, 2016 |
“It was then discovered that there was a large piece of
concrete measuring about 6 meters by 2 meters in the scroll
case of the unit,” Sabotage... |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by ginajet(f): 8:37am On Jul 14, 2016 |
Really? Abeg what of Kanji Dam? |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by acunon: 8:38am On Jul 14, 2016 |
They will keep on syphoning money for repairs of a damn dam but no light even if it's jst 20 mins a day. But let me ask,if all these dams produce electricity where do they supply them to? Moon? |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by OnWebTech: 8:40am On Jul 14, 2016*. Modified: 8:51am On Jul 15, 2016 |
“It is a project that has prospect of employment for skilled young Nigerians.” Need logo design? |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by M17CXi: 8:40am On Jul 14, 2016 |
Ooh pls shut up!!!!!!!!!!
Enough fooling |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by justicejay(m): 8:40am On Jul 14, 2016 |
All dis na paper work |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by muller101(m): 8:41am On Jul 14, 2016 |
sarrki:its leave not live. |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by Proffdada: 8:41am On Jul 14, 2016*. Modified: 8:57am On Jul 14, 2016 |
![]()
|
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by meltiplexer: 8:41am On Jul 14, 2016 |
Beremx:Don't be impressed yet,this is just mouth talk until we see it working. Naijabetman say so |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by EvilSeeed: 8:43am On Jul 14, 2016 |
Finally!! Shiroro will be optimal again after god knows how many years. I wonder when we will hear same new about Kainji and our refineries nationwide. |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by raywan: 8:45am On Jul 14, 2016 |
Nice one.God bless nigeria |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by dafuturis(m): 8:45am On Jul 14, 2016 |
Impressive |
| Re: Shiroro Power Plant To Operate At Full Capacity After N2.4bn Repairs by BE811APP: 8:45am On Jul 14, 2016 |
2.4bn |
Only 8 Agencies Allowed To Operate At Nigerian Ports - NPA • Ajaokuta Steel To Operate At Full Capacity By 2017 – FG • Security Patrol Men At The Shiroro Dam In Niger State (photo) • 2 • 3 • 4
Nigeria’s Economy Worse In 90 Days Of APC – PDP • "I Will Not Leave APC For Gold-Diggers" – Okorocha • Atiku Can Be President Without Going To The United States – Tony Momoh