FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS - Properties - Nairaland

Nairaland Forum / Nairaland / General / Properties / FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS (15411 Views)

Fire Guts One-storey Building In Lagos State (video) / Residential Building Construction Mistakes In Nigeria You Need To Avoid / One Storey Building Of 4units Of 3bedroom For Sale In Coker Village Lagos (2) (3) (4)

(1) (2) (3) (4) (5) (6) (7) (8) (Reply) (Go Down)

FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(m): 4:34am On Jul 30, 2018
Hello good people of Nairalander.

Start date is 14th July 2018...

As a show of confidence in what we do. I have decided to bring to you my latest ongoing construction � work happening now in PHC Rivers State. Having battled with rain. I have come to bring to your notice that this construction has a 1 month time frame to Roofing from foundation to Decking. I don't base in PH I base in Lagos so I am sticking to the time.

Demolition of existing structure and rebuilding is all embedded in this one month take note. I designed the architectural design of this structure and am still the one building it. This is actually my 5th project this year running.

What am building is no blocks. Mainly structural works to Roofing... After one month we can add blocks to the upper floor...

Sit back and relax and I share a bit of the construction images. Contact me for your designs and construction services on +2347038166370, +2348081465833

1 Like

Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(m): 4:41am On Jul 30, 2018
This is the 3D Design of what we are doing

Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(m): 4:44am On Jul 30, 2018
This is the interior Design too. Done by me too...
It comprises of male and female saloon and a two bedroom flat on top. Land size is 10m x 6.6m

Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Nobody: 4:49am On Jul 30, 2018
Looking good.

I have no confidence in the timetable but I wait to be pleasantly surprised.

2 Likes

Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(m): 4:49am On Jul 30, 2018
More construction images

1 Like

Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by uwemjack(m): 2:10pm On Jul 30, 2018
[quote author=Dennis3D post=69819575][/quote]

State the start and finish date

1 Like 1 Share

Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(m): 3:39pm On Jul 30, 2018
We have done the carpentry work on decking as at July 23th to 27th And iron bending simultaneously. Taking it to 28th July

Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(m): 3:54pm On Jul 30, 2018
And we casted the staircase first to enable us do the decking...

1 Like 2 Shares

Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(m): 3:58pm On Jul 30, 2018
And we now casted the decking yesterday 29th July 2018. On a Sunday. Casting started by 8:00am and ended around 7:30pm

1 Like

Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(m): 4:03pm On Jul 30, 2018
And today 30th I climbed and wet the decking. Everything came out very well. We would allow it to rest for some days before I commends the structural upper floor pillars and lintel to roof beam...

Check out the decking looks...

Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(m): 4:12pm On Jul 30, 2018
More Reconstruction photos from the site before now

Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(m): 4:14pm On Jul 30, 2018
uwemjack:


State the start and finish date

See dates now
Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by uwemjack(m): 7:50pm On Jul 30, 2018
Dennis3D:


See dates now

Why didn't you construct a "mallam step"
Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Nobody: 7:54pm On Jul 30, 2018
uwemjack:


Why didn't you construct a "mallam step"

I actually salute him for not doing this. This is part of wastefulness that’s rampant in Nigerian builds as I discussed with AbdulWastecx a few weeks ago.

3 Likes 2 Shares

Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by uwemjack(m): 8:25pm On Jul 30, 2018
EgunMogaji:


I actually salute him for not doing this. This is part of wastefulness that’s rampant in Nigerian builds as I discussed with AbdulWastecx a few weeks ago.


Time and cost on a scale.
The mallam step though additional cost will save him 2days plus, considering he has a time constraint of 30day.
Also he will pay more in terms of Labour to cast the upper floor in two days, whereas they could be done in a day.
In the long run what you think you are saving by not using a "mallam step" for a project of this nature, you loose in time.

Let's do the maths
1. Cost of mallam step: materials and Labour = 22k
2. Cost of not using a mallam step - Labour to cast steps only = 10k + cost of additional 2day staying in an hotel and feeding and logistics= over 22k

Emphasis on this project considering the variables

3 Likes 1 Share

Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Rubbiish(m): 8:26pm On Jul 30, 2018
Dennis3D:
And we casted the staircase first to enable us do the decking...
Hmmm....U mean u casted the staircase as means to the deck?
Was the staircase given enough time to garner strength before receiving movement from floaters...What happened to mallam stair?

2 Likes 1 Share

Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Nobody: 8:42pm On Jul 30, 2018
uwemjack:



Time and cost on a scale.
The mallam step though additional cost will save him 2days plus, considering he has a time constraint of 30day.
Also he will pay more in terms of Labour to cast the upper floor in two days, whereas they could be done in a day.
In the long run what you think you are saving by not using a "mallam step" for a project of this nature, you loose in time.

Let's do the maths
1. Cost of mallam step: materials and Labour = 22k
2. Cost of not using a mallam step - Labour to cast steps only = 10k + cost of additional 2day staying in an hotel and feeding and logistics= over 22k

Emphasis on this project considering the variables

Here’s is the Achilles heels to your eloquent argument.

Is he going to cast the steps eventually?

As a client I’m saving money on materials = wood.

As a contractor I’m adding to my bottom line = efficiency. No rework.

Emphasis on the project to me is a well built structure. A timely built structure that wastes resources is not ideal.

A good contractor should be able to frame and pour a flight of stairs in a day. With the right concrete mixture and support it is ready for use immediately so zero time loss.

I’m still keeping an open mind to garner knowledge.

2 Likes

Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by uwemjack(m): 9:14pm On Jul 30, 2018
EgunMogaji:


Here’s is the Achilles heels to your eloquent argument.

Is he going to cast the steps eventually? [/b] if he installs a "mallam step" both will be casted on the same day[b]

As a client I’m saving money on materials = wood. [/b]you loose time and the contractor money[b]

As a contractor I’m adding to my bottom line = efficiency. No rework. rework is as a result of poor workmanship or supervision

Emphasis on the project to me is a well built structure. A timely built structure that wastes resources is not ideal. time, quality and cost

A good contractor should be able to frame and pour a flight of stairs in a day. With the right concrete mixture and support it is ready for use immediately so zero you will have to use a more expensive cement = more money, even at that not advisable to start walking up and down with loads of concrete. It will stress the concrete and you don't want that on a structural member time loss.

I’m still keeping an open mind to garner knowledge.
Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(m): 4:52am On Jul 31, 2018
uwemjack:



Time and cost on a scale.
The mallam step though additional cost will save him 2days plus, considering he has a time constraint of 30day.
Also he will pay more in terms of Labour to cast the upper floor in two days, whereas they could be done in a day.
In the long run what you think you are saving by not using a "mallam step" for a project of this nature, you loose in time.

Let's do the maths
1. Cost of mallam step: materials and Labour = 22k
2. Cost of not using a mallam step - Labour to cast steps only = 10k + cost of additional 2day staying in an hotel and feeding and logistics= over 22k

Emphasis on this project considering the variables

You said it all. Also what was a major constraint is space. All my 4 other projects this year has Malam steps. But they aren't built up environment like this one.

Also looking at time and cost. This method in fact rocks. Can't you see how neat the staircase looks
Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(m): 4:53am On Jul 31, 2018
Rubbiish:

Hmmm....U mean u casted the staircase as means to the deck?
Was the staircase given enough time to garner strength before receiving movement from floaters...What happened to mallam stair?

Yes it was. You can see the looks even after it's use
Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(m): 4:56am On Jul 31, 2018
EgunMogaji:


Here’s is the Achilles heels to your eloquent argument.

Is he going to cast the steps eventually?

As a client I’m saving money on materials = wood.

As a contractor I’m adding to my bottom line = efficiency. No rework.

Emphasis on the project to me is a well built structure. A timely built structure that wastes resources is not ideal.

A good contractor should be able to frame and pour a flight of stairs in a day. With the right concrete mixture and support it is ready for use immediately so zero time loss.

I’m still keeping an open mind to garner knowledge.

With my time frame. Am using a very good mixture of grade 15 and 20 concrete. That way am good to go.

Remember this is my 5th project this year and in fact my busiest year as far as building and construction is concerned and so much experience is already gathered.

1 Like 1 Share

Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(m): 4:58am On Jul 31, 2018
Let me show my other projects this year where I have used mallam step...

Picture 1 - Lakowe Ajah Lagos
Picture 2 - Owerri Imo State
Picture 3 - Owerri Imo State
Picture 4 - Oke Aro Ogun State

1 Like

Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(m): 5:12am On Jul 31, 2018
I totally understand the concepts of Mallam Step and why it should be used. Believe me. In locations like Owerri. I had that experience of people not using Mallam step. You know what they say when they were seeing me construct mallam step.

"It's a waste of money and material, in fact it makes them easier for them to cast the decking". The further said that it's stressful to climb mallam step especially if it's too steep by the Carpenter and so many other excuses.

But I was wondering in the first place because I haven't done it before (casting staircase first) but have seen it done. So I decided to do this here, having a very deep knowledge of the mixture to use after all research and consultations and wide experience in the use of concrete structures this year. And believe me. See how neat this staircase is. In fact the neatest I have done so far.

1 Like 2 Shares

Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Nobody: 5:15am On Jul 31, 2018
Dennis3D:


With my time frame. Am using a very good mixture of grade 15 and 20 concrete. That way am good to go.

Remember this is my 5th project this year and in fact my busiest year as far as building and construction is concerned and so much experience is already gathered.

You have my support for not doing double work on the steps.

What is the oldest build you’ve done and have you returned for inspection?

Thanks for sharing.

2 Likes 1 Share

Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Nobody: 7:36am On Jul 31, 2018
Dennis3D:
This is the 3D Design of what we are doing

Nice design.

Wondering the Material used for this type of facia and soffit. Is it plasterboard?

1 Like

Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(m): 9:08am On Jul 31, 2018
EgunMogaji:


You have my support for not doing double work on the steps.

What is the oldest build you’ve done and have you returned for inspection?

Thanks for sharing.

The oldest I have done personally is 5years now and it's looking so nice. If you don't mind I can share it here too
Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(m): 9:09am On Jul 31, 2018
gordonbarrett:


Nice design.

Wondering the Material used for this type of facia and soffit. Is it plasterboard?

It's called Kalsi Board. POP Water resistant plasterboard can be used too or direct concrete facial casting
Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(m): 9:18am On Jul 31, 2018
EgunMogaji:


You have my support for not doing double work on the steps.

What is the oldest build you’ve done and have you returned for inspection?

Thanks for sharing.

Check this out. Am going to show you guys the computer design before and after construction.

I built this in Ikorodu Lagos State

Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(m): 9:30am On Jul 31, 2018
To portray my points well enough. Am gonna post more of my completed projects here...

This is me also during the construction...

1 Like

Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(m): 9:44am On Jul 31, 2018
This and many more. But I would stop here to focus on the new project that this project is meant for.

Wait for updates today as I put up what am doing today on the saloon. Am doing the layout today after the decking have been left to rest. But the supports are all in place and reinforcements of the bracings...
Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Nobody: 12:30pm On Jul 31, 2018
Dennis3D:


It's called Kalsi Board. POP Water resistant plasterboard can be used too or direct concrete facial casting

Thanks for the information.

Is the Kalsi board cost effective compared to plasterboard, and will it require screeding after installation or just painting? I know it should be cheaper that concrete facia.

1 Like

Re: FASTEST ONE STOREY BUILDING CONSTRUCTION EVER BUILT IN 3 WEEKS & 5 DAYS by Dennis3D(m): 3:02pm On Jul 31, 2018
gordonbarrett:


Thanks for the information.

Is the Kalsi board cost effective compared to plasterboard, and will it require screeding after installation or just painting? I know it should be cheaper that concrete facia.

It's cheaper than concrete casting

(1) (2) (3) (4) (5) (6) (7) (8) (Reply)

Lekki Gardens Welfare Team Re-visit Survivors Of Collapsed Building (photos) / FMBN begins zero equity for housing loan subscribers / Huge Fire Breaks Out In 24-storey London Tower

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 43
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.