BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla - Properties (2) - Nairaland

Nairaland Forum / Nairaland / General / Properties / BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla (8990 Views)

Bitsworks Project Memoirs: Construction Of A Church Auditorium Surulere Lagos / BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd / Bitsworks Project Memoirs: Construction Of 4 Units Of 2 Bedrooms Flat Ikorodu (2) (3) (4)

(1) (2) (3) (4) (5) (Reply) (Go Down)

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 9:21pm On Jun 25, 2018
Casting of the substructure columns ongoing.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 5:06am On Jun 26, 2018
Plumbing work done at the substructure level before backfilling starts.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 1:53pm On Jun 26, 2018
Substructure work concluded, getting set for the backfilling and damp proof membrane.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 6:23am On Jun 27, 2018
Aerial pictures of the substructure work. Shot by BITSWORKS-1.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 1:11pm On Jun 27, 2018
Backfilling of foundation trenches ongoing.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 10:46pm On Jun 27, 2018
Backfilling still ongoing, 60 tons of filling dumped so far.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by seunben(m): 5:40pm On Jun 28, 2018
BITSWORKS:
Backfilling still ongoing, 60 tons of filling dumped so far.
Good job as usual. Please what's the size of the building as I am waiting patiently to know how much tons was used to fill the building. it is a learning process for me.
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 8:38pm On Jun 28, 2018
seunben:

Good job as usual. Please what's the size of the building as I am waiting patiently to know how much tons was used to fill the building. it is a learning process for me.

Thanks for the good words.

The size of the building is L-23.759m, B-9.576m. As of today 100 tons (5 trips of 20tons truck) of filling has been dumped. Its looking like we will still do between another 40-80 tons but not more than that. Please take into cognizance the number of coaches laid. We have 4 coaches in the front unit and 5 coaches at the rear unit.

You can also calculate the volume (cu3) of the trenches and convert to tonnages. Depending on the type of soil, the multiplying factor is different if its dry sand or moist sand.
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 8:46pm On Jun 28, 2018
Backfilling still ongoing, 100 tons dumped so far, 80 tons have been backfilled already. Today's dumping delivery was late in the day and we pushed the backfilling till tomorrow.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 4:20am On Jun 30, 2018
Backfilling still ongoing at a steady pace, 120 tons dumped and we are still a long way from completion.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 4:27am On Jun 30, 2018
After 120 tons of backfilling, we still have this much to do. By my rough calculation, we are looking at another 80 tons, hopefully no more than that.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 8:00am On Jul 02, 2018
Backfilling on hold temporarily due to the incessant rain and bad road. The dump trucks will not be able to access the filling sand location.
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by seunben(m): 7:50pm On Jul 02, 2018
BITSWORKS:
Backfilling on hold temporarily due to the incessant rain and bad road. The dump trucks will not be able to access the filling sand location.
sorry for the delay bro. How much are you paying for labour for each trip to do the backfilling.
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 5:16pm On Jul 03, 2018
seunben:

sorry for the delay bro. How much are you paying for labour for each trip to do the backfilling.

For each 20 tons trip its N6,000 but I was able to negotiate to N5,000. For 10 tons its N3,000. They will rent wheel barrows and shovels themselves.
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 11:51am On Jul 04, 2018
Backfilling still on hold due to bad road conditions to the Laterite site. We have lost 2 working days and today possibly will make it 3 days but am hoping for the best.
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 10:36am On Jul 06, 2018
We received a dump of 20 tons backfilling yesterday and another 20 tons this morning making a total of 160 tons dumped so far. Let's see how far we can go with this and how much backfilling will be needed to complete the task.
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by seunben(m): 9:12pm On Jul 06, 2018
carry on bro. patiently waiting for tomorrow's pics.
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 8:31pm On Jul 07, 2018
Backfilling still ongoing, 180 tons dumped so far. Half of the span of the building almost done, at the stair section where we have a drop down level.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 1:38pm On Jul 09, 2018
Half done, half to go. Compacting of the backfilled half in progress.

Rain has actually delayed this phase of the project but it also helped in solidifying the backfilling.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 2:32pm On Jul 10, 2018
Laying of the damp proof membrane (DPM) on the compacted backfilling.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 5:02pm On Jul 11, 2018
Laying of the german floor mat reinforcements, all set for casting but we have to hold on and complete the second half backfilling, compacting and reinforcements work.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 5:13pm On Jul 13, 2018
200 tons of backfilling dumped and filled and just a little more to go. We definitely need another 20 tons and we should be able to call it a wrap.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 4:32am On Jul 14, 2018
Aerial pictures of the german floor reinforcement mat work. Shot by BITSWORKS-1.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 6:14am On Jul 17, 2018
Backfilling almost complete, just a tiny bit more. After 220 tons, it looks like the trenches is swallowing the backfill. We will require just another 10 tons which we won't use up.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 6:26pm On Jul 19, 2018
Backfilling task accomplished at last. We used a total of 230 tons laterite sand to backfill.

It was a slow process due to the incessant rain that affected the dump trucks loading and also the backfilling work.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 4:51pm On Jul 20, 2018
Compacting of the backfilling ongoing. We initially planned to cast the german floor Thursday/Friday but I was not too pleased with the compacting done and told them to leave it for a day or two to get the rain to fall on it. That way, the backfilling compacts better and we top it off.

Casting of the german floor is shifted to next week, we should be able to lay the DPM and reinforcements mat tomorrow, Saturday.

1 Like

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 2:08pm On Jul 23, 2018
Backfilling, compacting, DPM laying and reinforcements mat concluded.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 3:17pm On Jul 23, 2018
Casting of the german floor in progress.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 4:40pm On Jul 23, 2018
Still ongoing.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by seunben(m): 7:34pm On Jul 23, 2018
keep the flag flying. pls update us on the quantities of material use for the german floor.
Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 1:51am On Jul 24, 2018
Front half of the german floor casting completed.

Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS: 10:07pm On Jul 25, 2018
seunben:
keep the flag flying. pls update us on the quantities of material use for the german floor.

Thank you. For the material, we did a bulk purchase of most of the materials used but I will try and do a breakdown based on usage
1. Granite - We purchased 30 tons and probably used close to 20 tons for the short pillars and german floor
2. Sharp sand - We purchased 20 tons and used it up, what's left is just little.
3. Cement - We used 82 bags using a mix ratio of 1:2:4

(1) (2) (3) (4) (5) (Reply)

THE HALLEYVINE RESIDENCE, SANGOTEDO, WITH LUXURIOUS HOUSES YET AFFORDABLE! / Three Bedroom And Two Bedroom Bungalow Development In Alakuko Area / Painting Of A Nairalander's 5 Bedroom Duplex at Iyana Ipaja Lagos.

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)