Hello, Cornerstone is here to bring to kwara an uncommon plan in Nigeria. Will be updating you starting from this weekend from site visitation to construction works and finishing. In you need more enquire on your building or how much a building will cost you or you need your home well designed and furnished you can reach me on whatsapp 08100452977 or mail; obed.toluwase@gmail.com Happy viewing..... |
Re: Construction Of A 5bedroom Bungalow @kwara by Timtol(m): 6:11am On Sep 05, 2018 |
More update coming.... |
Re: Construction Of A 5bedroom Bungalow @kwara by Timtol(m): 7:22am On Sep 05, 2018 |
The actual plan isnt Nigeria sytle but from elevation looks casual as Niaja building. It's really complex inward(interior) Will update you on the 3ds and construction activities. Thanks. Your views are welcome. |
Re: Construction Of A 5bedroom Bungalow @kwara by Timtol(m): 2:54pm On Sep 09, 2018 |
As the transit looks funny and later got in late,here is our update... On move to site...yesterday
|
Re: Construction Of A 5bedroom Bungalow @kwara by Timtol(m): 3:15pm On Sep 09, 2018 |
more.... 1 Like
|
Re: Construction Of A 5bedroom Bungalow @kwara by Timtol(m): 3:22pm On Sep 09, 2018 |
The client had started moulding the blocks before i was contacted so got the report the water content is high which led to the brittleness of the one i tested. One of the two broken blocks. Needs more sunshine. Some are okay now. Another thousand was justed moulded which is alright. 1 Like
|
Re: Construction Of A 5bedroom Bungalow @kwara by Timtol(m): 3:26pm On Sep 09, 2018 |
As the needed findings and measurement are carried out. The plot is 200ft by 100ft Part of the plot is rocky and part sloppy but generally the soil is hard. 1 Like
|
Re: Construction Of A 5bedroom Bungalow @kwara by Timtol(m): 3:42pm On Sep 09, 2018 |
More.... 1 Like
|
Re: Construction Of A 5bedroom Bungalow @kwara by Timtol(m): 3:57pm On Sep 09, 2018 |
We heard a tipper of gravel yesterday morning for #4,500 by per tonne The plan will have to be modified finally printed and sealed this week hopefully. We plan for 1tonne each of Y10 for rings and Y12 for reinforcement bar. 1 Like |
Re: Construction Of A 5bedroom Bungalow @kwara by Timtol(m): 8:04pm On Sep 09, 2018 |
... |
Re: Construction Of A 5bedroom Bungalow @kwara by NobodyKnows(m): 9:54pm On Sep 09, 2018 |
Timtol:Update? Please kindly share the 3D and budget of the “complex” house 3 Likes |
Re: Construction Of A 5bedroom Bungalow @kwara by Timtol(m): 10:46pm On Sep 09, 2018 |
NobodyKnows:lol...hmmm Not ready yet. Will be uploaded in due time Thanks |
Re: Construction Of A 5bedroom Bungalow @kwara by Timtol(m): 10:46pm On Sep 09, 2018 |
NobodyKnows:lol...hmmm Not ready yet. Will be uploaded in due time Thanks |
Re: Construction Of A 5bedroom Bungalow @kwara by Timtol(m): 9:34pm On Sep 12, 2018 |
Drawings set.
....
|
Re: Construction Of A 5bedroom Bungalow @kwara by Timtol(m): 10:15am On Sep 13, 2018 |
Thanks for following Update shortly the 3D of the building. 1 Like |
Re: Construction Of A 5bedroom Bungalow @kwara by Timtol(m): 8:32pm On Sep 15, 2018 |
Had to visit the site again for further checkings and plans to cut and uproot the trees per the building sitting area. Site Clearance and more The Client want to start and finish ones. Wanted to have 50bags of cements first,rebars and other needed materials before kicking off.
|
Re: Construction Of A 5bedroom Bungalow @kwara by Asquare84(m): 8:42pm On Sep 15, 2018 |
Follow 1 Like |
Re: Construction Of A 5bedroom Bungalow @kwara by Timtol(m): 8:42pm On Sep 15, 2018 |
Timtol:The Simple Exterior building with angles inside Details shortly 1 Like
|
Re: Construction Of A 5bedroom Bungalow @kwara by Timtol(m): 8:50pm On Sep 15, 2018 |
Asquare84:Appreciated! |
Re: Construction Of A 5bedroom Bungalow @kwara by Hajivince(m): 9:16pm On Sep 15, 2018 |
Following 1 Like |
Re: Construction Of A 5bedroom Bungalow @kwara by Timtol(m): 2:18am On Sep 16, 2018 |
Hajivince:Thank u sir for following |
Re: Construction Of A 5bedroom Bungalow @kwara by Timtol(m): 2:20am On Sep 16, 2018 |
NobodyKnows:Now u have it posted |
Re: Construction Of A 5bedroom Bungalow @kwara by Timtol(m): 2:46am On Sep 16, 2018 |
apunanwu626:Now uploaded sir Details soon |
Re: Construction Of A 5bedroom Bungalow @kwara by Timtol(m): 2:55am On Sep 16, 2018 |
Timtol:DETAILS Building area of 376.70Sqm Car porch Visitor wc (open to the porch as demanded by the Client) Large main lounge(the Client is a fan of space) Dining 1 and 2 where the secondly one can almost be termed foyer open to the courtyard but has a double sliding doors Kitchen well spacious with it funny space Store Balcony Guest room ensuit Bedroom 2-4 ensuit Master bedroom ensuit with WIC Lobby Courtyard 1 Like |
Re: Construction Of A 5bedroom Bungalow @kwara by Timtol(m): 7:53pm On Sep 16, 2018 |
More Updates coming Thanks for following |
Re: Construction Of A 5bedroom Bungalow @kwara by Hajivince(m): 7:56pm On Sep 16, 2018 |
Timtol:When are you gonna start Profiling/setting out/excavation? |
Re: Construction Of A 5bedroom Bungalow @kwara by Timtol(m): 10:58pm On Sep 16, 2018 |
Hajivince:All in the client's hand. As he wanted. He said he will get back shortly trying to raise some fund. Thanks for following |
Re: Construction Of A 5bedroom Bungalow @kwara by Smartwave: 3:09pm On Sep 22, 2018 |
Timtol:pls is moulding your own block cheaper and good? |
Re: Construction Of A 5bedroom Bungalow @kwara by Timtol(m): 3:14pm On Sep 22, 2018 |
Smartwave:Yeah! As I earlier stated that the Client had moulded alot of blocks before I was contacted. Per standard the requirement should be 23blocks per cement and well vibrated but for this project the Client did 60blocks per bag which gave me a lot of concern. So find a better way out. Anyway its cheaper. 1 Like |
Re: Construction Of A 5bedroom Bungalow @kwara by Smartwave: 3:48pm On Sep 22, 2018 |
Timtol:please sir, I you then suggesting 'buying"? |
Re: Construction Of A 5bedroom Bungalow @kwara by Timtol(m): 3:52pm On Sep 22, 2018 |
Smartwave:This will actually depend on your budget sir. My view sir |
Architectural Design For Your Dream Home / How To Evict A Tenant In Lagos / Two Bedroom Bungalow Selling Within Estate At Ikorodu For 6.5m
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 21 |